Optimum Tap Position of 400 Kv Transformer in Rajasthan Power System

Parul Mishra, M. Sharma, Tushar Agarwal, Bhavesh Vyas
{"title":"Optimum Tap Position of 400 Kv Transformer in Rajasthan Power System","authors":"Parul Mishra, M. Sharma, Tushar Agarwal, Bhavesh Vyas","doi":"10.1109/WITCONECE48374.2019.9092891","DOIUrl":null,"url":null,"abstract":"This paper presents a case study to control high voltage in power systembychanging tap position of 400/220 kV transformers. Rajasthan power system having four765 kV GSS, twenty-seven 400 kV GSS, One twenty two 220 kV GSS and four fifty two 132 kV GSS is selected to carry out simulation based case study in MiPower software. Simulation model consists of 943 buses including 85 generator buses, 1142 transmission lines and 201 transformers. The continuous grid operations without operational studies and supervision may lead to create problems in power network. Similar problem is raised up in Rajasthan power network the taps of 400/220 kV transformers of 400 kV grid substation is lower than nominal while at some it is higher than nominal. Due to lack of observation thirteen numbers of 400 kV grid sub stations are observed to use higher tap ratios than nominal which results in higher network voltage at 220 kV level. Even the operators reversing the situation by keeping system shunt capacitors off to reduce the high voltage condition. Test network loading is about10500 MW. Case studies are carried out to observe the effect of reduction in transformer tap position of 400/220 kV, over the thirteen 400 kV grid substations. The impact on voltage profile of busses, system losses, financial analysis, loadings of system elements are presented at last.","PeriodicalId":350816,"journal":{"name":"2019 Women Institute of Technology Conference on Electrical and Computer Engineering (WITCON ECE)","volume":"66 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-11-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2019 Women Institute of Technology Conference on Electrical and Computer Engineering (WITCON ECE)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/WITCONECE48374.2019.9092891","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

This paper presents a case study to control high voltage in power systembychanging tap position of 400/220 kV transformers. Rajasthan power system having four765 kV GSS, twenty-seven 400 kV GSS, One twenty two 220 kV GSS and four fifty two 132 kV GSS is selected to carry out simulation based case study in MiPower software. Simulation model consists of 943 buses including 85 generator buses, 1142 transmission lines and 201 transformers. The continuous grid operations without operational studies and supervision may lead to create problems in power network. Similar problem is raised up in Rajasthan power network the taps of 400/220 kV transformers of 400 kV grid substation is lower than nominal while at some it is higher than nominal. Due to lack of observation thirteen numbers of 400 kV grid sub stations are observed to use higher tap ratios than nominal which results in higher network voltage at 220 kV level. Even the operators reversing the situation by keeping system shunt capacitors off to reduce the high voltage condition. Test network loading is about10500 MW. Case studies are carried out to observe the effect of reduction in transformer tap position of 400/220 kV, over the thirteen 400 kV grid substations. The impact on voltage profile of busses, system losses, financial analysis, loadings of system elements are presented at last.
拉贾斯坦邦电力系统400kv变压器的最佳分接位置
本文介绍了通过改变400/220千伏变压器分接位置来控制电力系统高压的实例。选取拉贾斯坦邦4台765 kV GSS、27台400 kV GSS、122台220 kV GSS和452台132 kV GSS的电力系统,在MiPower软件中进行了基于仿真的案例研究。仿真模型由943条母线组成,其中发电母线85条,输电线路1142条,变压器201台。电网在没有运行研究和监督的情况下连续运行,可能会给电网带来各种问题。拉贾斯坦邦电网也出现了类似的问题,400千伏电网变电站400/220千伏变压器的抽头低于标称,有的高于标称。由于缺乏观察,观察到13个400千伏电网变电站使用比标称更高的分接比,这导致220千伏水平的网络电压更高。甚至操作人员也通过关闭系统并联电容器来扭转局面,以减少高压情况。测试网络负载约为10500mw。通过对13个400千伏电网变电站400/220千伏变压器分接位置降低的效果进行了实例研究。最后介绍了对母线电压分布、系统损耗、财务分析、系统元件负载的影响。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信