Assessment of yearly available days for wind turbine installation in the western sea of Taiwan

Hsiang‐Chih Chan, Meng Chang, Ai-Tsz Liu, C. Chung, C. H. Cheng, F. Chiu
{"title":"Assessment of yearly available days for wind turbine installation in the western sea of Taiwan","authors":"Hsiang‐Chih Chan, Meng Chang, Ai-Tsz Liu, C. Chung, C. H. Cheng, F. Chiu","doi":"10.1109/UT.2013.6519875","DOIUrl":null,"url":null,"abstract":"Offshore wind farm is a renewable energy that has been commercially operated in Europe over 3.8 GW capacities in 2011 and will be targeted upon 150 GW in 2030. Taiwan also plans to install 3 GW offshore wind farms in 2030. Thus, a number of condition assessments and engineering designs are being studied, such as the site selection, the wind turbines layout, the environmental impact assessment, the maritime engineering, the installation and maintenance fleets. In this paper, we carried out the winds and waves as the critical conditions of sea status for the installation of offshore wind turbines. The winds and waves data were collected by a data buoy which was deployed near the entrance of Taichung Harbor. The wind speeds were measured at 15 m above the sea surface. In the case study, we assumed a jack-up vessel will be used for installation of wind turbines. Then, some benchmarking conditions are filled into the assessment. For example, the conditions for operated criteria were suggested as wind speeds below 15 m/s and significant wave heights below 1.5 m in a water depth of 30 m. Moreover, a continuous working duration is considered as 15 hours for installation of a wind turbine from a tower, a nacelle, and blades. Eventually, the yearly available days for the wind turbine installation were assessed about 175 days. Different working modes, such as piling, cable laying, and maintenance, were discussed those yearly available days as well. From the operation and maintenance (O&M) supporting vessels working days (260 days), an offshore wind farm owned 50 wind turbines and each needs maintenance of 260 hours every year that was a benchmark scenario. The supporting vessels require 6 at least that had been estimated.","PeriodicalId":354995,"journal":{"name":"2013 IEEE International Underwater Technology Symposium (UT)","volume":"6 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2013-03-05","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2013 IEEE International Underwater Technology Symposium (UT)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/UT.2013.6519875","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

Offshore wind farm is a renewable energy that has been commercially operated in Europe over 3.8 GW capacities in 2011 and will be targeted upon 150 GW in 2030. Taiwan also plans to install 3 GW offshore wind farms in 2030. Thus, a number of condition assessments and engineering designs are being studied, such as the site selection, the wind turbines layout, the environmental impact assessment, the maritime engineering, the installation and maintenance fleets. In this paper, we carried out the winds and waves as the critical conditions of sea status for the installation of offshore wind turbines. The winds and waves data were collected by a data buoy which was deployed near the entrance of Taichung Harbor. The wind speeds were measured at 15 m above the sea surface. In the case study, we assumed a jack-up vessel will be used for installation of wind turbines. Then, some benchmarking conditions are filled into the assessment. For example, the conditions for operated criteria were suggested as wind speeds below 15 m/s and significant wave heights below 1.5 m in a water depth of 30 m. Moreover, a continuous working duration is considered as 15 hours for installation of a wind turbine from a tower, a nacelle, and blades. Eventually, the yearly available days for the wind turbine installation were assessed about 175 days. Different working modes, such as piling, cable laying, and maintenance, were discussed those yearly available days as well. From the operation and maintenance (O&M) supporting vessels working days (260 days), an offshore wind farm owned 50 wind turbines and each needs maintenance of 260 hours every year that was a benchmark scenario. The supporting vessels require 6 at least that had been estimated.
台湾西海风力发电机安装年度可用日数评估
海上风电场是一种可再生能源,2011年在欧洲商业化运营的容量超过3.8吉瓦,到2030年将达到150吉瓦。台湾还计划在2030年安装3千兆瓦的海上风力发电场。因此,正在研究一些条件评估和工程设计,例如选址、风力涡轮机布局、环境影响评估、海事工程、安装和维护船队。在本文中,我们进行了风浪作为海上风力发电机安装的临界海况条件。风浪资料由台中港入口附近的数据浮标收集。风速是在海面以上15米处测量的。在案例研究中,我们假设一艘自升式船将用于安装风力涡轮机。然后,在评估中填写一些基准条件。例如,在水深为30 m的条件下,风速低于15 m/s,有效波高低于1.5 m。此外,从塔架、机舱和叶片安装风力发电机,连续工作时间为15小时。最终,每年可用于安装风力涡轮机的天数被评估为175天。讨论了不同的工作模式,如打桩,电缆敷设和维护,每年的可用天数。从运行和维护(O&M)支持船只的工作日(260天)来看,一个海上风电场拥有50台风力涡轮机,每台涡轮机每年需要维护260小时,这是一个基准情景。支持船只至少需要6艘,这是估计的。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信