Building Marine Infrastructure for Science

P. Phibbs
{"title":"Building Marine Infrastructure for Science","authors":"P. Phibbs","doi":"10.1109/OCEANS.2008.5152079","DOIUrl":null,"url":null,"abstract":"The NEPTUNE Canada cabled ocean observatory is a Canadian funded undersea utility whose sole purpose is to support research into the ocean depths. With 800 km of subsea cable, and five science sites with 10 kW power and 4 Gb/sec data transmission at each, it will represent the first of a new generation of cabled subsea observatories. In many ways NEPTUNE Canada matches the utilities all of us use every day in that it supplies electricity and \"telephone lines\" to customers' places of business. Both terrestrial and subsea utilities require major effort by specialised manufacturers and installers to build the infrastructure, and a knowledgeable management and engineering team to create specific requirements, protect the owner's interests during construction and manage the manufacturers and installers. However the management of the development and construction of undersea utilities for science differs significantly from the development and construction of more conventional utilities such as electrical grids and telephone networks. First and foremost, working in the marine environment versus on land changes the risk profile entirely. Whereas a failed piece of equipment in a terrestrial network may require two technicians and a cube van to drive out to a remote site, failures subsea will require months of planning, mobilization of ROVs and ships, as well as significant expenditures of money, effort and customer goodwill. Therefore for an undersea system to be economical and successful through its working life, a significant portion of the funding has to be spent on ensuring long term reliability of the subsea plant prior to installation. Secondly, NEPTUNE Canada is a utility dedicated to scientific use. The design of NEPTUNE Canada is driven jointly by the needs of scientists, funding issues and limits, and assessment of the current capabilities of the technologies. Terrestrial utility design is driven by commercial or regulatory requirements, which can usually be defined and fixed early in the project, so that requirements and specifications can be set prior to contract award. However some of the NEPTUNE Canada requirements have been deliberately kept flexible well into the development cycle, to allow accommodation of the scientists needs as those needs develop. This flexibility adds significantly to the challenge of risk identification and management. Thirdly, at the start of the NEPTUNE Canada project, no technology existed that could meet the scientist's requirements. Whereas terrestrial utilities tend to be a further step along a continuum of development, NEPTUNE Canada stepped boldly into an untried area. Managing this development risk with a capped budget would not have been possible without the support of the NEPTUNE Canada prime contractor, Alcatel Submarine Networks (ASN), a division of Alcatel-Lucent. The experience ASN brought from the submarine cable industry, plus its unmatched research and development engineering capabilities, have enabled NEPTUNE Canada to pursue the scientists' initial concept of high power and high bandwidth communications delivery to and from the deep ocean. This paper will use the experiences gained so far in the funding, development, manufacture and installation of the world's first multipurpose deepwater cabled ocean observatory to consider how useful the models of terrestrial power and communications utilities are when planning scientific utilities and infrastructure such as NEPTUNE Canada. It will discuss the challenges of managing the sometimes disparate interests and expectations of the groups and institutions involved. And it will identify some of the pitfalls that need to be avoided by anyone trying to build these types of infrastructure.","PeriodicalId":113677,"journal":{"name":"OCEANS 2008","volume":"9 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2008-09-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"OCEANS 2008","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/OCEANS.2008.5152079","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

The NEPTUNE Canada cabled ocean observatory is a Canadian funded undersea utility whose sole purpose is to support research into the ocean depths. With 800 km of subsea cable, and five science sites with 10 kW power and 4 Gb/sec data transmission at each, it will represent the first of a new generation of cabled subsea observatories. In many ways NEPTUNE Canada matches the utilities all of us use every day in that it supplies electricity and "telephone lines" to customers' places of business. Both terrestrial and subsea utilities require major effort by specialised manufacturers and installers to build the infrastructure, and a knowledgeable management and engineering team to create specific requirements, protect the owner's interests during construction and manage the manufacturers and installers. However the management of the development and construction of undersea utilities for science differs significantly from the development and construction of more conventional utilities such as electrical grids and telephone networks. First and foremost, working in the marine environment versus on land changes the risk profile entirely. Whereas a failed piece of equipment in a terrestrial network may require two technicians and a cube van to drive out to a remote site, failures subsea will require months of planning, mobilization of ROVs and ships, as well as significant expenditures of money, effort and customer goodwill. Therefore for an undersea system to be economical and successful through its working life, a significant portion of the funding has to be spent on ensuring long term reliability of the subsea plant prior to installation. Secondly, NEPTUNE Canada is a utility dedicated to scientific use. The design of NEPTUNE Canada is driven jointly by the needs of scientists, funding issues and limits, and assessment of the current capabilities of the technologies. Terrestrial utility design is driven by commercial or regulatory requirements, which can usually be defined and fixed early in the project, so that requirements and specifications can be set prior to contract award. However some of the NEPTUNE Canada requirements have been deliberately kept flexible well into the development cycle, to allow accommodation of the scientists needs as those needs develop. This flexibility adds significantly to the challenge of risk identification and management. Thirdly, at the start of the NEPTUNE Canada project, no technology existed that could meet the scientist's requirements. Whereas terrestrial utilities tend to be a further step along a continuum of development, NEPTUNE Canada stepped boldly into an untried area. Managing this development risk with a capped budget would not have been possible without the support of the NEPTUNE Canada prime contractor, Alcatel Submarine Networks (ASN), a division of Alcatel-Lucent. The experience ASN brought from the submarine cable industry, plus its unmatched research and development engineering capabilities, have enabled NEPTUNE Canada to pursue the scientists' initial concept of high power and high bandwidth communications delivery to and from the deep ocean. This paper will use the experiences gained so far in the funding, development, manufacture and installation of the world's first multipurpose deepwater cabled ocean observatory to consider how useful the models of terrestrial power and communications utilities are when planning scientific utilities and infrastructure such as NEPTUNE Canada. It will discuss the challenges of managing the sometimes disparate interests and expectations of the groups and institutions involved. And it will identify some of the pitfalls that need to be avoided by anyone trying to build these types of infrastructure.
建设海洋科学基础设施
NEPTUNE加拿大电缆海洋观测站是加拿大资助的海底公用事业,其唯一目的是支持对海洋深处的研究。拥有800公里的海底电缆,五个科学站点,每个站点具有10千瓦的功率和4gb /秒的数据传输,它将成为新一代海底电缆观测站的第一个。在许多方面,海王星加拿大公司与我们所有人每天使用的公用事业相匹配,因为它为客户的营业场所提供电力和“电话线”。无论是陆地还是海底设施,都需要专业的制造商和安装人员付出巨大的努力来建造基础设施,并且需要一个知识渊博的管理和工程团队来创建特定的要求,在施工期间保护业主的利益,并管理制造商和安装人员。然而,海底科学设施的开发和建设的管理与更传统的设施(如电网和电话网络)的开发和建设有很大不同。首先,与陆地相比,在海洋环境中工作完全改变了风险状况。地面网络中出现故障的设备可能需要两名技术人员和一辆立方体货车开到远程站点,而海底故障则需要数月的规划、rov和船舶的动员,以及大量的资金、精力和客户信誉支出。因此,为了使海底系统在其使用寿命内经济且成功,必须在安装之前将很大一部分资金用于确保海底设备的长期可靠性。其次,NEPTUNE加拿大是一个专门用于科学用途的公用事业。加拿大NEPTUNE的设计是由科学家的需求、资金问题和限制以及对当前技术能力的评估共同推动的。地面公用设施设计是由商业或监管需求驱动的,这些需求通常可以在项目早期定义和固定,因此需求和规范可以在合同授予之前设置。然而,加拿大NEPTUNE的一些要求在开发周期中故意保持灵活,以便在这些需求发展时能够满足科学家的需求。这种灵活性大大增加了风险识别和管理的挑战。第三,在加拿大海王星项目开始时,没有任何技术可以满足科学家的要求。鉴于地面公用事业往往是发展连续体的进一步步骤,加拿大NEPTUNE大胆地进入了一个未经尝试的领域。如果没有NEPTUNE加拿大公司的主承包商阿尔卡特-朗讯公司下属的阿尔卡特海底网络公司(ASN)的支持,在预算上限的情况下管理这一开发风险是不可能的。ASN从海底电缆行业带来的经验,加上其无与伦比的研究和开发工程能力,使NEPTUNE Canada能够实现科学家们最初的大功率和高带宽通信传输到深海的概念。本文将利用迄今为止在世界上第一个多用途深水电缆海洋观测站的资助、开发、制造和安装方面获得的经验,考虑地面电力和通信公用事业模型在规划科学公用事业和基础设施(如NEPTUNE Canada)时的有用性。它将讨论管理所涉及的群体和机构有时不同的利益和期望的挑战。它还将指出任何试图构建这类基础设施的人都需要避免的一些陷阱。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信