A Bayesian Critical Path Method for Managing Common Risks in Software Project Scheduling

Ngoc-Tuan Nguyen, H. Thang, Thi-Huong-Giang Vu
{"title":"A Bayesian Critical Path Method for Managing Common Risks in Software Project Scheduling","authors":"Ngoc-Tuan Nguyen, H. Thang, Thi-Huong-Giang Vu","doi":"10.1145/3287921.3287962","DOIUrl":null,"url":null,"abstract":"Although project managers nowadays can use a range of tools and techniques to develop, monitor and control project schedules, the task of creating project schedules is often very difficult since it has to deal with planning against uncertainty. Popular techniques for project scheduling based on the assumption that projects are carried out as planned or scheduled -- which hardly happens. This paper takes the advantage of Bayesian Networks in modeling uncertainty and incorporates them in Critical Path Method - one of the most popular means of monitoring project scheduling. The paper also examines common risk factors in project scheduling and proposes a model of 19 common risk factors. A tool was also built, and experiments were carried out to validate the model.","PeriodicalId":448008,"journal":{"name":"Proceedings of the 9th International Symposium on Information and Communication Technology","volume":"617 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2018-12-06","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"10","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of the 9th International Symposium on Information and Communication Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1145/3287921.3287962","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 10

Abstract

Although project managers nowadays can use a range of tools and techniques to develop, monitor and control project schedules, the task of creating project schedules is often very difficult since it has to deal with planning against uncertainty. Popular techniques for project scheduling based on the assumption that projects are carried out as planned or scheduled -- which hardly happens. This paper takes the advantage of Bayesian Networks in modeling uncertainty and incorporates them in Critical Path Method - one of the most popular means of monitoring project scheduling. The paper also examines common risk factors in project scheduling and proposes a model of 19 common risk factors. A tool was also built, and experiments were carried out to validate the model.
软件项目调度中常见风险管理的贝叶斯关键路径方法
尽管现在的项目经理可以使用一系列工具和技术来开发、监视和控制项目进度,但是创建项目进度的任务通常是非常困难的,因为它必须处理针对不确定性的计划。流行的项目调度技术基于项目按照计划或计划执行的假设——这几乎不可能发生。本文利用贝叶斯网络在不确定性建模方面的优势,并将其纳入关键路径法——一种最常用的项目进度监控方法。本文还研究了项目进度中的常见风险因素,并提出了一个包含19个常见风险因素的模型。建立了工具,并进行了实验验证。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信