{"title":"MILP model for the planning of a Computerized Numerical Control Lathes Machining Plant","authors":"M. Galli, Federico Kañevsky, M. A. Franco","doi":"10.19153/cleiej.24.2.4","DOIUrl":null,"url":null,"abstract":"This work introduces the formulation and application of a MILP model to solve the problem of planning the weekly production of a machining plant using numerical control lathes to manufacture spare parts for agricultural machines. The machining plant works under a Flexible Job Shop system and it has reduced workforce with different skills to operate the various high-complexity lathes and to carry out setup operations in each machine. The developed model is based on a basic formulation for the classic problem and we introduce some flexible adjustment for the various situations that may arise from different scheduling problems. The model is applied to various scenarios; and we include a discussion of the improvements brought about by the analysis.","PeriodicalId":418941,"journal":{"name":"CLEI Electron. J.","volume":"40 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2021-07-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"CLEI Electron. J.","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.19153/cleiej.24.2.4","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
This work introduces the formulation and application of a MILP model to solve the problem of planning the weekly production of a machining plant using numerical control lathes to manufacture spare parts for agricultural machines. The machining plant works under a Flexible Job Shop system and it has reduced workforce with different skills to operate the various high-complexity lathes and to carry out setup operations in each machine. The developed model is based on a basic formulation for the classic problem and we introduce some flexible adjustment for the various situations that may arise from different scheduling problems. The model is applied to various scenarios; and we include a discussion of the improvements brought about by the analysis.