Study on Cost and Schedule Control in Warship Planned Maintenance

Xie Li, W. Xiang, Chen Chuan
{"title":"Study on Cost and Schedule Control in Warship Planned Maintenance","authors":"Xie Li, W. Xiang, Chen Chuan","doi":"10.1109/ICRMEM.2008.29","DOIUrl":null,"url":null,"abstract":"The earned value measure is introduced into the cost and schedule control of warship planned maintenance for the over budget and schedule delays problem. The flowchart and application range of earned value measure is summarized. The application procedure of the earned value measure in the cost and schedule control of warship planned maintenance is given. Then the over budget and schedule delays are analyzed quantitatively in repair of some type warship. For different instance, the concrete forecast methods of cost at completion are put forward in the date of examine, which finally proved that the application of the earned value measure in the cost and schedule control of warship maintenance is feasible and valid.","PeriodicalId":430801,"journal":{"name":"2008 International Conference on Risk Management & Engineering Management","volume":"16 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2008-11-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2008 International Conference on Risk Management & Engineering Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICRMEM.2008.29","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

Abstract

The earned value measure is introduced into the cost and schedule control of warship planned maintenance for the over budget and schedule delays problem. The flowchart and application range of earned value measure is summarized. The application procedure of the earned value measure in the cost and schedule control of warship planned maintenance is given. Then the over budget and schedule delays are analyzed quantitatively in repair of some type warship. For different instance, the concrete forecast methods of cost at completion are put forward in the date of examine, which finally proved that the application of the earned value measure in the cost and schedule control of warship maintenance is feasible and valid.
舰船计划维修成本与进度控制研究
针对舰船计划维修存在的预算超支和工期延误问题,将挣值度量引入到计划维修的成本和进度控制中。总结了挣值度量的工作流程和应用范围。给出了挣值度量在舰船计划维修成本和进度控制中的应用步骤。然后定量分析了某型军舰维修中出现的预算超支和工期延误问题。针对不同的实例,提出了完工成本的具体预测方法,最终证明了挣值度量在舰船维修成本和进度控制中的应用是可行和有效的。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信