Research on the operating process of DC De-icer and its De-icing efficiency in China Southern Power Grid

Yanzhou Chen, Qi Wang, Baoquan Gu, Yanlei Cai, F. Wen
{"title":"Research on the operating process of DC De-icer and its De-icing efficiency in China Southern Power Grid","authors":"Yanzhou Chen, Qi Wang, Baoquan Gu, Yanlei Cai, F. Wen","doi":"10.1109/ASSCC.2012.6523333","DOIUrl":null,"url":null,"abstract":"The China Southern Power Grid (CSG) has installed 6 sets of DC-deicer on its backbone transmission grid since the ice disaster in 2008, among which the DC-deicer in Gaopo substation of Gao-Zhao ±500kV DC transmission lines is the first OPGW deicer in CSG. Most of the existing DC-deicing research work concerns on the analyzing of transmission lines without considering the installation of de-icing switches. However, the icing problem of overhead ground lines has become the secondary influencing factor in the causation of power system fault during winter. Given this background, the general situation of the 6 sets of DC de-icer is presented and the de-icing operating process and its efficiency after the installation of de-icing switches are studied. Finally, suggestions are given on basis of the research.","PeriodicalId":341348,"journal":{"name":"2012 10th International Power & Energy Conference (IPEC)","volume":"100 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2012-11-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2012 10th International Power & Energy Conference (IPEC)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ASSCC.2012.6523333","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

The China Southern Power Grid (CSG) has installed 6 sets of DC-deicer on its backbone transmission grid since the ice disaster in 2008, among which the DC-deicer in Gaopo substation of Gao-Zhao ±500kV DC transmission lines is the first OPGW deicer in CSG. Most of the existing DC-deicing research work concerns on the analyzing of transmission lines without considering the installation of de-icing switches. However, the icing problem of overhead ground lines has become the secondary influencing factor in the causation of power system fault during winter. Given this background, the general situation of the 6 sets of DC de-icer is presented and the de-icing operating process and its efficiency after the installation of de-icing switches are studied. Finally, suggestions are given on basis of the research.
南方电网直流除冰器运行过程及除冰效率研究
自2008年冰灾以来,南方电网在其骨干输电网安装了6套直流除冰装置,其中高赵±500kV直流输电线路高坡变电站的直流除冰装置是南方电网首台OPGW除冰装置。现有的直流除冰研究工作大多是对输电线路的分析,而没有考虑除冰开关的安装。然而,架空地线结冰问题已成为冬季电力系统故障的次要影响因素。在此背景下,介绍了6台直流除冰器的概况,并对安装除冰开关后的除冰运行过程及其效率进行了研究。最后,在研究的基础上提出了建议。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信