Surge Peak Pressure Magnitude Impact due to Vapour Formation and Collapse: Simulation Study, Mitigation and Testing

Aqeela Hani Alwi, Nicholas Philip
{"title":"Surge Peak Pressure Magnitude Impact due to Vapour Formation and Collapse: Simulation Study, Mitigation and Testing","authors":"Aqeela Hani Alwi, Nicholas Philip","doi":"10.2523/IPTC-19231-MS","DOIUrl":null,"url":null,"abstract":"\n A surge study was conducted for the addition of a new LNG storage tank in PETRONAS Malaysia LNG in Bintulu, Sarawak. With the new LNG storage tank being the largest, furthest, highest elevation and with the biggest LNG loading pump capacity, a thorough surge study is essential to ensure safe operations of the existing loading lines network.\n During emergency situations, Emergency Shutdown (ESD) system may be activated where the ESD valves will be closed within 15 seconds to return the loading lines network into safe conditions. However, with the rapid closure of ESD valves, there is a sudden velocity change to the LNG liquid in the loading lines. This results in a vapour formation and collapse phenomenon which causes a surge pressure peak and resultant transient force onto the piping.\n The surge study started with a simulation study, where it was found that the initial surge pressure may surpass the loading lines piping design pressure. Then, the simulation carries on evaluating the possible mitigation measures that could be applied to the loading lines network to reduce the surge pressure to safe operating limits below the piping design pressure. Once satisfied, an actual ESD test was conducted where the ESD situation is replicated and the actual surge pressure was recorded. This test serves to reaffirm the simulation study and possibly quantify the magnitude of surge pressure experienced in real ESD situations.\n The mitigation measures of a 20 second pump delay timer and kick back valves to open during ESD activation was applied prior to the ESD test. During the test, the surge pressure peaks at approx. 20 barg, which was 4 times the normal loading pressure. This is as expected from the surge simulation considering mitigation measures are applied. If the mitigation measures were not applied, the surge pressure peak may go up to 10x the normal loading pressure, enormously exceeding the loading lines design pressure and may be catastrophic. Additional findings and discussion on the test results are presented in this manuscript.\n In conclusion, the surge pressure magnitude experienced due to sudden velocity change may peak numerous times above the normal pressure even though only for a short time. This situation is applicable to LNG loading lines but is also possibly applicable to other liquid lines with sudden fluid velocity change within the piping. It is important to ensure that the necessary mitigation actions are taken prior to putting the lines into service.","PeriodicalId":105730,"journal":{"name":"Day 2 Wed, March 27, 2019","volume":"85 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-03-22","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Wed, March 27, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2523/IPTC-19231-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

A surge study was conducted for the addition of a new LNG storage tank in PETRONAS Malaysia LNG in Bintulu, Sarawak. With the new LNG storage tank being the largest, furthest, highest elevation and with the biggest LNG loading pump capacity, a thorough surge study is essential to ensure safe operations of the existing loading lines network. During emergency situations, Emergency Shutdown (ESD) system may be activated where the ESD valves will be closed within 15 seconds to return the loading lines network into safe conditions. However, with the rapid closure of ESD valves, there is a sudden velocity change to the LNG liquid in the loading lines. This results in a vapour formation and collapse phenomenon which causes a surge pressure peak and resultant transient force onto the piping. The surge study started with a simulation study, where it was found that the initial surge pressure may surpass the loading lines piping design pressure. Then, the simulation carries on evaluating the possible mitigation measures that could be applied to the loading lines network to reduce the surge pressure to safe operating limits below the piping design pressure. Once satisfied, an actual ESD test was conducted where the ESD situation is replicated and the actual surge pressure was recorded. This test serves to reaffirm the simulation study and possibly quantify the magnitude of surge pressure experienced in real ESD situations. The mitigation measures of a 20 second pump delay timer and kick back valves to open during ESD activation was applied prior to the ESD test. During the test, the surge pressure peaks at approx. 20 barg, which was 4 times the normal loading pressure. This is as expected from the surge simulation considering mitigation measures are applied. If the mitigation measures were not applied, the surge pressure peak may go up to 10x the normal loading pressure, enormously exceeding the loading lines design pressure and may be catastrophic. Additional findings and discussion on the test results are presented in this manuscript. In conclusion, the surge pressure magnitude experienced due to sudden velocity change may peak numerous times above the normal pressure even though only for a short time. This situation is applicable to LNG loading lines but is also possibly applicable to other liquid lines with sudden fluid velocity change within the piping. It is important to ensure that the necessary mitigation actions are taken prior to putting the lines into service.
蒸汽形成和崩塌造成的喘振峰值压力量级影响:模拟研究、缓解和测试
为在沙捞越Bintulu的马来西亚国家石油公司液化天然气公司增加一个新的液化天然气储罐,进行了一项激增研究。由于新的LNG储罐是最大、最远、海拔最高的,并且具有最大的LNG装载泵容量,因此对现有装载线网络的安全运行进行彻底的调压研究至关重要。在紧急情况下,可以启动紧急关闭(ESD)系统,ESD阀将在15秒内关闭,使负载管线网络恢复到安全状态。然而,随着ESD阀门的快速关闭,LNG液体在装载管道中的速度会发生突然变化。这将导致蒸汽的形成和坍塌现象,从而导致浪涌压力峰值和对管道产生的瞬时力。喘振研究从模拟研究开始,发现初始喘振压力可能超过加载管线的管道设计压力。在此基础上,通过仿真对加载线网络可能采取的缓解措施进行了评估,以将喘振压力降低到低于管道设计压力的安全运行极限。一旦满足要求,就进行实际的ESD测试,复制ESD情况并记录实际的喘振压力。该测试有助于验证模拟研究结果,并可能量化在实际ESD情况下所经历的喘振压力的大小。在ESD测试之前,采用了20秒的泵延迟计时器和在ESD激活期间打开的反踢阀等缓解措施。在测试过程中,喘振压力峰值约为。20巴,是正常装载压力的4倍。考虑到采用了缓解措施,这与从浪涌模拟中预期的结果一致。如果不采取缓解措施,浪涌压力峰值可能达到正常加载压力的10倍,大大超过加载线的设计压力,可能造成灾难性后果。附加的发现和讨论的测试结果提出了在这个手稿。综上所述,由于速度的突然变化,即使在很短的时间内,所经历的喘振压力值也可能比正常压力高很多倍。这种情况适用于LNG装载管道,但也可能适用于管道内流体速度突然变化的其他液体管道。重要的是要确保在线路投入使用之前采取必要的缓解行动。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信