Application experience with 69 kV steel utility poles

R. George, L. Stetson
{"title":"Application experience with 69 kV steel utility poles","authors":"R. George, L. Stetson","doi":"10.1109/REPCON.1999.768680","DOIUrl":null,"url":null,"abstract":"In 1997, a 69 kV single pole power line was designed and built by Dawson Public Power District in Central Nebraska using steel poles instead of wood. The power line is 9 miles in length and connects rural distribution substations. The construction also allowed for a voltage upgrade from 34.5 kV to 69 kV. The steel alternative to wood was initially considered as a means of extending the life of conventional southern yellow pine (SYP) poles. A closer examination of the physical characteristics revealed advantages in overall strength, buckling, and bending. The steel poles consisted of galvanized tubular steel, classes 1, 2 and 3, and lengths from 55 ft to 70 ft. The 2 piece tapered poles are slip fit (overlap approx. 24-in) together above ground line. The 12.5 kV underbuild utilizes fiberglass cross arms and standoffs. Conventional pole bands were replaced with guying tees, thimble eyes and eye bolts for both overhead and down guys respectively. The steel pole eliminated the need for the normal TM-9X shield wire ground and reduced framing labor and material cost. The overall result was a stronger and lower initial cost power line. The minimal inconvenience of setting a 2-piece pole was more than offset by the labor saved in transporting and framing. During 1998 grounding tests were conducted on steel poles with and without ground rods. These tests revealed that the steel poles were effectively grounded whether with or without a parallel ground rod. Rock fill around the poles in place of soil did not greatly reduce the grounding resistance to earth.","PeriodicalId":364482,"journal":{"name":"1999 Rural Electric Power Conference (Cat. No. 99CH36302)","volume":"14 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"1999-05-02","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"4","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"1999 Rural Electric Power Conference (Cat. No. 99CH36302)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/REPCON.1999.768680","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 4

Abstract

In 1997, a 69 kV single pole power line was designed and built by Dawson Public Power District in Central Nebraska using steel poles instead of wood. The power line is 9 miles in length and connects rural distribution substations. The construction also allowed for a voltage upgrade from 34.5 kV to 69 kV. The steel alternative to wood was initially considered as a means of extending the life of conventional southern yellow pine (SYP) poles. A closer examination of the physical characteristics revealed advantages in overall strength, buckling, and bending. The steel poles consisted of galvanized tubular steel, classes 1, 2 and 3, and lengths from 55 ft to 70 ft. The 2 piece tapered poles are slip fit (overlap approx. 24-in) together above ground line. The 12.5 kV underbuild utilizes fiberglass cross arms and standoffs. Conventional pole bands were replaced with guying tees, thimble eyes and eye bolts for both overhead and down guys respectively. The steel pole eliminated the need for the normal TM-9X shield wire ground and reduced framing labor and material cost. The overall result was a stronger and lower initial cost power line. The minimal inconvenience of setting a 2-piece pole was more than offset by the labor saved in transporting and framing. During 1998 grounding tests were conducted on steel poles with and without ground rods. These tests revealed that the steel poles were effectively grounded whether with or without a parallel ground rod. Rock fill around the poles in place of soil did not greatly reduce the grounding resistance to earth.
具有69千伏钢电线杆的应用经验
1997年,内布拉斯加州中部的道森公共电力区设计并建造了一条69千伏的单极电力线,使用的是钢杆而不是木头。这条电线长9英里,连接着农村的配电变电站。该建设还允许电压从34.5千伏升级到69千伏。钢材替代木材最初被认为是延长传统南方黄松(SYP)杆寿命的一种手段。对其物理特性的进一步研究揭示了其在整体强度、屈曲和弯曲方面的优势。钢杆由镀锌钢管组成,等级1、2和3,长度从55英尺到70英尺。两件锥形杆是滑动配合(重叠约。24英寸)一起在地面线上。12.5千伏的基础结构采用玻璃纤维交叉臂和支架。传统的杆带分别被顶杆和下杆的三通、顶针和螺栓所取代。钢杆消除了普通TM-9X屏蔽线接地的需要,减少了框架的人工和材料成本。总体结果是一条更强、初始成本更低的电力线。设置2件杆的最小不便被运输和框架节省的劳动力所抵消。1998年,对有接地棒和没有接地棒的钢杆进行了接地试验。这些试验表明,无论是否有平行接地棒,钢杆都能有效接地。在两极周围填石代替土壤并没有大大降低接地对地球的阻力。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信