Successful Delivery of Decommissioning Project via Artificial Reefing Option in Malaysia

M. Z. Sulaiman, M. I. M. Ros, Zainuddin B. Kamarudin, M. R. A. Rahman, Zakaria Kasah, M. H. Yusof
{"title":"Successful Delivery of Decommissioning Project via Artificial Reefing Option in Malaysia","authors":"M. Z. Sulaiman, M. I. M. Ros, Zainuddin B. Kamarudin, M. R. A. Rahman, Zakaria Kasah, M. H. Yusof","doi":"10.2523/IPTC-19554-MS","DOIUrl":null,"url":null,"abstract":"\n This paper will discuss further on the recent decommissioning project of fields which has been completed on November 2017. These two platforms had been totally removed and became an artificial reef at Sarawak water in Malaysia. This paper will show the activities and best practices; the team had gone through from early stage until completion of the process based on the decommissioning phases. The decommissioning framework consists of five phases starting from Late Life Planning and Preparation; Regulatory, Compliance and Permitting; Facilities Hook-down and wells make safe; Removal and Remediation and lastly, Post Remediation. In baseline inspection, the underwater inspection had provided some information to the contractor on the scope and revealed some of the uncertainties about the decommissioning project. On an important note, an engineering study is critical to ensure safe operation. After our observation, we noted that actual operation is similar to the engineering's simulation where the team had to follow the engineering accordingly. Reefing engineering crucially needed to be performed to ensure the facilities been placed at the right location and position. During offshore execution removal of facilities, there were challenges we faced such as malfunction of the cutting/dredge equipment which led to a back up plan and innovative solution. We had to utilize other available equipments available onboard (Diamond wire cutter, abrasive waterjet internal cutter, dredger, soil plug removal, airlift, cutting torch etc.). Selection of cutting tools also needed to be considered to minimize the pinch effect of the facilities. Finally, Post decommissioning survey had been carried during the Post Remediation phase to assess the successful of the project. The post-decommissioning/reefing survey had been carried out and the result observed new marine growth and numbers of fishes at the reefed platform. It had been concluded that this decommissioning reefing project was successful. This paper should be an interest to those who will be exploring abandonment and decommissioning project which includes reefing as one of the decommissioning options. This paper will also show on decommissioning process through Engineering, Preparation, Removal and Disposal (EPRD) approach contract. The novelty in this paper is on the assurance that had been made by Company via baseline and post reefing survey to ensure environment aspect had been considered.","PeriodicalId":105730,"journal":{"name":"Day 2 Wed, March 27, 2019","volume":"39 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-03-22","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Wed, March 27, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2523/IPTC-19554-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

This paper will discuss further on the recent decommissioning project of fields which has been completed on November 2017. These two platforms had been totally removed and became an artificial reef at Sarawak water in Malaysia. This paper will show the activities and best practices; the team had gone through from early stage until completion of the process based on the decommissioning phases. The decommissioning framework consists of five phases starting from Late Life Planning and Preparation; Regulatory, Compliance and Permitting; Facilities Hook-down and wells make safe; Removal and Remediation and lastly, Post Remediation. In baseline inspection, the underwater inspection had provided some information to the contractor on the scope and revealed some of the uncertainties about the decommissioning project. On an important note, an engineering study is critical to ensure safe operation. After our observation, we noted that actual operation is similar to the engineering's simulation where the team had to follow the engineering accordingly. Reefing engineering crucially needed to be performed to ensure the facilities been placed at the right location and position. During offshore execution removal of facilities, there were challenges we faced such as malfunction of the cutting/dredge equipment which led to a back up plan and innovative solution. We had to utilize other available equipments available onboard (Diamond wire cutter, abrasive waterjet internal cutter, dredger, soil plug removal, airlift, cutting torch etc.). Selection of cutting tools also needed to be considered to minimize the pinch effect of the facilities. Finally, Post decommissioning survey had been carried during the Post Remediation phase to assess the successful of the project. The post-decommissioning/reefing survey had been carried out and the result observed new marine growth and numbers of fishes at the reefed platform. It had been concluded that this decommissioning reefing project was successful. This paper should be an interest to those who will be exploring abandonment and decommissioning project which includes reefing as one of the decommissioning options. This paper will also show on decommissioning process through Engineering, Preparation, Removal and Disposal (EPRD) approach contract. The novelty in this paper is on the assurance that had been made by Company via baseline and post reefing survey to ensure environment aspect had been considered.
在马来西亚通过人工珊瑚礁方案成功交付退役项目
本文将进一步讨论最近于2017年11月完成的油田退役项目。这两个平台已被完全拆除,成为马来西亚沙捞越水域的人工礁。本文将展示活动和最佳实践;该团队已经经历了从早期阶段到基于退役阶段的过程的完成。退役框架包括五个阶段,从晚年规划和准备开始;监管、合规和许可;设施吊钩和井确保安全;移除和修复,最后是修复后。在基线检查中,水下检查为承包商提供了一些关于范围的信息,并揭示了退役项目的一些不确定性。重要的是,工程研究对于确保安全运行至关重要。经过我们的观察,我们注意到实际操作与工程模拟类似,团队必须相应地遵循工程。礁化工程至关重要,以确保设施被放置在正确的位置和位置。在海上执行移除设施的过程中,我们面临着一些挑战,例如切割/疏浚设备的故障,这导致了后备计划和创新的解决方案。我们不得不利用船上其他可用的设备(钻石线切割机,磨料水射流内部切割机,挖泥船,土塞清除,空气提升,切割炬等)。切削工具的选择也需要考虑,以尽量减少设备的夹紧效应。最后,在修复后阶段进行了退役后调查,以评估项目的成功。我们进行了退役/珊瑚礁化后的调查,结果发现在珊瑚礁平台上有新的海洋生物生长和鱼类数量。得出的结论是,这个退役珊瑚礁项目是成功的。这篇论文应该是那些将探索废弃和退役项目的人感兴趣的,其中包括珊瑚礁作为退役选择之一。本文还将介绍通过工程、准备、移除和处置(EPRD)方式合同的退役过程。本文的新颖之处在于公司通过基线和礁化后调查做出的保证,以确保考虑了环境因素。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信