{"title":"Anticipation for efficient electricity transmission network investments","authors":"V. Rious, P. Dessante, J. Glachant","doi":"10.1109/INFRA.2008.5439602","DOIUrl":null,"url":null,"abstract":"This paper proposes a model and preliminary results to evaluate the efficiency of anticipating the connection of power plants with shorter construction duration than the time needed to obtain the right to upgrade the network and finally to do this reinforcement. This evaluation is made in presence of a cost of anticipation related to the study of the project of network investment and to the administrative procedures needed to obtain the building agreement. This model compares a proactive TSO that anticipates the connection of new generators and then the required network reinforcement, with a reactive one that does not make any anticipation but that may then face greater congestion while the network is being reinforced. The efficiency of these behaviors is measured in terms of social cost. We find out that there exists a limit of probability for the connection of generators beyond which a proactive TSO is more efficient than a reactive one. Evaluated on a realistic case of connection, this limit of probability is found quite low, which indicates that the proactive behavior for a TSO shall generally be the optimal one.","PeriodicalId":207041,"journal":{"name":"2008 First International Conference on Infrastructure Systems and Services: Building Networks for a Brighter Future (INFRA)","volume":"2010 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2008-11-10","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"8","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2008 First International Conference on Infrastructure Systems and Services: Building Networks for a Brighter Future (INFRA)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/INFRA.2008.5439602","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 8

Abstract

This paper proposes a model and preliminary results to evaluate the efficiency of anticipating the connection of power plants with shorter construction duration than the time needed to obtain the right to upgrade the network and finally to do this reinforcement. This evaluation is made in presence of a cost of anticipation related to the study of the project of network investment and to the administrative procedures needed to obtain the building agreement. This model compares a proactive TSO that anticipates the connection of new generators and then the required network reinforcement, with a reactive one that does not make any anticipation but that may then face greater congestion while the network is being reinforced. The efficiency of these behaviors is measured in terms of social cost. We find out that there exists a limit of probability for the connection of generators beyond which a proactive TSO is more efficient than a reactive one. Evaluated on a realistic case of connection, this limit of probability is found quite low, which indicates that the proactive behavior for a TSO shall generally be the optimal one.
对高效输电网投资的预期
本文提出了一个模型并给出了初步结果,以评估在获得电网升级改造权并最终进行电网升级改造所需时间内,对工期较短的电厂进行预接入的效率。这一评价是在与研究网络投资项目和获得建筑协议所需的行政程序有关的预期费用的情况下进行的。该模型比较了主动TSO和被动TSO,前者预测新发电机的连接,然后进行所需的网络加固,后者不做任何预测,但在网络加固时可能面临更大的拥塞。这些行为的效率是用社会成本来衡量的。我们发现发电机连接存在一个概率极限,超过这个极限,主动TSO比无功TSO更有效。通过对实际连接情况的评估,发现该概率极限很低,这表明TSO的主动行为通常是最优行为。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信