{"title":"A Necessary and Sufficient Condition for Obtaining Feasible Solution to Hydro Power Scheduling with Multiple Operating Zones","authors":"Q. Zhai, X. Guan, F. Gao","doi":"10.1109/PES.2007.386073","DOIUrl":null,"url":null,"abstract":"Hydro generation scheduling with complicated discrete dynamic operating constraints and multiple operating zones is extremely difficult. One of the most important problems is to identify the feasibility of a hydro unit commitment and to construct a feasible solution efficiently. This paper focuses addressing the issues of the hydro generation scheduling problem with a single hydroelectric plant and several units and multiple operating zones. Based on analysis of the structure of water conservation equations, a necessary and sufficient condition on the problem feasibility is presented and is applied in constructing feasible solution as efficient tool. Its application for generating efficient cutting planes in mixed integer programming problem is discussed. The theoretical results are also validated by numerical examples.","PeriodicalId":380613,"journal":{"name":"2007 IEEE Power Engineering Society General Meeting","volume":"7 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2007-06-24","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"6","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2007 IEEE Power Engineering Society General Meeting","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/PES.2007.386073","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 6

Abstract

Hydro generation scheduling with complicated discrete dynamic operating constraints and multiple operating zones is extremely difficult. One of the most important problems is to identify the feasibility of a hydro unit commitment and to construct a feasible solution efficiently. This paper focuses addressing the issues of the hydro generation scheduling problem with a single hydroelectric plant and several units and multiple operating zones. Based on analysis of the structure of water conservation equations, a necessary and sufficient condition on the problem feasibility is presented and is applied in constructing feasible solution as efficient tool. Its application for generating efficient cutting planes in mixed integer programming problem is discussed. The theoretical results are also validated by numerical examples.
水电多作业区调度可行解的充分必要条件
具有复杂离散动态运行约束和多运行区域的水力发电调度是一个非常困难的问题。其中最重要的问题之一是确定水电机组承建的可行性,并有效地构建一个可行的解决方案。本文主要研究了单水电厂、多机组、多工作区的水力发电调度问题。在分析保水方程结构的基础上,提出了问题可行性的一个充要条件,并将其作为构造可行解的有效工具加以应用。讨论了该方法在混合整数规划问题中生成有效切割平面的应用。数值算例验证了理论结果。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信