Evaluation of Measures Undertaken in the Distribution Network Based on the Potential of Reducing the Costs of Supply Interruptions

V. Detfich, P. Skala, Z. Špaček, V. Blazek
{"title":"Evaluation of Measures Undertaken in the Distribution Network Based on the Potential of Reducing the Costs of Supply Interruptions","authors":"V. Detfich, P. Skala, Z. Špaček, V. Blazek","doi":"10.1109/PCT.2007.4538601","DOIUrl":null,"url":null,"abstract":"The paper presents a new method allowing us to express, in financial terms, the contribution of certain measures undertaken in the network that result in increasing the reliability of electricity supply to customers. This method is based on the potential of reducing the costs of supply interruptions. Simulation tools elaborated by EGU Brno, a. s. which respect the non- homogeneity of the numbers and durations of supply interruptions on individual feeders are used for this purpose. The results obtained follow from the distribution of annual numbers of supply interruptions on feeders and from the distribution of their durations reflecting the real situation on a given group of feeders. The costs of supply interruptions are calculated based on customer's standards of electricity supply continuity. Practical application of the method is demonstrated by using an example of applying a slow auto-reclosing in a 22 kV overhead distribution network and of installing telecontrolled switching elements on a model 22 kV feeder.","PeriodicalId":356805,"journal":{"name":"2007 IEEE Lausanne Power Tech","volume":"41 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2007-07-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"5","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2007 IEEE Lausanne Power Tech","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/PCT.2007.4538601","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 5

Abstract

The paper presents a new method allowing us to express, in financial terms, the contribution of certain measures undertaken in the network that result in increasing the reliability of electricity supply to customers. This method is based on the potential of reducing the costs of supply interruptions. Simulation tools elaborated by EGU Brno, a. s. which respect the non- homogeneity of the numbers and durations of supply interruptions on individual feeders are used for this purpose. The results obtained follow from the distribution of annual numbers of supply interruptions on feeders and from the distribution of their durations reflecting the real situation on a given group of feeders. The costs of supply interruptions are calculated based on customer's standards of electricity supply continuity. Practical application of the method is demonstrated by using an example of applying a slow auto-reclosing in a 22 kV overhead distribution network and of installing telecontrolled switching elements on a model 22 kV feeder.
基于降低供应中断成本潜力的配电网措施评价
本文提出了一种新的方法,使我们能够用财务术语来表示在电网中采取的某些措施对提高客户电力供应可靠性的贡献。这种方法是基于降低供应中断成本的潜力。由EGU Brno, a. s.详细阐述的仿真工具考虑了单个馈线上供电中断的数量和持续时间的非同质性,用于此目的。根据馈线年供电中断次数的分布及其持续时间的分布,得到了反映给定馈线组实际情况的结果。供电中断的成本是根据客户的供电连续性标准来计算的。通过在22kv架空配电网中应用慢速自动重合闸和在22kv馈线上安装遥控开关元件的实例,说明了该方法的实际应用。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信