{"title":"Improved Drilling Efficiencies Using Offline Cementing Saves Days on Well and Reduces Costs","authors":"Samuel Van Meter, Kristin Kutchak, Habib Guerrero","doi":"10.2118/196600-ms","DOIUrl":null,"url":null,"abstract":"\n Drilling in the Appalachian basin in Pennsylvania has evolved since its inception. Operators have shifted their focus from mere wellbore delivery to delivering wells in the shortest amount of time to reduce risks and costs, as well as drive efficiency. This paper presents a case study in which offline cementing helped improve operation efficiency by reducing drilling times and provided significant cost savings.\n Offline cementing is not a new concept. In Q4 2015, an operator drilling in the Eagle Ford shale began the movement of their program toward offline cementing of both the surface and production casings. The operator determined that reducing flat time was crucial to create a cost savings (Hsieh 2018). When another operator began their 2018 drilling program in northeastern Pennsylvania, improving efficiencies was discussed with the service company. After quantifying the experience obtained during a previous project, the service company proposed offline cementing because of the economic benefits it could provide.\n The service company was able to cement both the surface and intermediate casing strings offline while the operator skidded to the next well to begin rigging up. All surface casings were drilled and cemented offline and the rig skidded back to drill for the intermediate casings, which were also cemented offline. Approximately 15 hours was saved by skidding between surface strings, and another 16 hours was saved between intermediate casings.\n This paper discusses the successful use of offline cementing during drilling operations in northeastern Pennsylvania. The flat time reduction achieved during this drilling program can be quantified into a cost savings of approximately USD 80,000 per well.","PeriodicalId":197372,"journal":{"name":"Day 2 Wed, October 16, 2019","volume":"7 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-10-15","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Wed, October 16, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/196600-ms","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

Drilling in the Appalachian basin in Pennsylvania has evolved since its inception. Operators have shifted their focus from mere wellbore delivery to delivering wells in the shortest amount of time to reduce risks and costs, as well as drive efficiency. This paper presents a case study in which offline cementing helped improve operation efficiency by reducing drilling times and provided significant cost savings. Offline cementing is not a new concept. In Q4 2015, an operator drilling in the Eagle Ford shale began the movement of their program toward offline cementing of both the surface and production casings. The operator determined that reducing flat time was crucial to create a cost savings (Hsieh 2018). When another operator began their 2018 drilling program in northeastern Pennsylvania, improving efficiencies was discussed with the service company. After quantifying the experience obtained during a previous project, the service company proposed offline cementing because of the economic benefits it could provide. The service company was able to cement both the surface and intermediate casing strings offline while the operator skidded to the next well to begin rigging up. All surface casings were drilled and cemented offline and the rig skidded back to drill for the intermediate casings, which were also cemented offline. Approximately 15 hours was saved by skidding between surface strings, and another 16 hours was saved between intermediate casings. This paper discusses the successful use of offline cementing during drilling operations in northeastern Pennsylvania. The flat time reduction achieved during this drilling program can be quantified into a cost savings of approximately USD 80,000 per well.
离线固井提高了钻井效率,节省了作业时间,降低了成本
宾夕法尼亚州阿巴拉契亚盆地的钻探活动从一开始就在不断发展。为了降低风险和成本,提高效率,作业者已经将重点从单纯的井筒交付转移到在最短的时间内完成井筒交付。本文介绍了一个实例研究,该实例通过减少钻井时间和显著节约成本,帮助提高了作业效率。离线固井并不是一个新概念。2015年第四季度,一家作业公司在Eagle Ford页岩进行钻井作业,开始对地面和生产套管进行离线固井。作业者认为,减少平井时间对于节省成本至关重要(Hsieh 2018)。当另一家运营商在宾夕法尼亚州东北部开始2018年的钻井计划时,他们与服务公司讨论了提高效率的问题。在量化了之前项目的经验后,服务公司考虑到线下固井可以带来的经济效益,建议进行线下固井。当作业者转向下一口井开始装配时,服务公司能够离线固井地面和中间套管柱。所有地面套管均在脱机状态下进行钻井和固井,然后钻机回钻中间套管,中间套管也在脱机状态下进行固井。地面管柱之间的滑动节省了大约15个小时,中间套管之间的滑动节省了16个小时。本文讨论了离线固井在宾夕法尼亚州东北部钻井作业中的成功应用。在该钻井计划中,减少的平井时间可以量化为每口井节省约80,000美元的成本。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信
小红书