Analisa Produktivitas Tenaga Kerja Pada Pekerjaaan Rangka Atap

M. Mulyadi, H. Hasnawati, Muhammad Ridha
{"title":"Analisa Produktivitas Tenaga Kerja Pada Pekerjaaan Rangka Atap","authors":"M. Mulyadi, H. Hasnawati, Muhammad Ridha","doi":"10.30601/JTSU.V5I2.285","DOIUrl":null,"url":null,"abstract":"Productivity is an important factor in determining the success of a construction work. Increased productivity will reduce work time, and that means it will reduce costs. In general, the value of productivity is determined by the factor of the volume of work, implementation time, and the number of workers. In order to get the job done well, a planning effort is needed by paying attention to these factors. For this reason, this study was conducted to determine the value of productivity in one component of building construction work, namely lightweight steel roof truss work. The object of study was the work of lightweight steel roof truss 4 (four) project sites, namely the 4 x 25 Shop Houses Construction Project in Meulaboh, West Aceh, the Building of the Rector & Administration Bureau Building of STKIP Bina Bangsa Getsempena Banda Aceh, the Construction of the Getsempena Lhoksukon North Aceh STIKES Building and the Construction of North Aceh RIKI STIKes Building, Bina Nusantara Idi, East Aceh. The roof truss material used is type C Truss 75 0.75 Thickness. The volume of roof truss work is planned to be 2022.38 m2. The study was conducted through field observations by directly recording the volume of work, the duration of each stage of work, and the number of workers involved. The results of the analysis show that the productivity value for roof truss works is obtained by an average of 2,062 m2 / hour or 16,499 m2 / day. In the implementation of roof truss work, the amount of labor used is the same in all segments, so the value of productivity tends to be determined by the magnitude of the ratio between the volume of work and the effective time of implementation. Thus, if the amount of work volume can be completed in a shorter time then the value of productivity will increase","PeriodicalId":336743,"journal":{"name":"Jurnal Teknik Sipil Unaya","volume":"1047 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-08-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Teknik Sipil Unaya","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.30601/JTSU.V5I2.285","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Productivity is an important factor in determining the success of a construction work. Increased productivity will reduce work time, and that means it will reduce costs. In general, the value of productivity is determined by the factor of the volume of work, implementation time, and the number of workers. In order to get the job done well, a planning effort is needed by paying attention to these factors. For this reason, this study was conducted to determine the value of productivity in one component of building construction work, namely lightweight steel roof truss work. The object of study was the work of lightweight steel roof truss 4 (four) project sites, namely the 4 x 25 Shop Houses Construction Project in Meulaboh, West Aceh, the Building of the Rector & Administration Bureau Building of STKIP Bina Bangsa Getsempena Banda Aceh, the Construction of the Getsempena Lhoksukon North Aceh STIKES Building and the Construction of North Aceh RIKI STIKes Building, Bina Nusantara Idi, East Aceh. The roof truss material used is type C Truss 75 0.75 Thickness. The volume of roof truss work is planned to be 2022.38 m2. The study was conducted through field observations by directly recording the volume of work, the duration of each stage of work, and the number of workers involved. The results of the analysis show that the productivity value for roof truss works is obtained by an average of 2,062 m2 / hour or 16,499 m2 / day. In the implementation of roof truss work, the amount of labor used is the same in all segments, so the value of productivity tends to be determined by the magnitude of the ratio between the volume of work and the effective time of implementation. Thus, if the amount of work volume can be completed in a shorter time then the value of productivity will increase
分析屋脊劳动力的生产力
生产力是决定建筑工程成功与否的一个重要因素。生产力的提高将减少工作时间,这意味着它将降低成本。一般来说,生产力的价值是由工作量、实施时间和工人人数等因素决定的。为了把工作做好,需要通过注意这些因素来制定计划。因此,本研究旨在确定建筑施工工作的一个组成部分的生产率值,即轻钢屋架工程。研究的对象是轻钢屋架的工作4(4)个项目地点,即在亚齐西部Meulaboh的4 × 25商店房屋建设项目,Bina Bangsa Getsempena Banda Aceh的STKIP校长和行政管理局大楼的建设,Getsempena Lhoksukon北亚齐STIKES大楼的建设和北亚齐RIKI STIKES大楼的建设,Bina Nusantara Idi,东亚齐。屋架使用的材料为C型桁架,厚度为75 0.75。屋架工程量规划为2022.38 m2。这项研究是通过实地观察进行的,直接记录了工作量、每个工作阶段的持续时间和所涉及的工人人数。分析结果表明,屋架工程的生产率值平均为2062 m2 /小时或16499 m2 /天。在屋架工程的实施中,各个环节所使用的劳动量是相同的,因此生产率的价值往往由工作量与实施有效时间之比的大小来决定。因此,如果工作量可以在较短的时间内完成,那么生产力的价值就会增加
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信