The challenges of sub-optimal substation site selection

H. Dehbonei
{"title":"The challenges of sub-optimal substation site selection","authors":"H. Dehbonei","doi":"10.1109/DTEC.2016.7731287","DOIUrl":null,"url":null,"abstract":"This paper discusses sub-optimal substation site selection and the challenges of developing an earthing design for the substation and transmission line, as well as the solutions adopted. The site selected was close to a major Telstra exchange and high pressure gas valve, on a system with a high fault capacity, poor soil resistivity and which is connected to a transmission line possessing limited OHEW length. The earthing design identified possible existing LFI issues beyond the project's geographical location. Both gas and water steel pipelines were running parallel to the existing transmission line, over a considerable distance. A detailed analytical model was prepared, which showed the significance of the proximity effect. Risk based and deterministic criteria were compared to establish the best safety criteria for this design. A preliminary site test (using deep electrodes) was conducted to verify soil resistivity test results. The contractor's test readings were found to be inaccurate and were re-done. Follow up testing reflected sound correlation between field and modelled results. To avoid underground asset mitigation, special and cost effective earthing design was adopted. It was discussed and agreed with Telstra and colleagues in the distribution section to minimise transfer voltage via Common Multiple Earth Neutral (CMEN). This case study illustrates that engaging major stakeholders is key to the success of complex projects.","PeriodicalId":417330,"journal":{"name":"2016 Down to Earth Conference (DTEC)","volume":"286 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2016-09-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2016 Down to Earth Conference (DTEC)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/DTEC.2016.7731287","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

This paper discusses sub-optimal substation site selection and the challenges of developing an earthing design for the substation and transmission line, as well as the solutions adopted. The site selected was close to a major Telstra exchange and high pressure gas valve, on a system with a high fault capacity, poor soil resistivity and which is connected to a transmission line possessing limited OHEW length. The earthing design identified possible existing LFI issues beyond the project's geographical location. Both gas and water steel pipelines were running parallel to the existing transmission line, over a considerable distance. A detailed analytical model was prepared, which showed the significance of the proximity effect. Risk based and deterministic criteria were compared to establish the best safety criteria for this design. A preliminary site test (using deep electrodes) was conducted to verify soil resistivity test results. The contractor's test readings were found to be inaccurate and were re-done. Follow up testing reflected sound correlation between field and modelled results. To avoid underground asset mitigation, special and cost effective earthing design was adopted. It was discussed and agreed with Telstra and colleagues in the distribution section to minimise transfer voltage via Common Multiple Earth Neutral (CMEN). This case study illustrates that engaging major stakeholders is key to the success of complex projects.
次优变电站选址的挑战
本文讨论了变电站的次优选址、变电站和输电线路的接地设计所面临的挑战以及所采取的解决办法。所选站点靠近Telstra的主要交换机和高压气体阀,系统故障容量大,土壤电阻率差,并且与OHEW长度有限的传输线相连。接地设计确定了项目地理位置之外可能存在的LFI问题。天然气和水的钢制管道与现有的输电线平行运行,距离相当远。建立了详细的分析模型,表明了邻近效应的显著性。对基于风险的标准和确定性标准进行比较,以确定该设计的最佳安全标准。为验证土壤电阻率测试结果,进行了初步现场试验(采用深电极)。发现承包商的测试读数不准确,重新做了一次。后续测试反映了现场结果与模拟结果之间良好的相关性。为了避免对地下资产的影响,采用了特殊的、经济有效的接地设计。Telstra和配电部门的同事讨论并同意通过公共多重接地中性点(CMEN)将传输电压降至最低。这个案例研究说明了主要利益相关者的参与是复杂项目成功的关键。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信