Advanced Steam Turbine Technology for Unique Double Reheat Steam Power Plant Layout

Benjamin Kloss-Grote, M. Wechsung, R. Quinkertz, Henning Almstedt
{"title":"Advanced Steam Turbine Technology for Unique Double Reheat Steam Power Plant Layout","authors":"Benjamin Kloss-Grote, M. Wechsung, R. Quinkertz, Henning Almstedt","doi":"10.1115/gt2019-90934","DOIUrl":null,"url":null,"abstract":"\n Environmental aspects have increased the pressure on the fossil power generation industry to reduce carbon dioxide (CO2) emissions. One way to achieve this is by increasing the overall plant efficiency, which also fosters an economical plant operation. How can the efficiency of a next generation coal fired ultra super critical (USC) steam power plant (SPP) be increased significantly in the nearest future while maintaining its familiar reliability and availability at the same time? In China’s national USC SPP demonstration project, Pingshan Phase II, this challenge is met by a double reheat cross compound turboset with one elevated and one conventional turbine layout, together with increased steam parameters of up to 325 bar and steam temperatures of up to 630°C. The nominal electrical capacity of the plant will be 1350 megawatts (MW). With this set up, a ‘half-net’ efficiency of more than 52.2 percent is expected [‘half-net’ = gross efficiency with generator power reduced by boiler feed water pump power consumption]. The first, elevated turbine train consists of two high-pressure modules having different pressure stages and one generator and it is located close to the main headers of the boiler at a height of appr. 83 meters. This unique turbine arrangement allows the expensive high-temperature pipes to be shortened, leading to substantially reduced pipe pressure losses and costs. The second turbine train will be installed on a conventional turbine deck at a height of appr. 17 meters and consists of two intermediate pressure and three low pressure turbine modules as well as a second generator. In this paper, the advanced steam turbine technology for this power plant concept is presented and discussed in detail.\n To achieve the next level of efficiency with an SPP today, the application of the 700°C material class is not possible to due to the slow progress of the associated technology development. It is more expedient to exploit the limits of the 600°C material class to the highest possible extent in USC conditions i.e. to the pressures and temperatures mentioned above. Design concept studies have shown that 52.2% ‘half-net’ efficiency cannot be achieved with a single reheat layout, so a double reheat (DRH) layout has been chosen. In addition, 1350 MW cannot be achieved with one turbine train (tandem compound), but only with two turbine trains (cross compound). In order to achieve the highest reliability possible, proven turbine design topologies and features have been used. The major change to the Siemens barrel type VHP turbine was a material change from 10% Chromium steels to FB2 and CB2. The HP turbine received increased wall thicknesses as well as a similar material change compared to a standard USC design. In order to control the oxidation at these elevated temperatures, oxidation protection measures have been applied where required. The startup procedure has been tailored specifically to the needs of a double reheat cross compound configuration.","PeriodicalId":105494,"journal":{"name":"Volume 8: Microturbines, Turbochargers, and Small Turbomachines; Steam Turbines","volume":"51 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-11-05","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Volume 8: Microturbines, Turbochargers, and Small Turbomachines; Steam Turbines","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1115/gt2019-90934","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Environmental aspects have increased the pressure on the fossil power generation industry to reduce carbon dioxide (CO2) emissions. One way to achieve this is by increasing the overall plant efficiency, which also fosters an economical plant operation. How can the efficiency of a next generation coal fired ultra super critical (USC) steam power plant (SPP) be increased significantly in the nearest future while maintaining its familiar reliability and availability at the same time? In China’s national USC SPP demonstration project, Pingshan Phase II, this challenge is met by a double reheat cross compound turboset with one elevated and one conventional turbine layout, together with increased steam parameters of up to 325 bar and steam temperatures of up to 630°C. The nominal electrical capacity of the plant will be 1350 megawatts (MW). With this set up, a ‘half-net’ efficiency of more than 52.2 percent is expected [‘half-net’ = gross efficiency with generator power reduced by boiler feed water pump power consumption]. The first, elevated turbine train consists of two high-pressure modules having different pressure stages and one generator and it is located close to the main headers of the boiler at a height of appr. 83 meters. This unique turbine arrangement allows the expensive high-temperature pipes to be shortened, leading to substantially reduced pipe pressure losses and costs. The second turbine train will be installed on a conventional turbine deck at a height of appr. 17 meters and consists of two intermediate pressure and three low pressure turbine modules as well as a second generator. In this paper, the advanced steam turbine technology for this power plant concept is presented and discussed in detail. To achieve the next level of efficiency with an SPP today, the application of the 700°C material class is not possible to due to the slow progress of the associated technology development. It is more expedient to exploit the limits of the 600°C material class to the highest possible extent in USC conditions i.e. to the pressures and temperatures mentioned above. Design concept studies have shown that 52.2% ‘half-net’ efficiency cannot be achieved with a single reheat layout, so a double reheat (DRH) layout has been chosen. In addition, 1350 MW cannot be achieved with one turbine train (tandem compound), but only with two turbine trains (cross compound). In order to achieve the highest reliability possible, proven turbine design topologies and features have been used. The major change to the Siemens barrel type VHP turbine was a material change from 10% Chromium steels to FB2 and CB2. The HP turbine received increased wall thicknesses as well as a similar material change compared to a standard USC design. In order to control the oxidation at these elevated temperatures, oxidation protection measures have been applied where required. The startup procedure has been tailored specifically to the needs of a double reheat cross compound configuration.
先进的汽轮机技术,独特的双再热蒸汽电厂布局
环境因素增加了化石发电行业减少二氧化碳排放的压力。实现这一目标的一种方法是提高工厂的整体效率,这也促进了工厂的经济运行。如何在不久的将来显著提高下一代燃煤超超临界(USC)蒸汽发电厂(SPP)的效率,同时保持其熟悉的可靠性和可用性?在中国国家级超超临界SPP示范项目屏山二期中,采用双再热交叉复合汽轮机组,采用一种高架和一种常规涡轮布局,同时将蒸汽参数提高到325巴,蒸汽温度提高到630℃,以应对这一挑战。该电站的标称发电量为1350兆瓦(MW)。有了这个装置,预计“半净”效率将超过52.2%[“半净”=发电机功率减少后的总效率,锅炉给水泵的功率消耗]。第一种,高架涡轮机组由两个具有不同压力级的高压模块和一台发电机组成,位于锅炉主集箱附近,高度为apr。83米。这种独特的涡轮布置可以缩短昂贵的高温管道,从而大大降低管道压力损失和成本。第二个涡轮列车将被安装在一个传统的涡轮甲板上,高度为apr。17米,由两个中压和三个低压涡轮模块以及第二台发电机组成。本文对该电厂概念的先进汽轮机技术进行了详细的介绍和讨论。由于相关技术发展进展缓慢,为了实现SPP的下一个效率水平,700°C材料级别的应用是不可能的。在USC条件下,即在上述压力和温度下,尽可能地利用600°C材料类别的极限是更有利的。设计概念研究表明,单次再热布局无法达到52.2%的“半净”效率,因此选择了双再热(DRH)布局。此外,1350mw不能用一个涡轮串(串联复合)来实现,而只能用两个涡轮串(交叉复合)来实现。为了达到尽可能高的可靠性,已经使用了经过验证的涡轮设计拓扑结构和特征。西门子桶式甚高压涡轮的主要变化是材料从10%铬钢改为FB2和CB2。与标准USC设计相比,HP涡轮的壁厚增加了,材料也发生了类似的变化。为了控制这些高温下的氧化,在需要的地方采取了氧化保护措施。启动程序专门针对双再热交叉化合物配置的需要进行了定制。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信