Optimalisasi Biaya dan Waktu Proyek Kontruksi Pelebaran Jalan Menggunakan Earned Value

Sentot Tri Wibowo, S. Suwarno, Ahmad Ridwan, Haris Wicaksono, Fitry Rahmawaty
{"title":"Optimalisasi Biaya dan Waktu Proyek Kontruksi Pelebaran Jalan Menggunakan Earned Value","authors":"Sentot Tri Wibowo, S. Suwarno, Ahmad Ridwan, Haris Wicaksono, Fitry Rahmawaty","doi":"10.30737/jurmateks.v4i2.1828","DOIUrl":null,"url":null,"abstract":"In a construction project, there are several aspects that cause the project not to go according to plan. Cost and time are aspects that need to be considered to avoid losses incurred in a project. Jombang-ploso-legundi-gresik road project is one of the road widening projects carried out by PT. Mix Pro Indonesia. The project was carried out with the aim that access to (Surabaya-Mojokerto) or further trans Java toll road is quicker safe and smoother. This research aims to optimize the cost and time on the project using the Earned Value method. Calculations include the calculation of ACWP (Actual Cost of Work Performance), BCWS (Budgeted Cost Work Schedule), and BCWP (Budgeted Cost for Work Performed) using the Earned Value method. From these parameters, estimate aspects of cost and time. As well as project analysis of acceleration on a critical trajectory of work. The results of calculations in the 12th week obtained a BCWS value of Rp 1,216,677,846,400 BCWP = Rp 3,040,372,140,080, ACWP = Rp 3,678,560,000. CV value = -Rp 109,203,495.92, SV = Rp 895,646,816.82, CPI = 0.827, and for SPI = 2,499. From these results it can be seen that the CPI value < 1 which means that there are project expenditures that exceed the original plan. With the results, it can be used as a reference in the implementation of project activities.","PeriodicalId":382880,"journal":{"name":"Jurnal Manajemen Teknologi & Teknik Sipil","volume":"6 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2021-10-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Manajemen Teknologi & Teknik Sipil","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.30737/jurmateks.v4i2.1828","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

Abstract

In a construction project, there are several aspects that cause the project not to go according to plan. Cost and time are aspects that need to be considered to avoid losses incurred in a project. Jombang-ploso-legundi-gresik road project is one of the road widening projects carried out by PT. Mix Pro Indonesia. The project was carried out with the aim that access to (Surabaya-Mojokerto) or further trans Java toll road is quicker safe and smoother. This research aims to optimize the cost and time on the project using the Earned Value method. Calculations include the calculation of ACWP (Actual Cost of Work Performance), BCWS (Budgeted Cost Work Schedule), and BCWP (Budgeted Cost for Work Performed) using the Earned Value method. From these parameters, estimate aspects of cost and time. As well as project analysis of acceleration on a critical trajectory of work. The results of calculations in the 12th week obtained a BCWS value of Rp 1,216,677,846,400 BCWP = Rp 3,040,372,140,080, ACWP = Rp 3,678,560,000. CV value = -Rp 109,203,495.92, SV = Rp 895,646,816.82, CPI = 0.827, and for SPI = 2,499. From these results it can be seen that the CPI value < 1 which means that there are project expenditures that exceed the original plan. With the results, it can be used as a reference in the implementation of project activities.
优化道路扩建项目的成本和时间使用实际价值
在一个建设项目中,有几个方面导致项目没有按计划进行。成本和时间是需要考虑的方面,以避免在项目中发生损失。Jombang-ploso-legundi-gresik道路项目是PT. Mix Pro Indonesia进行的道路拓宽项目之一。该项目旨在使通往(泗水- mojokerto)或更远的跨爪哇收费公路更快捷、更安全、更顺畅。本研究旨在利用挣值法优化项目的成本和时间。计算方法包括使用挣值法计算ACWP(实际工作绩效成本)、BCWS(预算成本工作进度)和BCWP(预算完成工作成本)。根据这些参数,估算成本和时间。以及关键工作轨迹上加速度的项目分析。第12周的计算结果得到BCWS值为Rp 1,216,677,846,400 BCWP = Rp 3,040,372,140,080, ACWP = Rp 3,678,560,000。CV值= -Rp 109,203,495.92, SV = Rp 895,646,816.82, CPI = 0.827, SPI = 2,499。从这些结果可以看出,CPI值< 1,即存在超出原计划的项目支出。研究结果可作为项目活动实施的参考。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信
小红书