Reducing the duration of right-of-way acquisition process for high voltage transmission power lines projects

Mobasher Alasmry, Khalil Alsayed, Jaman Alzahrni, Abdu Hobany
{"title":"Reducing the duration of right-of-way acquisition process for high voltage transmission power lines projects","authors":"Mobasher Alasmry, Khalil Alsayed, Jaman Alzahrni, Abdu Hobany","doi":"10.1109/SASG.2016.7849672","DOIUrl":null,"url":null,"abstract":"Right of way process of high voltage, 110–132 K.V, transmission power lines projects is complicated process as it is based on more than fifty interrelated steps that involve several departments and governmental agencies to obtain the necessary permits and secure approvals of power lines routes. Permitting process has to be within time frame of about one to one and a half year which is composing twenty five to thirty percent of project life cycle. Obtaining permits is in accordance with pre-set technical and economical constraints is more challenging factors to assure constructability and maintainability of route proposal. This paper will focus on the factors affecting the R.O.W process of high voltage transmission lines by presenting systematic approach entitled; six phases of high voltage transmission lines R.O.W process. Among the phases is proposing three routes for transmission lines then its study to select the most cost effective route by utilizing CAD & DEM files. Field portion of the process is significant, gathering field data accurately then analyzing to converting into profile and route maps is vital phase, this phase has couple of criteria to make sure the data obtained during site visit is in integration with technical and economical requirements. Also identifying risks encountered during study of route alternatives along with mitigation measures is discussed; risk identification of process will speed up the R.O.W by minimizing permitting duration particularly at phase five as it is alone consumes 70–80 % of the whole permitting process duration.","PeriodicalId":343189,"journal":{"name":"2016 Saudi Arabia Smart Grid (SASG)","volume":"18 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2016-12-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2016 Saudi Arabia Smart Grid (SASG)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/SASG.2016.7849672","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

Abstract

Right of way process of high voltage, 110–132 K.V, transmission power lines projects is complicated process as it is based on more than fifty interrelated steps that involve several departments and governmental agencies to obtain the necessary permits and secure approvals of power lines routes. Permitting process has to be within time frame of about one to one and a half year which is composing twenty five to thirty percent of project life cycle. Obtaining permits is in accordance with pre-set technical and economical constraints is more challenging factors to assure constructability and maintainability of route proposal. This paper will focus on the factors affecting the R.O.W process of high voltage transmission lines by presenting systematic approach entitled; six phases of high voltage transmission lines R.O.W process. Among the phases is proposing three routes for transmission lines then its study to select the most cost effective route by utilizing CAD & DEM files. Field portion of the process is significant, gathering field data accurately then analyzing to converting into profile and route maps is vital phase, this phase has couple of criteria to make sure the data obtained during site visit is in integration with technical and economical requirements. Also identifying risks encountered during study of route alternatives along with mitigation measures is discussed; risk identification of process will speed up the R.O.W by minimizing permitting duration particularly at phase five as it is alone consumes 70–80 % of the whole permitting process duration.
减少高压输电线路项目路权获取过程的持续时间
高压路权过程,110-132 K。第五,输电线路项目是一个复杂的过程,因为它基于50多个相互关联的步骤,涉及几个部门和政府机构,以获得必要的许可和确保电力线路线的批准。许可过程必须在大约一年到一年半的时间框架内这占了项目生命周期的25%到30%。根据预先设定的技术和经济限制获得许可证是确保路线建议的可建造性和可维护性的更具挑战性的因素。本文将采用系统的方法对影响高压输电线路转流过程的因素进行研究。六相高压输电线路R.O.W过程。其中提出了输电线路的三种路线,并利用CAD和DEM文件进行了选择最具成本效益路线的研究。现场部分的过程是重要的,准确地收集现场数据,然后分析到转换成剖面图和路线图是至关重要的阶段,这一阶段有几个标准,以确保在现场访问期间获得的数据与技术和经济要求相结合。此外,还讨论了在研究备选路线时遇到的风险以及缓解措施;过程的风险识别将通过最小化许可时间来加快R.O.W,特别是在第五阶段,因为仅这一阶段就消耗了整个许可过程时间的70 - 80%。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信