{"title":"Implementation of building contracts in the project management system case study. Part I","authors":"M. Rogalska, Z. Hejducki","doi":"10.5604/01.3001.0016.2712","DOIUrl":null,"url":null,"abstract":"The article presents an example of the functioning ofa team of Project Managers at various levels of construction projectmanagement. A detailed procedure for the implementationof the project at the lowest level of the PM structure, in a companyspecialized in roofing works, in particular flat roofs with largesurfaces, was presented. The article contains the authors experiencesand observations from engineering activities in the conductof construction contracts as a Project Manager (PM).","PeriodicalId":175990,"journal":{"name":"Przegląd Budowlany","volume":"39 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-02-26","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"Przegląd Budowlany","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.5604/01.3001.0016.2712","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
Abstract
The article presents an example of the functioning ofa team of Project Managers at various levels of construction projectmanagement. A detailed procedure for the implementationof the project at the lowest level of the PM structure, in a companyspecialized in roofing works, in particular flat roofs with largesurfaces, was presented. The article contains the authors experiencesand observations from engineering activities in the conductof construction contracts as a Project Manager (PM).