Efficiency factor and risk factor based user case point test effort estimation model compatible with agile software development

Abu Wahid Md Masud Parvez
{"title":"Efficiency factor and risk factor based user case point test effort estimation model compatible with agile software development","authors":"Abu Wahid Md Masud Parvez","doi":"10.1109/ICITEED.2013.6676222","DOIUrl":null,"url":null,"abstract":"In software outsourcing industry, to win a contract, outsourcing companies need to consider the price that they will introduce to customers. Therefore, estimation has played an important role in any type of software project and as well as for test projects. Particularly, the estimation of testing has been more critical and magnitude as companies need to present or bid their prices on the project to win the outsourcing contract. Wrong estimation can negatively affect the company sales in both ways. On the one side, the profit margin could be reduced or hurt when the bidding is less than that real effort. On the other side, the company could lose the project when the bidding is higher than that of competitors. Therefore, it is extremely necessary to apply economic and systematic estimation model or process to enhance the accuracy in estimation. The integration of highly skilled workforce and accurate test effort estimation software will provide significant benefits to companies. Up to now, there are various existing models of test effort estimation, yet use case point estimation is one of the most popular models in the agile software development industry. The present paper aims to investigate the use case point estimation model. Following the analysis, we have developed two important elements namely, efficiency and risk factor based on a new layer in the model developed by us. The benefit of the new model is to increase the performance and effectiveness of the use case point estimation model.","PeriodicalId":204082,"journal":{"name":"2013 International Conference on Information Technology and Electrical Engineering (ICITEE)","volume":"76 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2013-10-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"18","resultStr":null,"platform":"Semanticscholar","paperid":null,"PeriodicalName":"2013 International Conference on Information Technology and Electrical Engineering (ICITEE)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICITEED.2013.6676222","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 18

Abstract

In software outsourcing industry, to win a contract, outsourcing companies need to consider the price that they will introduce to customers. Therefore, estimation has played an important role in any type of software project and as well as for test projects. Particularly, the estimation of testing has been more critical and magnitude as companies need to present or bid their prices on the project to win the outsourcing contract. Wrong estimation can negatively affect the company sales in both ways. On the one side, the profit margin could be reduced or hurt when the bidding is less than that real effort. On the other side, the company could lose the project when the bidding is higher than that of competitors. Therefore, it is extremely necessary to apply economic and systematic estimation model or process to enhance the accuracy in estimation. The integration of highly skilled workforce and accurate test effort estimation software will provide significant benefits to companies. Up to now, there are various existing models of test effort estimation, yet use case point estimation is one of the most popular models in the agile software development industry. The present paper aims to investigate the use case point estimation model. Following the analysis, we have developed two important elements namely, efficiency and risk factor based on a new layer in the model developed by us. The benefit of the new model is to increase the performance and effectiveness of the use case point estimation model.
与敏捷软件开发兼容的基于效率因子和风险因子的用户用例点测试工作量估算模型
在软件外包行业,为了赢得合同,外包公司需要考虑他们将向客户介绍的价格。因此,评估在任何类型的软件项目以及测试项目中都扮演着重要的角色。特别是,测试的评估变得更加关键和重要,因为公司需要在项目上展示或投标他们的价格以赢得外包合同。错误的估计会在两方面对公司的销售产生负面影响。一方面,当出价低于实际努力时,利润率可能会减少或受损。另一方面,当出价高于竞争对手时,公司可能会失去项目。因此,采用经济、系统的估算模型或流程来提高估算精度是十分必要的。高度熟练的劳动力和准确的测试工作评估软件的集成将为公司提供显著的好处。到目前为止,已有各种各样的测试工作量估计模型,而用例点估计是敏捷软件开发行业中最流行的模型之一。本文旨在研究用例点估计模型。在分析的基础上,我们在模型中增加了一个新的层次,提出了效率和风险两个重要的要素。新模型的好处是提高了用例点估计模型的性能和有效性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
求助全文
约1分钟内获得全文 求助全文
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信