工业选矿设备尺寸及中间负荷的优化

William R. Ernst ★, Mark G. Mod
{"title":"工业选矿设备尺寸及中间负荷的优化","authors":"William R. Ernst ★,&nbsp;Mark G. Mod","doi":"10.1016/0377-841X(78)90005-0","DOIUrl":null,"url":null,"abstract":"<div><p>Two important items must be considered in the early stages of design of a processing plant which contains a cyclic element such as a scaling crystallizer, a filter, a fixed bed adsorber, etc. They are the influence of cycle length on the size of all equipment elements in the process, and the effect of available storage capacity of feed to the cyclic element on process economics. These considerations are particularly important in the development of equipment sizes for industrial minerals processing plants, many of which contain scaling crystallizers.</p><p>The problem of determining cycle time for an item of equipment of fixed capacity to either maximize total production, or to minimize operating costs has been discussed previously. The present work examines a constrained version of this classical problem. It addresses the problem of determining the cycle time that minimizes annual operating costs after the annual plant production rate has been fixed. First, a generalized material balance is developed for a model processing plant which contains scaling and non-scaling elements. Second, a generalized equation which represents rate of scale formation is used in conjunction with the material balance equation to relate equipment design capacity and the required amount of storage capacity with cycle time. Third, a generalized cost equation is developed which can be used to determine optimum cycle time, optimum equipment sizes and required storage capacity. An example is given.</p></div>","PeriodicalId":100475,"journal":{"name":"Engineering and Process Economics","volume":"3 4","pages":"Pages 247-255"},"PeriodicalIF":0.0000,"publicationDate":"1978-11-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://sci-hub-pdf.com/10.1016/0377-841X(78)90005-0","citationCount":"3","resultStr":"{\"title\":\"Optimization of equipment sizes and intermediate surge capacity in industrial minerals processing plants\",\"authors\":\"William R. Ernst ★,&nbsp;Mark G. Mod\",\"doi\":\"10.1016/0377-841X(78)90005-0\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"<div><p>Two important items must be considered in the early stages of design of a processing plant which contains a cyclic element such as a scaling crystallizer, a filter, a fixed bed adsorber, etc. They are the influence of cycle length on the size of all equipment elements in the process, and the effect of available storage capacity of feed to the cyclic element on process economics. These considerations are particularly important in the development of equipment sizes for industrial minerals processing plants, many of which contain scaling crystallizers.</p><p>The problem of determining cycle time for an item of equipment of fixed capacity to either maximize total production, or to minimize operating costs has been discussed previously. The present work examines a constrained version of this classical problem. It addresses the problem of determining the cycle time that minimizes annual operating costs after the annual plant production rate has been fixed. First, a generalized material balance is developed for a model processing plant which contains scaling and non-scaling elements. Second, a generalized equation which represents rate of scale formation is used in conjunction with the material balance equation to relate equipment design capacity and the required amount of storage capacity with cycle time. Third, a generalized cost equation is developed which can be used to determine optimum cycle time, optimum equipment sizes and required storage capacity. An example is given.</p></div>\",\"PeriodicalId\":100475,\"journal\":{\"name\":\"Engineering and Process Economics\",\"volume\":\"3 4\",\"pages\":\"Pages 247-255\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"1978-11-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"https://sci-hub-pdf.com/10.1016/0377-841X(78)90005-0\",\"citationCount\":\"3\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Engineering and Process Economics\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://www.sciencedirect.com/science/article/pii/0377841X78900050\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Engineering and Process Economics","FirstCategoryId":"1085","ListUrlMain":"https://www.sciencedirect.com/science/article/pii/0377841X78900050","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 3

摘要

在设计包含循环元件的加工厂(如结垢结晶器、过滤器、固定床吸附器等)的早期阶段,必须考虑两个重要项目。它们是循环长度对过程中所有设备元件尺寸的影响,以及循环元件的进料可用储存容量对过程经济的影响。这些考虑在工业矿物加工厂的设备尺寸的发展中特别重要,其中许多都包含结垢结晶器。确定一个固定容量设备项目的周期时间以使总产量最大化或使运行成本最小化的问题已经在前面讨论过了。目前的工作考察了这个经典问题的一个约束版本。它解决的问题是,在工厂年生产率固定之后,确定使年运营成本最小化的周期时间。首先,建立了包含结垢和非结垢元素的模型加工厂的广义物料衡算。其次,将表示结垢率的广义方程与物料平衡方程结合使用,将设备设计容量和所需的存储容量与周期时间联系起来。第三,建立了一个可用于确定最佳周期时间、最佳设备尺寸和所需存储容量的广义成本方程。给出了一个例子。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Optimization of equipment sizes and intermediate surge capacity in industrial minerals processing plants

Two important items must be considered in the early stages of design of a processing plant which contains a cyclic element such as a scaling crystallizer, a filter, a fixed bed adsorber, etc. They are the influence of cycle length on the size of all equipment elements in the process, and the effect of available storage capacity of feed to the cyclic element on process economics. These considerations are particularly important in the development of equipment sizes for industrial minerals processing plants, many of which contain scaling crystallizers.

The problem of determining cycle time for an item of equipment of fixed capacity to either maximize total production, or to minimize operating costs has been discussed previously. The present work examines a constrained version of this classical problem. It addresses the problem of determining the cycle time that minimizes annual operating costs after the annual plant production rate has been fixed. First, a generalized material balance is developed for a model processing plant which contains scaling and non-scaling elements. Second, a generalized equation which represents rate of scale formation is used in conjunction with the material balance equation to relate equipment design capacity and the required amount of storage capacity with cycle time. Third, a generalized cost equation is developed which can be used to determine optimum cycle time, optimum equipment sizes and required storage capacity. An example is given.

求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信