{"title":"利用崩溃法设计项目进度,将光纤压缩到家庭项目进度","authors":"Zha Sha Putri Anugerah, D. Pratami, Mohammad Deni Akbar","doi":"10.12928/IJIO.V2I1.3025","DOIUrl":null,"url":null,"abstract":"ABC Company is an agent of network construction, operation, and maintenance. ABC Company is currently implementing the STTF (Shit to the Front) project, which is the project to add FTTH (Fiber to the Home) networks in areas that can have high customer demand. One of the STTF project construction sites is the Indra Prahasta II housing location. However, the project is currently experiencing work delays due to the Covid-19 disaster in Indonesia. Delays in project execution can result in potential prospects choosing another company that provides similar services. The project schedule can be accelerated using the crashing method and TCTO (Time Cost Trade-Off) analysis to solve this problem. This research's acceleration will be carried out with alternatives for adding 3 hours, 2 hours, 1 hour, and an alternative to increasing workers' number. This project has an average duration of 55 working days with a total cost of Rp 604,124,460. The results obtained from data processing, on the alternative of adding 1 hour of overtime work, the total duration becomes 54 working days with total project cost is Rp 605,734,138. In addition to 2 hours of overtime work, the project's total duration can be reduced to 54 days with a total project cost Rp 606,803,619. And for the addition of 3 hours overtime, the total duration can be shortened to 54 days with a total cost of Rp 606,803,619. As for increasing the number of workers, project work duration can be shortened to 54 working days with a total project cost Rp 604,556,748","PeriodicalId":52674,"journal":{"name":"International Journal of Industrial Electronics Control and Optimization","volume":"1 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-02-24","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"3","resultStr":"{\"title\":\"Designing project schedule using crashing method to compress the fiber to the home project schedule\",\"authors\":\"Zha Sha Putri Anugerah, D. Pratami, Mohammad Deni Akbar\",\"doi\":\"10.12928/IJIO.V2I1.3025\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"ABC Company is an agent of network construction, operation, and maintenance. ABC Company is currently implementing the STTF (Shit to the Front) project, which is the project to add FTTH (Fiber to the Home) networks in areas that can have high customer demand. One of the STTF project construction sites is the Indra Prahasta II housing location. However, the project is currently experiencing work delays due to the Covid-19 disaster in Indonesia. Delays in project execution can result in potential prospects choosing another company that provides similar services. The project schedule can be accelerated using the crashing method and TCTO (Time Cost Trade-Off) analysis to solve this problem. This research's acceleration will be carried out with alternatives for adding 3 hours, 2 hours, 1 hour, and an alternative to increasing workers' number. This project has an average duration of 55 working days with a total cost of Rp 604,124,460. The results obtained from data processing, on the alternative of adding 1 hour of overtime work, the total duration becomes 54 working days with total project cost is Rp 605,734,138. In addition to 2 hours of overtime work, the project's total duration can be reduced to 54 days with a total project cost Rp 606,803,619. And for the addition of 3 hours overtime, the total duration can be shortened to 54 days with a total cost of Rp 606,803,619. As for increasing the number of workers, project work duration can be shortened to 54 working days with a total project cost Rp 604,556,748\",\"PeriodicalId\":52674,\"journal\":{\"name\":\"International Journal of Industrial Electronics Control and Optimization\",\"volume\":\"1 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-02-24\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"3\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International Journal of Industrial Electronics Control and Optimization\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.12928/IJIO.V2I1.3025\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of Industrial Electronics Control and Optimization","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.12928/IJIO.V2I1.3025","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 3
摘要
ABC公司是一家网络建设、运营和维护代理公司。ABC公司目前正在实施STTF (Shit to the Front)项目,这是一个在客户需求高的地区增加FTTH(光纤到户)网络的项目。STTF项目的建筑工地之一是Indra Prahasta II住宅。然而,由于印度尼西亚的Covid-19灾难,该项目目前正在经历工作延误。项目执行的延迟可能导致潜在客户选择另一家提供类似服务的公司。利用崩溃法和TCTO(时间成本权衡)分析可以加快项目进度。本研究将以增加3小时、2小时、1小时的替代方案和增加工人人数的替代方案进行加速。该项目平均工期为55个工作日,总费用为604,124,460卢比。根据数据处理的结果,在增加1小时加班的情况下,总工期为54个工作日,项目总成本为Rp 605,734,138。除了2小时的加班,项目的总工期可以减少到54天,项目总成本为606,803,619卢比。加上加班3小时,总工期可以缩短为54天,总费用为Rp 606,803,619。在增加工人数量方面,可以将项目工期缩短为54个工作日,项目总成本为Rp 604,556,748
Designing project schedule using crashing method to compress the fiber to the home project schedule
ABC Company is an agent of network construction, operation, and maintenance. ABC Company is currently implementing the STTF (Shit to the Front) project, which is the project to add FTTH (Fiber to the Home) networks in areas that can have high customer demand. One of the STTF project construction sites is the Indra Prahasta II housing location. However, the project is currently experiencing work delays due to the Covid-19 disaster in Indonesia. Delays in project execution can result in potential prospects choosing another company that provides similar services. The project schedule can be accelerated using the crashing method and TCTO (Time Cost Trade-Off) analysis to solve this problem. This research's acceleration will be carried out with alternatives for adding 3 hours, 2 hours, 1 hour, and an alternative to increasing workers' number. This project has an average duration of 55 working days with a total cost of Rp 604,124,460. The results obtained from data processing, on the alternative of adding 1 hour of overtime work, the total duration becomes 54 working days with total project cost is Rp 605,734,138. In addition to 2 hours of overtime work, the project's total duration can be reduced to 54 days with a total project cost Rp 606,803,619. And for the addition of 3 hours overtime, the total duration can be shortened to 54 days with a total cost of Rp 606,803,619. As for increasing the number of workers, project work duration can be shortened to 54 working days with a total project cost Rp 604,556,748