资源约束下的多模式项目调度问题

IF 0.4 Q4 MANAGEMENT
Cansu Altintas, M. Azizoglu
{"title":"资源约束下的多模式项目调度问题","authors":"Cansu Altintas, M. Azizoglu","doi":"10.4018/IJITPM.2020010104","DOIUrl":null,"url":null,"abstract":"In this study, the authors consider a project scheduling problem with a single non-renewable resource. The authors assume that the resource is released at scheduled times and specified quantities and the resource is consumed at activity completion. The activities can be processed at different modes where a mode is defined by a processing time and a resource requirement amount. The problem is to select the modes and timings of the activities so as to minimize the project completion time. The authors give a mixed integer linear programming model and discuss some variable elimination mechanisms to enhance its efficiency.","PeriodicalId":43211,"journal":{"name":"International Journal of Information Technology Project Management","volume":null,"pages":null},"PeriodicalIF":0.4000,"publicationDate":"1900-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"4","resultStr":"{\"title\":\"A Resource Constrained Project Scheduling Problem With Multi-Modes\",\"authors\":\"Cansu Altintas, M. Azizoglu\",\"doi\":\"10.4018/IJITPM.2020010104\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In this study, the authors consider a project scheduling problem with a single non-renewable resource. The authors assume that the resource is released at scheduled times and specified quantities and the resource is consumed at activity completion. The activities can be processed at different modes where a mode is defined by a processing time and a resource requirement amount. The problem is to select the modes and timings of the activities so as to minimize the project completion time. The authors give a mixed integer linear programming model and discuss some variable elimination mechanisms to enhance its efficiency.\",\"PeriodicalId\":43211,\"journal\":{\"name\":\"International Journal of Information Technology Project Management\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.4000,\"publicationDate\":\"1900-01-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"4\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International Journal of Information Technology Project Management\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.4018/IJITPM.2020010104\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q4\",\"JCRName\":\"MANAGEMENT\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of Information Technology Project Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4018/IJITPM.2020010104","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"MANAGEMENT","Score":null,"Total":0}
引用次数: 4

摘要

在本研究中,作者考虑了单一不可再生资源的项目调度问题。作者假设资源在预定的时间和指定的数量被释放,资源在活动完成时被消耗。活动可以在不同的模式下进行处理,其中模式由处理时间和资源需求数量定义。问题是选择活动的模式和时间安排,以最小化项目完成时间。给出了一种混合整数线性规划模型,并讨论了一些变量消去机制以提高其效率。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
A Resource Constrained Project Scheduling Problem With Multi-Modes
In this study, the authors consider a project scheduling problem with a single non-renewable resource. The authors assume that the resource is released at scheduled times and specified quantities and the resource is consumed at activity completion. The activities can be processed at different modes where a mode is defined by a processing time and a resource requirement amount. The problem is to select the modes and timings of the activities so as to minimize the project completion time. The authors give a mixed integer linear programming model and discuss some variable elimination mechanisms to enhance its efficiency.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
CiteScore
1.70
自引率
25.00%
发文量
20
期刊介绍: The mission of International Journal of Information Technology Project Management (IJITPM) is to provide a forum for practitioners and researchers from both public and private sectors of project management professionals, along with information systems researchers, software developers and vendors, to contribute and to circulate ground-breaking work, and to shape future directions for research, as well as to help project leaders and managers apply various advanced techniques in information systems. It encourages discussions on how the various information systems can improve project management as well as how advances in project management can affect the growth of information systems.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信