Hawiyah Unayzah储气库远程工厂验收测试对项目进度、成本和质量的贡献

Mansour Al-Saidi, Hamad Al-Fouzan
{"title":"Hawiyah Unayzah储气库远程工厂验收测试对项目进度、成本和质量的贡献","authors":"Mansour Al-Saidi, Hamad Al-Fouzan","doi":"10.2523/iptc-22252-ea","DOIUrl":null,"url":null,"abstract":"\n This paper shares the Project Management Team's experience of conducting a Remote Factory Acceptance Test (Remote-FAT) at the Hawiyah Unayzah Gas Reservoir Storage project instead of the conventional approach of a conventional Factory Acceptance Test (FAT). The paper also highlights the advantages gained from a Remote-FAT, along with the value engineering created. In addition, this paper will present some deficiencies and areas of improvement. This shared experience is from the point of view as a PMT client or customer. At Hawiyah Unayzah Gas Reservoir Storage (HUGRS), the Remote-FAT approach was used with many disciplines, such as mechanical, electrical, pipelines, etc. This paper focuses on the process control system experience only, from 2020 to 2021. Meanwhile the HUGRS project is in progress and is expected to be completed by 2024.\n Conducting a FAT is one of the main milestones in projects. The conventional method is usually to have individuals physically visit the manufacturer to check and approve shipping the purchased devices/equipment to the project site. Sometimes this practice \"FAT\" takes place in the same country where the project is being constructed. But in other cases, the manufacturer is not even on the same continent, requiring travel of hundreds or thousands of kilometers. During COVID-19, there were many active projects that needed to conduct FAT activities, but travel was suddenly restricted. Therefore, the only option was to proceed with Remote-FAT. One of these running projects is HUGRS.\n The Remote-FAT is a virtual inspection check conducted by the client and vendor via online video streaming at the manufacturer location. Multiple cameras are used and located in different views to visualize whatever needs to be seen. In some cases, the Remote-FAT can be conducted through sharing a screen only, such as system graphics and logic test. The client and the vendor verify and conduct the test, following the same steps that they would perform in the conventional FAT. This Remote-FAT had already existed for a couple of years, but many project managers considered it as a fancy tool that did not add value. This evaluation was proven wrong by COVID-19. Remote-FAT has become the most convenient approach recently and adopted around the world. For the past two years, the process control systems engineers at HUGRS conducted many Remote-FATs with different vendors for dissimilar systems. The advantages and disadvantages were recorded as lessons learned — part of PMT practice — and will be shared in the next sections of this paper.","PeriodicalId":11027,"journal":{"name":"Day 3 Wed, February 23, 2022","volume":"10 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2022-02-21","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"The Contribution of Remote Factory Acceptance Test Towards Project's Schedule, Cost & Quality at Hawiyah Unayzah Gas Reservoir Storage\",\"authors\":\"Mansour Al-Saidi, Hamad Al-Fouzan\",\"doi\":\"10.2523/iptc-22252-ea\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n This paper shares the Project Management Team's experience of conducting a Remote Factory Acceptance Test (Remote-FAT) at the Hawiyah Unayzah Gas Reservoir Storage project instead of the conventional approach of a conventional Factory Acceptance Test (FAT). The paper also highlights the advantages gained from a Remote-FAT, along with the value engineering created. In addition, this paper will present some deficiencies and areas of improvement. This shared experience is from the point of view as a PMT client or customer. At Hawiyah Unayzah Gas Reservoir Storage (HUGRS), the Remote-FAT approach was used with many disciplines, such as mechanical, electrical, pipelines, etc. This paper focuses on the process control system experience only, from 2020 to 2021. Meanwhile the HUGRS project is in progress and is expected to be completed by 2024.\\n Conducting a FAT is one of the main milestones in projects. The conventional method is usually to have individuals physically visit the manufacturer to check and approve shipping the purchased devices/equipment to the project site. Sometimes this practice \\\"FAT\\\" takes place in the same country where the project is being constructed. But in other cases, the manufacturer is not even on the same continent, requiring travel of hundreds or thousands of kilometers. During COVID-19, there were many active projects that needed to conduct FAT activities, but travel was suddenly restricted. Therefore, the only option was to proceed with Remote-FAT. One of these running projects is HUGRS.\\n The Remote-FAT is a virtual inspection check conducted by the client and vendor via online video streaming at the manufacturer location. Multiple cameras are used and located in different views to visualize whatever needs to be seen. In some cases, the Remote-FAT can be conducted through sharing a screen only, such as system graphics and logic test. The client and the vendor verify and conduct the test, following the same steps that they would perform in the conventional FAT. This Remote-FAT had already existed for a couple of years, but many project managers considered it as a fancy tool that did not add value. This evaluation was proven wrong by COVID-19. Remote-FAT has become the most convenient approach recently and adopted around the world. For the past two years, the process control systems engineers at HUGRS conducted many Remote-FATs with different vendors for dissimilar systems. The advantages and disadvantages were recorded as lessons learned — part of PMT practice — and will be shared in the next sections of this paper.\",\"PeriodicalId\":11027,\"journal\":{\"name\":\"Day 3 Wed, February 23, 2022\",\"volume\":\"10 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-02-21\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 3 Wed, February 23, 2022\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2523/iptc-22252-ea\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 3 Wed, February 23, 2022","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2523/iptc-22252-ea","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

本文分享了项目管理团队在Hawiyah Unayzah气藏存储项目中进行远程工厂验收测试(Remote-FAT)的经验,而不是传统的工厂验收测试(FAT)方法。本文还强调了从Remote-FAT获得的优势,以及所创造的价值工程。此外,本文还将提出一些不足和需要改进的地方。这种共享的经验是从PMT客户或客户的角度来看的。在Hawiyah Unayzah天然气储层(HUGRS), Remote-FAT方法被用于许多学科,如机械、电气、管道等。本文只关注过程控制系统的经验,从2020年到2021年。与此同时,HUGRS项目正在进行中,预计将于2024年完工。进行评估是项目的主要里程碑之一。传统的方法通常是让个人亲自访问制造商,检查并批准将购买的设备/设备运送到项目现场。有时,这种“FAT”做法发生在正在建设项目的同一个国家。但在其他情况下,制造商甚至不在同一大洲,需要旅行数百或数千公里。在2019冠状病毒病期间,有许多需要开展FAT活动的活跃项目,但旅行突然受到限制。因此,唯一的选择就是继续使用Remote-FAT。其中一个正在运行的项目是HUGRS。Remote-FAT是由客户和供应商在制造商所在地通过在线视频流进行的虚拟检查。使用多个摄像头,并位于不同的视图,以可视化需要看到的任何东西。在某些情况下,Remote-FAT只能通过共享一个屏幕进行,例如系统图形和逻辑测试。客户和供应商验证并执行测试,遵循他们在传统FAT中执行的相同步骤。这种Remote-FAT已经存在了几年,但是许多项目经理认为它是一种花哨的工具,没有增加价值。这种评价被新冠肺炎疫情证明是错误的。远程fat已成为近年来最方便的方法,并在世界各地采用。在过去的两年中,HUGRS的过程控制系统工程师与不同的供应商就不同的系统进行了许多remote - fat。优点和缺点被记录为经验教训- PMT实践的一部分-并将在本文的下一部分中分享。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
The Contribution of Remote Factory Acceptance Test Towards Project's Schedule, Cost & Quality at Hawiyah Unayzah Gas Reservoir Storage
This paper shares the Project Management Team's experience of conducting a Remote Factory Acceptance Test (Remote-FAT) at the Hawiyah Unayzah Gas Reservoir Storage project instead of the conventional approach of a conventional Factory Acceptance Test (FAT). The paper also highlights the advantages gained from a Remote-FAT, along with the value engineering created. In addition, this paper will present some deficiencies and areas of improvement. This shared experience is from the point of view as a PMT client or customer. At Hawiyah Unayzah Gas Reservoir Storage (HUGRS), the Remote-FAT approach was used with many disciplines, such as mechanical, electrical, pipelines, etc. This paper focuses on the process control system experience only, from 2020 to 2021. Meanwhile the HUGRS project is in progress and is expected to be completed by 2024. Conducting a FAT is one of the main milestones in projects. The conventional method is usually to have individuals physically visit the manufacturer to check and approve shipping the purchased devices/equipment to the project site. Sometimes this practice "FAT" takes place in the same country where the project is being constructed. But in other cases, the manufacturer is not even on the same continent, requiring travel of hundreds or thousands of kilometers. During COVID-19, there were many active projects that needed to conduct FAT activities, but travel was suddenly restricted. Therefore, the only option was to proceed with Remote-FAT. One of these running projects is HUGRS. The Remote-FAT is a virtual inspection check conducted by the client and vendor via online video streaming at the manufacturer location. Multiple cameras are used and located in different views to visualize whatever needs to be seen. In some cases, the Remote-FAT can be conducted through sharing a screen only, such as system graphics and logic test. The client and the vendor verify and conduct the test, following the same steps that they would perform in the conventional FAT. This Remote-FAT had already existed for a couple of years, but many project managers considered it as a fancy tool that did not add value. This evaluation was proven wrong by COVID-19. Remote-FAT has become the most convenient approach recently and adopted around the world. For the past two years, the process control systems engineers at HUGRS conducted many Remote-FATs with different vendors for dissimilar systems. The advantages and disadvantages were recorded as lessons learned — part of PMT practice — and will be shared in the next sections of this paper.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信