尼日利亚拉各斯州公共和私人建筑项目延误原因的比较评估

D. S. Kadiri, A. Akintoye, B. Onabanjo
{"title":"尼日利亚拉各斯州公共和私人建筑项目延误原因的比较评估","authors":"D. S. Kadiri, A. Akintoye, B. Onabanjo","doi":"10.36108/ujees/9102.10.0240","DOIUrl":null,"url":null,"abstract":"Delay in the execution of construction projects is a major problem confronting the Nigerian construction industry. If unchecked, it will constitute a setback to the realisation of the infrastructure development component of the sustainable development agenda of the United Nations. This paper compared the causes of delay in public and private building projects in Lagos State, Nigeria with a view to enhancing project time performance. The study was conducted using a random sample of 87 Architectural firms and 88 contracting firms out of a population of 289 and 293, respectively in the study area. These represent 30% of the population of Architectural and contracting firms, in the study area. Data were retrieved from 47 Architectural and 48 contracting firms and analysed using mean score and student t-test. Results from the study indicated that delay in public building projects was mostly due to contractor’s financial difficulties with mean score (MS) of 2.84, rise in materials prices (MS = 2.80) and variations (MS = 2.72). On the other hand, client’s interference (MS = 2.92), rise in materials prices (MS = 2.83) and slow decision by clients (MS = 2.74) were the major causes of delay in private projects. T-test also revealed that the respondents were significantly different in opinion on 12 out of the 30 causes of delay in both project types in the study area.","PeriodicalId":23413,"journal":{"name":"UNIOSUN Journal of Engineering and Environmental Sciences","volume":"37 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-09-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"A Comparative Assessment of Causes of Delay in Public and Private Building Projects in Lagos State, Nigeria\",\"authors\":\"D. S. Kadiri, A. Akintoye, B. Onabanjo\",\"doi\":\"10.36108/ujees/9102.10.0240\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Delay in the execution of construction projects is a major problem confronting the Nigerian construction industry. If unchecked, it will constitute a setback to the realisation of the infrastructure development component of the sustainable development agenda of the United Nations. This paper compared the causes of delay in public and private building projects in Lagos State, Nigeria with a view to enhancing project time performance. The study was conducted using a random sample of 87 Architectural firms and 88 contracting firms out of a population of 289 and 293, respectively in the study area. These represent 30% of the population of Architectural and contracting firms, in the study area. Data were retrieved from 47 Architectural and 48 contracting firms and analysed using mean score and student t-test. Results from the study indicated that delay in public building projects was mostly due to contractor’s financial difficulties with mean score (MS) of 2.84, rise in materials prices (MS = 2.80) and variations (MS = 2.72). On the other hand, client’s interference (MS = 2.92), rise in materials prices (MS = 2.83) and slow decision by clients (MS = 2.74) were the major causes of delay in private projects. T-test also revealed that the respondents were significantly different in opinion on 12 out of the 30 causes of delay in both project types in the study area.\",\"PeriodicalId\":23413,\"journal\":{\"name\":\"UNIOSUN Journal of Engineering and Environmental Sciences\",\"volume\":\"37 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-09-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"UNIOSUN Journal of Engineering and Environmental Sciences\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.36108/ujees/9102.10.0240\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"UNIOSUN Journal of Engineering and Environmental Sciences","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.36108/ujees/9102.10.0240","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

建设项目的延迟执行是尼日利亚建筑业面临的一个主要问题。如果不加以制止,它将对实现联合国可持续发展议程的基础设施发展组成部分造成挫折。本文比较了尼日利亚拉各斯州公共和私人建筑项目延误的原因,以期提高项目的时间绩效。该研究是在研究地区的289家建筑公司和293家承包公司中随机抽取87家建筑公司和88家承包公司进行的。这些公司占研究区域建筑和承包公司总数的30%。数据来自47家建筑公司和48家承包公司,并使用平均分和学生t检验进行分析。研究结果显示,公共建筑工程延误的主要原因是承包商的财务困难,平均得分(MS)为2.84,材料价格上涨(MS = 2.80)和变化(MS = 2.72)。另一方面,客户的干扰(MS = 2.92)、材料价格上涨(MS = 2.83)和客户决策缓慢(MS = 2.74)是导致私人项目延误的主要原因。t检验还显示,在研究区域两种项目类型的30个延迟原因中,受访者对12个原因的意见存在显着差异。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
A Comparative Assessment of Causes of Delay in Public and Private Building Projects in Lagos State, Nigeria
Delay in the execution of construction projects is a major problem confronting the Nigerian construction industry. If unchecked, it will constitute a setback to the realisation of the infrastructure development component of the sustainable development agenda of the United Nations. This paper compared the causes of delay in public and private building projects in Lagos State, Nigeria with a view to enhancing project time performance. The study was conducted using a random sample of 87 Architectural firms and 88 contracting firms out of a population of 289 and 293, respectively in the study area. These represent 30% of the population of Architectural and contracting firms, in the study area. Data were retrieved from 47 Architectural and 48 contracting firms and analysed using mean score and student t-test. Results from the study indicated that delay in public building projects was mostly due to contractor’s financial difficulties with mean score (MS) of 2.84, rise in materials prices (MS = 2.80) and variations (MS = 2.72). On the other hand, client’s interference (MS = 2.92), rise in materials prices (MS = 2.83) and slow decision by clients (MS = 2.74) were the major causes of delay in private projects. T-test also revealed that the respondents were significantly different in opinion on 12 out of the 30 causes of delay in both project types in the study area.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信