{"title":"优化起下钻以减少油气钻井作业的平钻时间","authors":"Dagogo Sopriala Omubo","doi":"10.24940/ijird/2023/v12/i1/jan23016","DOIUrl":null,"url":null,"abstract":"Tripping, relating to oil and gas drilling operations, is a term used to describe running in or pulling out tubulars into or from an already drilled borehole. It is common to all well delivery operations in the oil and gas industry, including drilling, completions, work-over, and abandonment. \nBesides drilling a well that meets technical specifications in a safe manner and within the approved budget, well delivery success is not achieved if the specified time is exceeded. Time is an essential factor as it also has a large influence on cost. Well delivery time could be classified as either drilling time (time allotted to activities where the well depth increases with time) or flat time (time allotted to activities that do not directly contribute to an increase in well depth). \nFlat time reduction is a key strategy used to reduce oil and gas well delivery costs. This is applicable in drilling operations, specifically where well cost is directly proportional to time. There is ample room for drilling performance improvement by reducing flat time without eroding well quality. Oil and gas well delivery performance engineers are, therefore, constantly seeking ways to reduce flat time to the barest minimum. \nTripping optimization refers to the application of specific methods aimed at preventing technical issues while tripping and reducing tripping time. Tripping is one of the major contributors to flat time, with typically circa 8 to 10% of planned tripping time (exclusive of casing and completion running time) in drilling operations. This means tripping optimization has a direct effect on flat time reduction and, by extension, well cost reduction. \nThis article discusses various tripping optimization techniques and how they promote flat time reduction in oil and gas well drilling operations. It emphasizes how drilling operations can be more time-efficient and consequently cost-efficient by improved tripping practices.","PeriodicalId":14101,"journal":{"name":"International journal of innovative research and development","volume":"59 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-03-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Tripping Optimization to Promote Flat Time Reduction in Oil and Gas Well Drilling Operations\",\"authors\":\"Dagogo Sopriala Omubo\",\"doi\":\"10.24940/ijird/2023/v12/i1/jan23016\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Tripping, relating to oil and gas drilling operations, is a term used to describe running in or pulling out tubulars into or from an already drilled borehole. It is common to all well delivery operations in the oil and gas industry, including drilling, completions, work-over, and abandonment. \\nBesides drilling a well that meets technical specifications in a safe manner and within the approved budget, well delivery success is not achieved if the specified time is exceeded. Time is an essential factor as it also has a large influence on cost. Well delivery time could be classified as either drilling time (time allotted to activities where the well depth increases with time) or flat time (time allotted to activities that do not directly contribute to an increase in well depth). \\nFlat time reduction is a key strategy used to reduce oil and gas well delivery costs. This is applicable in drilling operations, specifically where well cost is directly proportional to time. There is ample room for drilling performance improvement by reducing flat time without eroding well quality. Oil and gas well delivery performance engineers are, therefore, constantly seeking ways to reduce flat time to the barest minimum. \\nTripping optimization refers to the application of specific methods aimed at preventing technical issues while tripping and reducing tripping time. Tripping is one of the major contributors to flat time, with typically circa 8 to 10% of planned tripping time (exclusive of casing and completion running time) in drilling operations. This means tripping optimization has a direct effect on flat time reduction and, by extension, well cost reduction. \\nThis article discusses various tripping optimization techniques and how they promote flat time reduction in oil and gas well drilling operations. It emphasizes how drilling operations can be more time-efficient and consequently cost-efficient by improved tripping practices.\",\"PeriodicalId\":14101,\"journal\":{\"name\":\"International journal of innovative research and development\",\"volume\":\"59 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-03-09\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International journal of innovative research and development\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.24940/ijird/2023/v12/i1/jan23016\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International journal of innovative research and development","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.24940/ijird/2023/v12/i1/jan23016","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

起下钻与石油和天然气钻井作业有关,是一个术语,用于描述将管柱下入或从已经钻探的井眼中取出。这在油气行业的所有井交付作业中都很常见,包括钻井、完井、修井和弃井。除了以安全的方式在批准的预算范围内钻出符合技术规范的井外,如果超过规定的时间,则无法成功交付井。时间是一个重要的因素,因为它对成本也有很大的影响。井的交付时间可以分为钻井时间(分配给井深随时间增加的活动的时间)或平坦时间(分配给不直接增加井深的活动的时间)。减少平井时间是降低油气井交付成本的关键策略。这适用于钻井作业,特别是钻井成本与时间成正比的作业。通过减少平井时间而不影响井质量,钻井性能有很大的改进空间。因此,油气井交付性能工程师不断寻求将平井时间减少到最低限度的方法。起下钻优化是指为了防止起下钻过程中出现技术问题,减少起下钻时间而采用的具体方法。起下钻是造成平钻时间的主要因素之一,通常约占钻井作业计划起下钻时间的8%至10%(不包括套管和完井作业时间)。这意味着起下钻优化可以直接减少平井时间,进而降低成本。本文讨论了各种起下钻优化技术,以及它们如何促进油气钻井作业中的平钻时间缩短。它强调了如何通过改进起下钻操作来提高钻井作业的时间效率和成本效益。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Tripping Optimization to Promote Flat Time Reduction in Oil and Gas Well Drilling Operations
Tripping, relating to oil and gas drilling operations, is a term used to describe running in or pulling out tubulars into or from an already drilled borehole. It is common to all well delivery operations in the oil and gas industry, including drilling, completions, work-over, and abandonment. Besides drilling a well that meets technical specifications in a safe manner and within the approved budget, well delivery success is not achieved if the specified time is exceeded. Time is an essential factor as it also has a large influence on cost. Well delivery time could be classified as either drilling time (time allotted to activities where the well depth increases with time) or flat time (time allotted to activities that do not directly contribute to an increase in well depth). Flat time reduction is a key strategy used to reduce oil and gas well delivery costs. This is applicable in drilling operations, specifically where well cost is directly proportional to time. There is ample room for drilling performance improvement by reducing flat time without eroding well quality. Oil and gas well delivery performance engineers are, therefore, constantly seeking ways to reduce flat time to the barest minimum. Tripping optimization refers to the application of specific methods aimed at preventing technical issues while tripping and reducing tripping time. Tripping is one of the major contributors to flat time, with typically circa 8 to 10% of planned tripping time (exclusive of casing and completion running time) in drilling operations. This means tripping optimization has a direct effect on flat time reduction and, by extension, well cost reduction. This article discusses various tripping optimization techniques and how they promote flat time reduction in oil and gas well drilling operations. It emphasizes how drilling operations can be more time-efficient and consequently cost-efficient by improved tripping practices.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信