{"title":"上游海上设施重量增长研究","authors":"Ray Rui, Jason B. Walker","doi":"10.2118/170696-PA","DOIUrl":null,"url":null,"abstract":"On the basis of our analysis and observations of projects in the database provided by Independent Project Analysis (IPA), one-half of topsides have more than 10% weight growth from authorization to completion, and more than one in three substructures have more than 10% weight growth from authorization to completion. Meanwhile, estimated contingency has a much narrower range compared with actual required contingency. To help the industry understand offshore-facility weight predictability, IPA recently conducted a comprehensive study that sheds new light on facility weight performance and identifies the root causes of weight growth, providing guidelines for improving predictability.","PeriodicalId":19446,"journal":{"name":"Oil and gas facilities","volume":"47 1","pages":"107-112"},"PeriodicalIF":0.0000,"publicationDate":"2015-04-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"4","resultStr":"{\"title\":\"Upstream Offshore-Facility Weight-Growth Study\",\"authors\":\"Ray Rui, Jason B. Walker\",\"doi\":\"10.2118/170696-PA\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"On the basis of our analysis and observations of projects in the database provided by Independent Project Analysis (IPA), one-half of topsides have more than 10% weight growth from authorization to completion, and more than one in three substructures have more than 10% weight growth from authorization to completion. Meanwhile, estimated contingency has a much narrower range compared with actual required contingency. To help the industry understand offshore-facility weight predictability, IPA recently conducted a comprehensive study that sheds new light on facility weight performance and identifies the root causes of weight growth, providing guidelines for improving predictability.\",\"PeriodicalId\":19446,\"journal\":{\"name\":\"Oil and gas facilities\",\"volume\":\"47 1\",\"pages\":\"107-112\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2015-04-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"4\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Oil and gas facilities\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/170696-PA\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Oil and gas facilities","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/170696-PA","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
On the basis of our analysis and observations of projects in the database provided by Independent Project Analysis (IPA), one-half of topsides have more than 10% weight growth from authorization to completion, and more than one in three substructures have more than 10% weight growth from authorization to completion. Meanwhile, estimated contingency has a much narrower range compared with actual required contingency. To help the industry understand offshore-facility weight predictability, IPA recently conducted a comprehensive study that sheds new light on facility weight performance and identifies the root causes of weight growth, providing guidelines for improving predictability.