{"title":"高层建筑工程延误原因调查及补救措施——以浦那为例","authors":"Kushal K.Panchariya","doi":"10.9790/9622-0707057277","DOIUrl":null,"url":null,"abstract":"At present, the approval processes involved in construction projects is complex all over country While undertaking construction projects like residential, commercial or industrial etc., it has been observed that obtaining clearances for the Building Projects has become cumbersome and lengthy. Overthepastdecade it has been observing that huge population enters into big cities like Pune for bread and butter, so there is tremendous demand for housing. This demand is fulfilled by developer, builder. But due to less availability of land, vertical construction is most demanding in the form of high rise buildings. But at the same time some sensitive issues like getting approvals on time and ground facts like delays in getting approvals need to be focus so customer will get its possession in time from developer and at the same time builder shall not incur losses due to delay in sanctioning of approvals as it plays magnificent role.","PeriodicalId":13972,"journal":{"name":"International Journal of Engineering Research and Applications","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2017-07-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Investigation of Causes of Delay in High Rise Building Project and Remedial Measures Case Study-Pune\",\"authors\":\"Kushal K.Panchariya\",\"doi\":\"10.9790/9622-0707057277\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"At present, the approval processes involved in construction projects is complex all over country While undertaking construction projects like residential, commercial or industrial etc., it has been observed that obtaining clearances for the Building Projects has become cumbersome and lengthy. Overthepastdecade it has been observing that huge population enters into big cities like Pune for bread and butter, so there is tremendous demand for housing. This demand is fulfilled by developer, builder. But due to less availability of land, vertical construction is most demanding in the form of high rise buildings. But at the same time some sensitive issues like getting approvals on time and ground facts like delays in getting approvals need to be focus so customer will get its possession in time from developer and at the same time builder shall not incur losses due to delay in sanctioning of approvals as it plays magnificent role.\",\"PeriodicalId\":13972,\"journal\":{\"name\":\"International Journal of Engineering Research and Applications\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2017-07-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"International Journal of Engineering Research and Applications\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.9790/9622-0707057277\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"International Journal of Engineering Research and Applications","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.9790/9622-0707057277","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

目前,在全国范围内,建筑项目的审批程序是复杂的。在从事住宅、商业或工业等建筑项目时,人们发现获得建筑项目的许可已经变得繁琐和漫长。在过去的十年里,它观察到大量人口进入像浦那这样的大城市是为了面包和黄油,因此对住房有巨大的需求。这种需求由开发商、建筑商来满足。但由于可用土地较少,高层建筑形式的垂直建筑要求最高。但与此同时,需要关注一些敏感问题,如按时获得批准和延迟获得批准等基本事实,以便客户及时从开发商手中获得所有权,同时建筑商不会因批准延迟而蒙受损失,因为它发挥着重要作用。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Investigation of Causes of Delay in High Rise Building Project and Remedial Measures Case Study-Pune
At present, the approval processes involved in construction projects is complex all over country While undertaking construction projects like residential, commercial or industrial etc., it has been observed that obtaining clearances for the Building Projects has become cumbersome and lengthy. Overthepastdecade it has been observing that huge population enters into big cities like Pune for bread and butter, so there is tremendous demand for housing. This demand is fulfilled by developer, builder. But due to less availability of land, vertical construction is most demanding in the form of high rise buildings. But at the same time some sensitive issues like getting approvals on time and ground facts like delays in getting approvals need to be focus so customer will get its possession in time from developer and at the same time builder shall not incur losses due to delay in sanctioning of approvals as it plays magnificent role.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信