{"title":"建设项目挣值分析要点","authors":"B. Costa, Jorge G. Farías, Mohammad K. Najjar, Mayara Amario, C. A. Soares, A. Haddad","doi":"10.4028/p-6emexf","DOIUrl":null,"url":null,"abstract":"Construction projects are typically carried out under high-risk conditions and managers are forced to handle a great deal of uncertainty during the construction process. The Earned-Value Analysis is a control technique that provides early warnings of performance by quantitative measures, enabling timely corrective actions to ensure project success. This method was developed to control and adjust the project's baseline during execution. The objective of this article is to discuss the main implications of using EVA in construction projects through a case study. Results proved the applicability of the method in the construction industry. The various indicators generated allow managers to make forecasts for optimistic, realistic, and pessimistic scenarios, having the opportunity to correct any deviations in advance. In addition to forecasts, benchmarking data can be generated for the planners or companies responsible for the project, thus increasing the accuracy of future projects.","PeriodicalId":34329,"journal":{"name":"Journal of Electrical and Computer Engineering Innovations","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2022-06-20","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Highlights of Earned Value Analysis in Construction Projects\",\"authors\":\"B. Costa, Jorge G. Farías, Mohammad K. Najjar, Mayara Amario, C. A. Soares, A. Haddad\",\"doi\":\"10.4028/p-6emexf\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Construction projects are typically carried out under high-risk conditions and managers are forced to handle a great deal of uncertainty during the construction process. The Earned-Value Analysis is a control technique that provides early warnings of performance by quantitative measures, enabling timely corrective actions to ensure project success. This method was developed to control and adjust the project's baseline during execution. The objective of this article is to discuss the main implications of using EVA in construction projects through a case study. Results proved the applicability of the method in the construction industry. The various indicators generated allow managers to make forecasts for optimistic, realistic, and pessimistic scenarios, having the opportunity to correct any deviations in advance. In addition to forecasts, benchmarking data can be generated for the planners or companies responsible for the project, thus increasing the accuracy of future projects.\",\"PeriodicalId\":34329,\"journal\":{\"name\":\"Journal of Electrical and Computer Engineering Innovations\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-06-20\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Electrical and Computer Engineering Innovations\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.4028/p-6emexf\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Electrical and Computer Engineering Innovations","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.4028/p-6emexf","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

建设项目通常是在高风险的条件下进行的,管理者在施工过程中被迫处理大量的不确定性。挣值分析是一种控制技术,它通过定量测量提供早期的性能警告,使及时的纠正行动能够确保项目的成功。开发这种方法是为了在执行过程中控制和调整项目的基线。本文的目的是通过一个案例研究来讨论在建设项目中使用EVA的主要含义。结果证明了该方法在建筑业中的适用性。生成的各种指标允许管理人员对乐观、现实和悲观的情景做出预测,并有机会提前纠正任何偏差。除了预测之外,还可以为负责项目的规划者或公司生成基准数据,从而提高未来项目的准确性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Highlights of Earned Value Analysis in Construction Projects
Construction projects are typically carried out under high-risk conditions and managers are forced to handle a great deal of uncertainty during the construction process. The Earned-Value Analysis is a control technique that provides early warnings of performance by quantitative measures, enabling timely corrective actions to ensure project success. This method was developed to control and adjust the project's baseline during execution. The objective of this article is to discuss the main implications of using EVA in construction projects through a case study. Results proved the applicability of the method in the construction industry. The various indicators generated allow managers to make forecasts for optimistic, realistic, and pessimistic scenarios, having the opportunity to correct any deviations in advance. In addition to forecasts, benchmarking data can be generated for the planners or companies responsible for the project, thus increasing the accuracy of future projects.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
审稿时长
12 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信