{"title":"甘肃甘榜木瑞微型水力发电厂可行性规划研究","authors":"Rizky Monica Virgine, R. Setiabudy","doi":"10.1109/ICHVEPS47643.2019.9011085","DOIUrl":null,"url":null,"abstract":"Kampung Mului is one of the villages in the area of Paser, East Kalimantan. Kampung Mului has not received electricity from PLN so that people who lived in there use generator set for daily needs. Kampung Mului conditions is a fundamental reason for the empowering potential of a waterfall in Kampung Mului be a source of Micro Hydro Power (MHP). In this study, discussed the feasibility of investing MHP economically use comparative expenses Village MHP Mului 20 years of operation with the public electricity expenses Kampung Mului if not wearing the MHP The results of the research show the potential power of Kampung Mului waterfall is 116.08 kW and electricity needs of Kampung Mului is 19,92 kW. The cost of using Kampung Mului community using a generator set is bigger than the cost of using PLTMH which is Rp 2.791.210.000, if using underground cable and Rp 1.394.110.000, - if using ACSR cable. Based on this, the development of PLTMH Kampung Mului is feasible to be implemented in economic terms. This study can be applied and helps the electricity problem in Kampung Mului.","PeriodicalId":6677,"journal":{"name":"2019 2nd International Conference on High Voltage Engineering and Power Systems (ICHVEPS)","volume":"23 1","pages":"163-168"},"PeriodicalIF":0.0000,"publicationDate":"2019-10-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Study of Feasibility Planning Micro Hydro Power Plant in Kampung Mului, Paser\",\"authors\":\"Rizky Monica Virgine, R. Setiabudy\",\"doi\":\"10.1109/ICHVEPS47643.2019.9011085\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Kampung Mului is one of the villages in the area of Paser, East Kalimantan. Kampung Mului has not received electricity from PLN so that people who lived in there use generator set for daily needs. Kampung Mului conditions is a fundamental reason for the empowering potential of a waterfall in Kampung Mului be a source of Micro Hydro Power (MHP). In this study, discussed the feasibility of investing MHP economically use comparative expenses Village MHP Mului 20 years of operation with the public electricity expenses Kampung Mului if not wearing the MHP The results of the research show the potential power of Kampung Mului waterfall is 116.08 kW and electricity needs of Kampung Mului is 19,92 kW. The cost of using Kampung Mului community using a generator set is bigger than the cost of using PLTMH which is Rp 2.791.210.000, if using underground cable and Rp 1.394.110.000, - if using ACSR cable. Based on this, the development of PLTMH Kampung Mului is feasible to be implemented in economic terms. This study can be applied and helps the electricity problem in Kampung Mului.\",\"PeriodicalId\":6677,\"journal\":{\"name\":\"2019 2nd International Conference on High Voltage Engineering and Power Systems (ICHVEPS)\",\"volume\":\"23 1\",\"pages\":\"163-168\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-10-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2019 2nd International Conference on High Voltage Engineering and Power Systems (ICHVEPS)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ICHVEPS47643.2019.9011085\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2019 2nd International Conference on High Voltage Engineering and Power Systems (ICHVEPS)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICHVEPS47643.2019.9011085","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1
摘要
Kampung Mului是东加里曼丹Paser地区的一个村庄。甘榜木赖没有从PLN获得电力,因此居住在那里的人们使用发电机组满足日常需求。甘榜木瑞的条件是甘榜木瑞瀑布成为微型水力发电(MHP)来源的一个根本原因。在本研究中,讨论了投资MHP经济使用的可行性比较费用村MHP木瑞20年运行与公共电力费用甘邦木瑞如果不使用MHP,研究结果表明,甘邦木瑞瀑布的潜在功率为116.08 kW,甘邦木瑞的电力需求为19.92 kW。使用Kampung Mului社区使用发电机组的成本大于使用PLTMH的成本,如果使用地下电缆,PLTMH的成本为2.791.21万卢比,如果使用ACSR电缆,PLTMH的成本为1.394.11万卢比。基于此,PLTMH甘榜木瑞的开发在经济上是可行的。该研究可以应用于甘榜木瑞的电力问题。
Study of Feasibility Planning Micro Hydro Power Plant in Kampung Mului, Paser
Kampung Mului is one of the villages in the area of Paser, East Kalimantan. Kampung Mului has not received electricity from PLN so that people who lived in there use generator set for daily needs. Kampung Mului conditions is a fundamental reason for the empowering potential of a waterfall in Kampung Mului be a source of Micro Hydro Power (MHP). In this study, discussed the feasibility of investing MHP economically use comparative expenses Village MHP Mului 20 years of operation with the public electricity expenses Kampung Mului if not wearing the MHP The results of the research show the potential power of Kampung Mului waterfall is 116.08 kW and electricity needs of Kampung Mului is 19,92 kW. The cost of using Kampung Mului community using a generator set is bigger than the cost of using PLTMH which is Rp 2.791.210.000, if using underground cable and Rp 1.394.110.000, - if using ACSR cable. Based on this, the development of PLTMH Kampung Mului is feasible to be implemented in economic terms. This study can be applied and helps the electricity problem in Kampung Mului.