油田产能限制下的气举优化

Uche Chukwunonso Ifeanyi, Samuel Esieboma, Jennifer Uche
{"title":"油田产能限制下的气举优化","authors":"Uche Chukwunonso Ifeanyi, Samuel Esieboma, Jennifer Uche","doi":"10.2118/198744-MS","DOIUrl":null,"url":null,"abstract":"\n Optimizing oil production with facility constraints has become a challenge to most E&P companies even as they pursue sustainable resources. The innovative gas lift technique overcomes this challenge. The conventional gas lift well system has long been in use, but the design most times is limited by gas availability and pressure which limits the depth of gas lift injection for improved production rates. This challenge may not be evident in matured producing fields with gas compressors installed with available non-associated gas source wells, but truly such challenges arise in new fields especially owned by indigenous companies where much uncertainties at an early field life unavoidably allows you to be more stringent in expenditures towards development of a field gas lift project. A new gas lift concept was developed and studied in Field A in an offshore field of the Niger delta in the absence of gas compressors. This design has been proven to be suitable because it was used to bring four closed wells online even when those wells were removed from the company annual forecast. The original design consists of a minimum of two unloading valves and an orifice at a deeper depth, but because of the absence of scrubbers and gas compressors in the facility, pressure depletion in the reservoirs caused four flowing wells to be closed. The new design then sets dummy at shallow mandrels and uses a modified size of orifice to optimize available pressure and gas required to open the closed wells and still sustain other gas lifted wells connected to the same gas lift manifold. This campaign resulted to an additional 7000Bopd which is the primary discussion of this paper.","PeriodicalId":11110,"journal":{"name":"Day 2 Tue, August 06, 2019","volume":"60 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-08-05","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Gas Lift Optimization within Field Capacity Limitations\",\"authors\":\"Uche Chukwunonso Ifeanyi, Samuel Esieboma, Jennifer Uche\",\"doi\":\"10.2118/198744-MS\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\n Optimizing oil production with facility constraints has become a challenge to most E&P companies even as they pursue sustainable resources. The innovative gas lift technique overcomes this challenge. The conventional gas lift well system has long been in use, but the design most times is limited by gas availability and pressure which limits the depth of gas lift injection for improved production rates. This challenge may not be evident in matured producing fields with gas compressors installed with available non-associated gas source wells, but truly such challenges arise in new fields especially owned by indigenous companies where much uncertainties at an early field life unavoidably allows you to be more stringent in expenditures towards development of a field gas lift project. A new gas lift concept was developed and studied in Field A in an offshore field of the Niger delta in the absence of gas compressors. This design has been proven to be suitable because it was used to bring four closed wells online even when those wells were removed from the company annual forecast. The original design consists of a minimum of two unloading valves and an orifice at a deeper depth, but because of the absence of scrubbers and gas compressors in the facility, pressure depletion in the reservoirs caused four flowing wells to be closed. The new design then sets dummy at shallow mandrels and uses a modified size of orifice to optimize available pressure and gas required to open the closed wells and still sustain other gas lifted wells connected to the same gas lift manifold. This campaign resulted to an additional 7000Bopd which is the primary discussion of this paper.\",\"PeriodicalId\":11110,\"journal\":{\"name\":\"Day 2 Tue, August 06, 2019\",\"volume\":\"60 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-08-05\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Day 2 Tue, August 06, 2019\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2118/198744-MS\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Day 2 Tue, August 06, 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2118/198744-MS","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

摘要

在设施限制的情况下优化石油产量已经成为大多数勘探开发公司面临的挑战,即使他们追求可持续资源。创新的气举技术克服了这一挑战。传统的气举井系统已经使用了很长时间,但大多数时候的设计受到气体可用性和压力的限制,这限制了气举注入的深度,以提高产量。这一挑战在成熟的生产油田中可能并不明显,因为这些油田安装了气体压缩机和可用的非伴生气源井,但在新油田,特别是本土公司拥有的新油田中,这种挑战确实会出现,因为这些油田早期的许多不确定性不可避免地会让你在开发气田气举项目时更加严格地控制支出。在尼日尔三角洲海上油田的A油田,在没有气体压缩机的情况下,开发和研究了一种新的气举概念。这种设计已被证明是合适的,因为它使4口关闭的井上线,即使这些井已从公司的年度预测中删除。最初的设计包括至少两个卸载阀和一个较深的孔板,但由于设施中没有洗涤器和气体压缩机,储层的压力耗尽导致4口流动井关闭。然后,新设计将假人设置在浅心轴上,并使用修改尺寸的孔板来优化打开关闭井所需的可用压力和气体,同时仍然维持连接到同一气举歧管的其他气举井。这一举措带来了额外的7000桶/天的产量,这是本文的主要讨论内容。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Gas Lift Optimization within Field Capacity Limitations
Optimizing oil production with facility constraints has become a challenge to most E&P companies even as they pursue sustainable resources. The innovative gas lift technique overcomes this challenge. The conventional gas lift well system has long been in use, but the design most times is limited by gas availability and pressure which limits the depth of gas lift injection for improved production rates. This challenge may not be evident in matured producing fields with gas compressors installed with available non-associated gas source wells, but truly such challenges arise in new fields especially owned by indigenous companies where much uncertainties at an early field life unavoidably allows you to be more stringent in expenditures towards development of a field gas lift project. A new gas lift concept was developed and studied in Field A in an offshore field of the Niger delta in the absence of gas compressors. This design has been proven to be suitable because it was used to bring four closed wells online even when those wells were removed from the company annual forecast. The original design consists of a minimum of two unloading valves and an orifice at a deeper depth, but because of the absence of scrubbers and gas compressors in the facility, pressure depletion in the reservoirs caused four flowing wells to be closed. The new design then sets dummy at shallow mandrels and uses a modified size of orifice to optimize available pressure and gas required to open the closed wells and still sustain other gas lifted wells connected to the same gas lift manifold. This campaign resulted to an additional 7000Bopd which is the primary discussion of this paper.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信