{"title":"具有设置时间和机器可用时间的并行多用途机器上的高多重作业调度","authors":"Caixia Jing, Wanzhen Huang, Lei Zhang, Heng Zhang","doi":"10.1142/s0217595922500129","DOIUrl":null,"url":null,"abstract":"In this paper, we consider the scheduling of high multiplicity jobs on parallel multi-purpose machines with setup times and machine available times, with the objective of minimizing makespan. High multiplicity means that jobs are partitioned into several groups and in each group all jobs are identical. Whenever there is a switch from processing a job of one group to a job of another group, a setup time is needed. Multi-purpose machine implies that each job can only be processed by a specific subset of all the machines, called processing set. A mixed integer programming is formulated for this NP-hard problem. A heuristic is proposed to solve the problem. Lower bounds are developed to evaluate the heuristic algorithm. Extensive numerical computations are performed and the results show that the heuristic generates solutions with makespan within 2% above the lower bounds in average, and outperforms CPLEX 12.6 for large scale and complex problems.","PeriodicalId":8478,"journal":{"name":"Asia Pac. J. Oper. Res.","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2022-04-05","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Scheduling High Multiplicity Jobs on Parallel Multi-Purpose Machines with Setup Times and Machine Available Times\",\"authors\":\"Caixia Jing, Wanzhen Huang, Lei Zhang, Heng Zhang\",\"doi\":\"10.1142/s0217595922500129\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In this paper, we consider the scheduling of high multiplicity jobs on parallel multi-purpose machines with setup times and machine available times, with the objective of minimizing makespan. High multiplicity means that jobs are partitioned into several groups and in each group all jobs are identical. Whenever there is a switch from processing a job of one group to a job of another group, a setup time is needed. Multi-purpose machine implies that each job can only be processed by a specific subset of all the machines, called processing set. A mixed integer programming is formulated for this NP-hard problem. A heuristic is proposed to solve the problem. Lower bounds are developed to evaluate the heuristic algorithm. Extensive numerical computations are performed and the results show that the heuristic generates solutions with makespan within 2% above the lower bounds in average, and outperforms CPLEX 12.6 for large scale and complex problems.\",\"PeriodicalId\":8478,\"journal\":{\"name\":\"Asia Pac. J. Oper. Res.\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2022-04-05\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Asia Pac. J. Oper. Res.\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1142/s0217595922500129\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Asia Pac. J. Oper. Res.","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1142/s0217595922500129","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
Scheduling High Multiplicity Jobs on Parallel Multi-Purpose Machines with Setup Times and Machine Available Times
In this paper, we consider the scheduling of high multiplicity jobs on parallel multi-purpose machines with setup times and machine available times, with the objective of minimizing makespan. High multiplicity means that jobs are partitioned into several groups and in each group all jobs are identical. Whenever there is a switch from processing a job of one group to a job of another group, a setup time is needed. Multi-purpose machine implies that each job can only be processed by a specific subset of all the machines, called processing set. A mixed integer programming is formulated for this NP-hard problem. A heuristic is proposed to solve the problem. Lower bounds are developed to evaluate the heuristic algorithm. Extensive numerical computations are performed and the results show that the heuristic generates solutions with makespan within 2% above the lower bounds in average, and outperforms CPLEX 12.6 for large scale and complex problems.