{"title":"巴基斯坦公路项目延误的原因识别和最小化","authors":"S. Sohu, A. Chandio, K. Ullah","doi":"10.22581/muet1982.1901.09","DOIUrl":null,"url":null,"abstract":"The problem of delay in construction industry is a regular phenomenon worldwide, and construction industry of Pakistan has no exception, particularly in highways projects. Delay can be described as the extension of time to complete the construction project. The aim of this paper is to identify main causes of delays in highway projects of Pakistan, and to determine mitigating measures for the identified causes. The research method of this study is based on literature review, questionnaire survey and semi structured interview. From in-depth literature review, twenty-six common causes of delay were found. A questionnaire survey was carried out among construction professionals of highway projects. The causes of delay in highways projects were ranked referring to their Mean values. A semi structured interview was carried out to determine mitigation measures for the top ten causes of delays. The data gathered from questionnaire survey was analyzed using SPSS (Statistical Package for the Social Sciences) while, data collected through semi structured interviews was analyzed using Nvivo software. The findings of this study are expected to be useful for construction parties, to mitigate the delays in highway construction projects of Pakistan.","PeriodicalId":13063,"journal":{"name":"Hygeia J. D.Med.10 (1) August 2018 - January 2019","volume":"222 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2019-01-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"8","resultStr":"{\"title\":\"Identification of Causes and Minimization of Delays in Highway Projects of Pakistan\",\"authors\":\"S. Sohu, A. Chandio, K. Ullah\",\"doi\":\"10.22581/muet1982.1901.09\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"The problem of delay in construction industry is a regular phenomenon worldwide, and construction industry of Pakistan has no exception, particularly in highways projects. Delay can be described as the extension of time to complete the construction project. The aim of this paper is to identify main causes of delays in highway projects of Pakistan, and to determine mitigating measures for the identified causes. The research method of this study is based on literature review, questionnaire survey and semi structured interview. From in-depth literature review, twenty-six common causes of delay were found. A questionnaire survey was carried out among construction professionals of highway projects. The causes of delay in highways projects were ranked referring to their Mean values. A semi structured interview was carried out to determine mitigation measures for the top ten causes of delays. The data gathered from questionnaire survey was analyzed using SPSS (Statistical Package for the Social Sciences) while, data collected through semi structured interviews was analyzed using Nvivo software. The findings of this study are expected to be useful for construction parties, to mitigate the delays in highway construction projects of Pakistan.\",\"PeriodicalId\":13063,\"journal\":{\"name\":\"Hygeia J. D.Med.10 (1) August 2018 - January 2019\",\"volume\":\"222 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-01-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"8\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Hygeia J. D.Med.10 (1) August 2018 - January 2019\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.22581/muet1982.1901.09\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Hygeia J. D.Med.10 (1) August 2018 - January 2019","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.22581/muet1982.1901.09","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 8
摘要
建筑业的延误问题是世界范围内的普遍现象,巴基斯坦建筑业也不例外,特别是公路工程。延迟可以被描述为完成建设项目的时间的延长。本文的目的是确定巴基斯坦公路项目延误的主要原因,并确定缓解措施的确定原因。本研究的研究方法为文献研究法、问卷调查法和半结构化访谈法。通过深入的文献回顾,我们发现了26种常见的延迟原因。对公路工程施工专业人员进行问卷调查。根据其平均值对公路项目延误原因进行排序。进行了半结构化访谈,以确定十大延误原因的缓解措施。问卷调查收集的数据使用SPSS (Statistical Package for Social Sciences)进行分析,半结构化访谈收集的数据使用Nvivo软件进行分析。本研究的结果有望对建设方有所帮助,以减轻巴基斯坦公路建设项目的延误。
Identification of Causes and Minimization of Delays in Highway Projects of Pakistan
The problem of delay in construction industry is a regular phenomenon worldwide, and construction industry of Pakistan has no exception, particularly in highways projects. Delay can be described as the extension of time to complete the construction project. The aim of this paper is to identify main causes of delays in highway projects of Pakistan, and to determine mitigating measures for the identified causes. The research method of this study is based on literature review, questionnaire survey and semi structured interview. From in-depth literature review, twenty-six common causes of delay were found. A questionnaire survey was carried out among construction professionals of highway projects. The causes of delay in highways projects were ranked referring to their Mean values. A semi structured interview was carried out to determine mitigation measures for the top ten causes of delays. The data gathered from questionnaire survey was analyzed using SPSS (Statistical Package for the Social Sciences) while, data collected through semi structured interviews was analyzed using Nvivo software. The findings of this study are expected to be useful for construction parties, to mitigate the delays in highway construction projects of Pakistan.