资源约束下施工调度问题的精确解

B. Sroka, E. Radziszewska-Zielina
{"title":"资源约束下施工调度问题的精确解","authors":"B. Sroka, E. Radziszewska-Zielina","doi":"10.3846/2029882X.2016.1196916","DOIUrl":null,"url":null,"abstract":"AbstractReduced time and, by the same token, the cost of the project is a crucial factor in contemporary construction. This article presents a method for the exact optimisation of a resource-constrained scheduling problem. Based on the Critical Path Method, graph theory and linear programming, an algorithm was developed and the FROPT program was written in Matlab to minimise the execution time of the task. By using the newly-created program, sample networks were calculated and the results were compared with results obtained by using the MS Project scheduling program (using approximation algorithm). The execution time obtained by using FROPT were on average 10% shorter than those obtained using MS Project. In selected cases the improvement in execution time reached 25%. A deterministic approach to the problem may shorten planned project times and bring financial benefits. Due to the exponential complexity of the algorithm, it is most useful in solving small or highly coherent networks. The algorithm and pr...","PeriodicalId":11839,"journal":{"name":"Engineering Structures and Technologies","volume":"8 1","pages":"71-78"},"PeriodicalIF":0.0000,"publicationDate":"2016-07-07","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://sci-hub-pdf.com/10.3846/2029882X.2016.1196916","citationCount":"0","resultStr":"{\"title\":\"An exact solution for the resource-constrained construction scheduling problem\",\"authors\":\"B. Sroka, E. Radziszewska-Zielina\",\"doi\":\"10.3846/2029882X.2016.1196916\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"AbstractReduced time and, by the same token, the cost of the project is a crucial factor in contemporary construction. This article presents a method for the exact optimisation of a resource-constrained scheduling problem. Based on the Critical Path Method, graph theory and linear programming, an algorithm was developed and the FROPT program was written in Matlab to minimise the execution time of the task. By using the newly-created program, sample networks were calculated and the results were compared with results obtained by using the MS Project scheduling program (using approximation algorithm). The execution time obtained by using FROPT were on average 10% shorter than those obtained using MS Project. In selected cases the improvement in execution time reached 25%. A deterministic approach to the problem may shorten planned project times and bring financial benefits. Due to the exponential complexity of the algorithm, it is most useful in solving small or highly coherent networks. The algorithm and pr...\",\"PeriodicalId\":11839,\"journal\":{\"name\":\"Engineering Structures and Technologies\",\"volume\":\"8 1\",\"pages\":\"71-78\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2016-07-07\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"https://sci-hub-pdf.com/10.3846/2029882X.2016.1196916\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Engineering Structures and Technologies\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.3846/2029882X.2016.1196916\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Engineering Structures and Technologies","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.3846/2029882X.2016.1196916","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

摘要:在当代建筑中,缩短时间和降低工程成本是一个至关重要的因素。本文提出了一种精确优化资源约束调度问题的方法。基于关键路径法、图论和线性规划,开发了一种算法,并在Matlab中编写了FROPT程序,使任务的执行时间最小化。利用新编写的程序对样本网络进行了计算,并与MS Project调度程序(采用近似算法)得到的结果进行了比较。使用FROPT获得的执行时间比使用MS Project获得的执行时间平均缩短10%。在某些情况下,执行时间的改进达到25%。解决问题的确定性方法可以缩短计划的项目时间并带来经济效益。由于该算法的指数复杂度,它在求解小型或高度相干的网络时最有用。算法和pr…
本文章由计算机程序翻译,如有差异,请以英文原文为准。
An exact solution for the resource-constrained construction scheduling problem
AbstractReduced time and, by the same token, the cost of the project is a crucial factor in contemporary construction. This article presents a method for the exact optimisation of a resource-constrained scheduling problem. Based on the Critical Path Method, graph theory and linear programming, an algorithm was developed and the FROPT program was written in Matlab to minimise the execution time of the task. By using the newly-created program, sample networks were calculated and the results were compared with results obtained by using the MS Project scheduling program (using approximation algorithm). The execution time obtained by using FROPT were on average 10% shorter than those obtained using MS Project. In selected cases the improvement in execution time reached 25%. A deterministic approach to the problem may shorten planned project times and bring financial benefits. Due to the exponential complexity of the algorithm, it is most useful in solving small or highly coherent networks. The algorithm and pr...
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
2
审稿时长
15 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信