{"title":"在X城Tangerang医院的800 kVA配送的周期性治疗分析","authors":"Ridho Alpha Kusuma, J. Prayogo, Choirul Mufit","doi":"10.26623/elektrika.v15i1.6478","DOIUrl":null,"url":null,"abstract":"In Indonesia, electricity supply for buildings or buildings with needs above 200kVA requires a distribution transformer owned by the customer, so that electrical energy transactions are carried out on the medium voltage side of 20kV. The distribution transformer in a hospital is a very vital component, especially during the COVID-19 pandemic where transformers are forced to continue operating above nominal levels without any maintenance. Distribution transformer maintenance includes visual inspection, monthly maintenance, maintenance every six months and annual maintenance. Treatments carried out on distribution transformers at X Hospital are DGA (Dissolved Gasses Analysis), transformer insulation testing, TTR (Transformer Turn Ratio) testing, Breakdown Voltage testing, thermovision testing and Winding Resistance testing; In addition, treatment or purification of transformer oil is also carried out based on testing. all dissolved gas and total dissolved gas (TDCG) decreased after the purification process and after purification there is still residual dissolved gas in the transformer. Interpretation of dissolved gas data (DGA) using several methods indicates a \"Thermal Fault > 300 Celsius\". This is in line with the results of thermovision on the transformer which shows a hot spot at the termination of the HV phase W bushing. Confirmation of this suspect will be checked after repairing the termination. Keywords: Distribution Transformer, Transformer, Maintenance. ABSTRAKDi Indonesia, suplai kelistrikan untuk bangunan atau gedung dengan kebutuhan diatas 200kVA maka diperlukan trafo distribusi yang dimiliki oleh pelanggan, sehingga transaksi energi listrik dilakukan di sisi tegangan menengah 20kV. Trafo distribusi di sebuah rumah sakit merupakan suatu komponen yang sangat vital, terutama selama masa pandemic COVID-19 dimana trafo dipaksa untuk tetap beroperasi diatas narus nominal tanpa adanya perawatan. Perawatan trafo distribusi meliputi inspeksi visual, perawatan bulanan, perawatan tiap enam bulan dan perawatan tahunan. Perawatan yang dilakukan di trafo distribusi di Rumah Sakit X ini adalah DGA (Dissolved Gasses Analysis), pengujian insulasi trafo, pengujian TTR (Transformer Turn Ratio), pengujian Breakdown Voltage, pengujian thermovision dan pengujian Winding Resistance, selain itu juga dilakukan treatment atau purifikasi oli trafo Berdasarkan pengujian. semua gas terlarut dan total gas terlarut (TDCG) menurun setelah proses pemurnian dan setelah pemurnian masih ada sisa gas terlarut di trafo. Interpretasi data gas terlarut (DGA) dengan beberapa metode menunjukkan adanya “Termal Fault > 300 Celcius”. Hal ini sejalan dengan hasil thermovision pada trafo yang menunjukkan adanya hot spot pada bagian terminasi busing W fasa HV. Konfirmasi tersangka ini akan dilakukan pengecekan setelah dilakukan perbaikan terminasi.","PeriodicalId":31998,"journal":{"name":"Elektrika","volume":"1 1","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2023-05-03","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Analisis Perawatan Berkala Trafo Distribusi 800 kVA pada Rumah Sakit X Kota Tangerang\",\"authors\":\"Ridho Alpha Kusuma, J. Prayogo, Choirul Mufit\",\"doi\":\"10.26623/elektrika.v15i1.6478\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"In Indonesia, electricity supply for buildings or buildings with needs above 200kVA requires a distribution transformer owned by the customer, so that electrical energy transactions are carried out on the medium voltage side of 20kV. The distribution transformer in a hospital is a very vital component, especially during the COVID-19 pandemic where transformers are forced to continue operating above nominal levels without any maintenance. Distribution transformer maintenance includes visual inspection, monthly maintenance, maintenance every six months and annual maintenance. Treatments carried out on distribution transformers at X Hospital are DGA (Dissolved Gasses Analysis), transformer insulation testing, TTR (Transformer Turn Ratio) testing, Breakdown Voltage testing, thermovision testing and Winding Resistance testing; In addition, treatment or purification of transformer oil is also carried out based on testing. all dissolved gas and total dissolved gas (TDCG) decreased after the purification process and after purification there is still residual dissolved gas in the transformer. Interpretation of dissolved gas data (DGA) using several methods indicates a \\\"Thermal Fault > 300 Celsius\\\". This is in line with the results of thermovision on the transformer which shows a hot spot at the termination of the HV phase W bushing. Confirmation of this suspect will be checked after repairing the termination. Keywords: Distribution Transformer, Transformer, Maintenance. ABSTRAKDi Indonesia, suplai kelistrikan untuk bangunan atau gedung dengan kebutuhan diatas 200kVA maka diperlukan trafo distribusi yang dimiliki oleh pelanggan, sehingga transaksi energi listrik dilakukan di sisi tegangan menengah 20kV. Trafo distribusi di sebuah rumah sakit merupakan suatu komponen yang sangat vital, terutama selama masa pandemic COVID-19 dimana trafo dipaksa untuk tetap beroperasi diatas narus nominal tanpa adanya perawatan. Perawatan trafo distribusi meliputi inspeksi visual, perawatan bulanan, perawatan tiap enam bulan dan perawatan tahunan. Perawatan yang dilakukan di trafo distribusi di Rumah Sakit X ini adalah DGA (Dissolved Gasses Analysis), pengujian insulasi trafo, pengujian TTR (Transformer Turn Ratio), pengujian Breakdown Voltage, pengujian thermovision dan pengujian Winding Resistance, selain itu juga dilakukan treatment atau purifikasi oli trafo Berdasarkan pengujian. semua gas terlarut dan total gas terlarut (TDCG) menurun setelah proses pemurnian dan setelah pemurnian masih ada sisa gas terlarut di trafo. Interpretasi data gas terlarut (DGA) dengan beberapa metode menunjukkan adanya “Termal Fault > 300 Celcius”. Hal ini sejalan dengan hasil thermovision pada trafo yang menunjukkan adanya hot spot pada bagian terminasi busing W fasa HV. Konfirmasi tersangka ini akan dilakukan pengecekan setelah dilakukan perbaikan terminasi.\",\"PeriodicalId\":31998,\"journal\":{\"name\":\"Elektrika\",\"volume\":\"1 1\",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-05-03\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Elektrika\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.26623/elektrika.v15i1.6478\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Elektrika","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.26623/elektrika.v15i1.6478","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
在印度尼西亚,建筑物或需求在200kVA以上的建筑物的电力供应需要客户拥有的配电变压器,因此电能交易在20kV的中压侧进行。医院的配电变压器是一个非常重要的部件,特别是在COVID-19大流行期间,变压器被迫继续在高于标称水平的情况下运行,而无需任何维护。配电变压器维护包括目测检查、月度维护、半年维护和年度维护。X医院对配电变压器进行的处理包括溶解气体分析(DGA)、变压器绝缘测试、TTR(变压器匝比)测试、击穿电压测试、热视测试和绕组电阻测试;此外,还根据试验对变压器油进行处理或净化。所有溶解气体和总溶解气体(TDCG)经过净化处理后降低,净化后变压器内仍有残余溶解气体存在。用几种方法解释溶解气体数据(DGA)表明存在“热断层> 300摄氏度”。这与变压器的热视觉结果一致,该结果显示在高压相W衬套的末端有一个热点。确认这个怀疑将检查修复后终止 . 关键词:配电变压器,变压器,维护【摘要】在印度尼西亚,供电线路为200kVA,供电线路为200kVA,供电线路为200kv,供电线路为200kv,供电线路为200kv,供电线路为200kv。新冠肺炎(COVID-19)大流行,新冠肺炎大流行,新冠肺炎大流行,新冠肺炎大流行,新冠肺炎大流行,新冠肺炎大流行,新冠肺炎大流行,新冠肺炎大流行,新冠肺炎大流行,新冠肺炎,新冠肺炎,新冠肺炎,新冠肺炎,新冠肺炎,新冠肺炎,新冠肺炎,新冠肺炎,新冠肺炎,新冠肺炎,新冠肺炎,新冠肺炎,新冠肺炎perwatan交通配送,melpuputi, perwatan bulanan, perwatan tianan, perwatan ta湖南。Perawatan yang dilakukan di traffic distribution busi di Rumah Sakit X ini adalah DGA(溶解气体分析),penguin insulasi traffic, penguin TTR(变压器匝比),penguin击穿电压,penguin热视觉,penguin绕组电阻,selain itu juga dilakukan treatment atau purifikasi oli traffic, Berdasarkan penguin。semua gas terarut和total gas terarut (TDCG) menurun setelah处理pemurnian dan setelah, pemurnian masih和sisa gas terarut / transport。天然气terlarut (DGA)解译资料:DGA方法:menunjukkan adanya“终端断层bbb300℃”。哈尔尼·塞贾兰·登甘·哈西尔热视帕达交通,杨门,朱克坎,阿达尼亚热点帕达巴达,巴达巴达终点站,巴士W法萨HV。Konfirmasi tersangka ini akan dilakukan pengecekan setelah dilakukan perbaikan terminasi。
Analisis Perawatan Berkala Trafo Distribusi 800 kVA pada Rumah Sakit X Kota Tangerang
In Indonesia, electricity supply for buildings or buildings with needs above 200kVA requires a distribution transformer owned by the customer, so that electrical energy transactions are carried out on the medium voltage side of 20kV. The distribution transformer in a hospital is a very vital component, especially during the COVID-19 pandemic where transformers are forced to continue operating above nominal levels without any maintenance. Distribution transformer maintenance includes visual inspection, monthly maintenance, maintenance every six months and annual maintenance. Treatments carried out on distribution transformers at X Hospital are DGA (Dissolved Gasses Analysis), transformer insulation testing, TTR (Transformer Turn Ratio) testing, Breakdown Voltage testing, thermovision testing and Winding Resistance testing; In addition, treatment or purification of transformer oil is also carried out based on testing. all dissolved gas and total dissolved gas (TDCG) decreased after the purification process and after purification there is still residual dissolved gas in the transformer. Interpretation of dissolved gas data (DGA) using several methods indicates a "Thermal Fault > 300 Celsius". This is in line with the results of thermovision on the transformer which shows a hot spot at the termination of the HV phase W bushing. Confirmation of this suspect will be checked after repairing the termination. Keywords: Distribution Transformer, Transformer, Maintenance. ABSTRAKDi Indonesia, suplai kelistrikan untuk bangunan atau gedung dengan kebutuhan diatas 200kVA maka diperlukan trafo distribusi yang dimiliki oleh pelanggan, sehingga transaksi energi listrik dilakukan di sisi tegangan menengah 20kV. Trafo distribusi di sebuah rumah sakit merupakan suatu komponen yang sangat vital, terutama selama masa pandemic COVID-19 dimana trafo dipaksa untuk tetap beroperasi diatas narus nominal tanpa adanya perawatan. Perawatan trafo distribusi meliputi inspeksi visual, perawatan bulanan, perawatan tiap enam bulan dan perawatan tahunan. Perawatan yang dilakukan di trafo distribusi di Rumah Sakit X ini adalah DGA (Dissolved Gasses Analysis), pengujian insulasi trafo, pengujian TTR (Transformer Turn Ratio), pengujian Breakdown Voltage, pengujian thermovision dan pengujian Winding Resistance, selain itu juga dilakukan treatment atau purifikasi oli trafo Berdasarkan pengujian. semua gas terlarut dan total gas terlarut (TDCG) menurun setelah proses pemurnian dan setelah pemurnian masih ada sisa gas terlarut di trafo. Interpretasi data gas terlarut (DGA) dengan beberapa metode menunjukkan adanya “Termal Fault > 300 Celcius”. Hal ini sejalan dengan hasil thermovision pada trafo yang menunjukkan adanya hot spot pada bagian terminasi busing W fasa HV. Konfirmasi tersangka ini akan dilakukan pengecekan setelah dilakukan perbaikan terminasi.