ANA平台导管架安装中的DP挑战

IF 3.9 4区 工程技术 Q1 ENGINEERING, MARINE
Brodogradnja Pub Date : 2022-10-01 DOI:10.21278/brod73401
K. Ardavanis, R. Nabergoj, F. Mauro
{"title":"ANA平台导管架安装中的DP挑战","authors":"K. Ardavanis, R. Nabergoj, F. Mauro","doi":"10.21278/brod73401","DOIUrl":null,"url":null,"abstract":"Installation of jacket platforms requires simultaneous and combined operations of multiple assets. Once the whole process has to be planned, it is necessary to predict in a fast and reliable way the possible weather limitations that may occur during the operations. The paper will present the major challenges of this unusual and innovative Dynamic Positioning analysis which has been carried out for Ana Jacket installation. The obtained results show that the Dynamic Positioning system of the core vessel in intact configuration is capable to hold the position for the investigated vessels' arrangements and design operative weather conditions. Lifting, upending and installation of Ana Jacket were carried out successfully in 2021.","PeriodicalId":55594,"journal":{"name":"Brodogradnja","volume":null,"pages":null},"PeriodicalIF":3.9000,"publicationDate":"2022-10-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"DP CHALLENGES IN ANA PLATFORM JACKET INSTALLATION\",\"authors\":\"K. Ardavanis, R. Nabergoj, F. Mauro\",\"doi\":\"10.21278/brod73401\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Installation of jacket platforms requires simultaneous and combined operations of multiple assets. Once the whole process has to be planned, it is necessary to predict in a fast and reliable way the possible weather limitations that may occur during the operations. The paper will present the major challenges of this unusual and innovative Dynamic Positioning analysis which has been carried out for Ana Jacket installation. The obtained results show that the Dynamic Positioning system of the core vessel in intact configuration is capable to hold the position for the investigated vessels' arrangements and design operative weather conditions. Lifting, upending and installation of Ana Jacket were carried out successfully in 2021.\",\"PeriodicalId\":55594,\"journal\":{\"name\":\"Brodogradnja\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":3.9000,\"publicationDate\":\"2022-10-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Brodogradnja\",\"FirstCategoryId\":\"5\",\"ListUrlMain\":\"https://doi.org/10.21278/brod73401\",\"RegionNum\":4,\"RegionCategory\":\"工程技术\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q1\",\"JCRName\":\"ENGINEERING, MARINE\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Brodogradnja","FirstCategoryId":"5","ListUrlMain":"https://doi.org/10.21278/brod73401","RegionNum":4,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"ENGINEERING, MARINE","Score":null,"Total":0}
引用次数: 2

摘要

导管架平台的安装需要多个资产的同时和组合操作。一旦必须对整个过程进行规划,就有必要以快速可靠的方式预测操作过程中可能出现的天气限制。本文将介绍这种不同寻常的创新动态定位分析的主要挑战,该分析是为Ana导管架安装进行的。所获得的结果表明,处于完整配置的核心船的动态定位系统能够为所研究的船只的布置和设计的操作天气条件保持位置。Ana导管架的吊装、翻转和安装于2021年成功实施。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
DP CHALLENGES IN ANA PLATFORM JACKET INSTALLATION
Installation of jacket platforms requires simultaneous and combined operations of multiple assets. Once the whole process has to be planned, it is necessary to predict in a fast and reliable way the possible weather limitations that may occur during the operations. The paper will present the major challenges of this unusual and innovative Dynamic Positioning analysis which has been carried out for Ana Jacket installation. The obtained results show that the Dynamic Positioning system of the core vessel in intact configuration is capable to hold the position for the investigated vessels' arrangements and design operative weather conditions. Lifting, upending and installation of Ana Jacket were carried out successfully in 2021.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
Brodogradnja
Brodogradnja ENGINEERING, MARINE-
CiteScore
4.30
自引率
38.90%
发文量
33
审稿时长
>12 weeks
期刊介绍: The journal is devoted to multidisciplinary researches in the fields of theoretical and experimental naval architecture and oceanology as well as to challenging problems in shipbuilding as well shipping, offshore and related shipbuilding industries worldwide. The aim of the journal is to integrate technical interests in shipbuilding, ocean engineering, sea and ocean shipping, inland navigation and intermodal transportation as well as environmental issues, overall safety, objects for wind, marine and hydrokinetic renewable energy production and sustainable transportation development at seas, oceans and inland waterways in relations to shipbuilding and naval architecture. The journal focuses on hydrodynamics, structures, reliability, materials, construction, design, optimization, production engineering, building and organization of building, project management, repair and maintenance planning, information systems in shipyards, quality assurance as well as outfitting, powering, autonomous marine vehicles, power plants and equipment onboard. Brodogradnja publishes original scientific papers, review papers, preliminary communications and important professional papers relevant in engineering and technology.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信