一种高效、有效的工程工期可靠性评估方法

IF 2.3 2区 工程技术 Q3 ENGINEERING, INDUSTRIAL
Lou Ren, Pei-Pei Li, Yan-Gang Zhao
{"title":"一种高效、有效的工程工期可靠性评估方法","authors":"Lou Ren, Pei-Pei Li, Yan-Gang Zhao","doi":"10.1080/16843703.2022.2138113","DOIUrl":null,"url":null,"abstract":"ABSTRACT The reliability assessment of the project duration is essential for successful project management; this has prompted the development of various methods to assess whether a project will be completed within the target duration. In this study, an efficient and effective method for assessing the reliability of project duration based on the method of moments is proposed, which utilizes bivariate-dimension reduction technology and the third-moment reliability index. The proposed method can avoid the extensive calculations of various factors in the commonly used methods: the correlation coefficients between each pair of paths and the joint failure probability of each pair of representative paths. From two numerical examples, it can be concluded that the proposed method can obtain almost the same results as Monte Carlo simulations with less calculation.","PeriodicalId":49133,"journal":{"name":"Quality Technology and Quantitative Management","volume":null,"pages":null},"PeriodicalIF":2.3000,"publicationDate":"2022-12-05","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"An efficient and effective method for reliability assessment of project duration\",\"authors\":\"Lou Ren, Pei-Pei Li, Yan-Gang Zhao\",\"doi\":\"10.1080/16843703.2022.2138113\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"ABSTRACT The reliability assessment of the project duration is essential for successful project management; this has prompted the development of various methods to assess whether a project will be completed within the target duration. In this study, an efficient and effective method for assessing the reliability of project duration based on the method of moments is proposed, which utilizes bivariate-dimension reduction technology and the third-moment reliability index. The proposed method can avoid the extensive calculations of various factors in the commonly used methods: the correlation coefficients between each pair of paths and the joint failure probability of each pair of representative paths. From two numerical examples, it can be concluded that the proposed method can obtain almost the same results as Monte Carlo simulations with less calculation.\",\"PeriodicalId\":49133,\"journal\":{\"name\":\"Quality Technology and Quantitative Management\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":2.3000,\"publicationDate\":\"2022-12-05\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Quality Technology and Quantitative Management\",\"FirstCategoryId\":\"5\",\"ListUrlMain\":\"https://doi.org/10.1080/16843703.2022.2138113\",\"RegionNum\":2,\"RegionCategory\":\"工程技术\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"ENGINEERING, INDUSTRIAL\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Quality Technology and Quantitative Management","FirstCategoryId":"5","ListUrlMain":"https://doi.org/10.1080/16843703.2022.2138113","RegionNum":2,"RegionCategory":"工程技术","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"ENGINEERING, INDUSTRIAL","Score":null,"Total":0}
引用次数: 1

摘要

摘要项目工期的可靠性评估对于项目管理的成功至关重要;这促使人们开发了各种方法来评估项目是否会在目标期限内完成。本研究利用二元降维技术和三阶矩可靠性指标,提出了一种基于矩量法的工程工期可靠性评估方法。所提出的方法可以避免常用方法中各种因素的大量计算:每对路径之间的相关系数和每对代表路径的联合失效概率。通过两个算例可以得出结论,该方法可以在较少的计算量下获得与蒙特卡罗模拟几乎相同的结果。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
An efficient and effective method for reliability assessment of project duration
ABSTRACT The reliability assessment of the project duration is essential for successful project management; this has prompted the development of various methods to assess whether a project will be completed within the target duration. In this study, an efficient and effective method for assessing the reliability of project duration based on the method of moments is proposed, which utilizes bivariate-dimension reduction technology and the third-moment reliability index. The proposed method can avoid the extensive calculations of various factors in the commonly used methods: the correlation coefficients between each pair of paths and the joint failure probability of each pair of representative paths. From two numerical examples, it can be concluded that the proposed method can obtain almost the same results as Monte Carlo simulations with less calculation.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
Quality Technology and Quantitative Management
Quality Technology and Quantitative Management ENGINEERING, INDUSTRIAL-OPERATIONS RESEARCH & MANAGEMENT SCIENCE
CiteScore
5.10
自引率
21.40%
发文量
47
审稿时长
>12 weeks
期刊介绍: Quality Technology and Quantitative Management is an international refereed journal publishing original work in quality, reliability, queuing service systems, applied statistics (including methodology, data analysis, simulation), and their applications in business and industrial management. The journal publishes both theoretical and applied research articles using statistical methods or presenting new results, which solve or have the potential to solve real-world management problems.
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信