{"title":"受战争影响和冲突敏感的阿富汗建筑业的项目成本绩效因素","authors":"Ahmad Shah Kakar, A. Hasan, K. N. Jha, Amarjit Singh","doi":"10.1108/jedt-11-2021-0657","DOIUrl":null,"url":null,"abstract":"\nPurpose\nThe Afghan construction industry faces resource shortages and heavily relies on foreign aid to fund public projects on the path to recovery and reconstruction. While the resource constraints demand cost-efficient delivery of construction projects, many Afghan public projects experience delays and cost overruns. This study aims to evaluate various attributes and factors influencing cost performance in public construction projects in Afghanistan.\n\n\nDesign/methodology/approach\nThe literature review and Delphi method identified 30 cost performance attributes relevant to the context of Afghanistan. Next, a questionnaire survey was conducted with construction management professionals working in the public sector in the Afghan construction industry to evaluate these attributes.\n\n\nFindings\nThis study found that the lack of resources, poor project management skills and corruption in procurement are the leading causes behind cost overruns in Afghan public projects. This study also identified five latent factors influencing cost performance in public projects in Afghanistan: competency of the project team, socioeconomic and political support, governance and public procurement, planning and risk management and project characteristics.\n\n\nResearch limitations/implications\nThe exploratory factor analysis did not reveal the relative significance of different cost performance success factors. Moreover, the ranking of cost performance attributes is based on the responses from the public sector construction professionals only.\n\n\nPractical implications\nThe construction industry in Afghanistan significantly contributes to the country’s social and economic growth and employment. This study’s findings will help researchers, project sponsors, government departments and industry practitioners interested in improving the cost performance in Afghan public projects.\n\n\nOriginality/value\nGiven the scarcity of research in war-affected and conflict-sensitive regions, this study fills a research gap on project cost performance by providing insights into the cost performance success factors in public projects in Afghanistan.\n","PeriodicalId":46533,"journal":{"name":"Journal of Engineering Design and Technology","volume":" ","pages":""},"PeriodicalIF":2.6000,"publicationDate":"2022-11-08","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Project cost performance factors in the war-affected and conflict-sensitive Afghan construction industry\",\"authors\":\"Ahmad Shah Kakar, A. Hasan, K. N. Jha, Amarjit Singh\",\"doi\":\"10.1108/jedt-11-2021-0657\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\nPurpose\\nThe Afghan construction industry faces resource shortages and heavily relies on foreign aid to fund public projects on the path to recovery and reconstruction. While the resource constraints demand cost-efficient delivery of construction projects, many Afghan public projects experience delays and cost overruns. This study aims to evaluate various attributes and factors influencing cost performance in public construction projects in Afghanistan.\\n\\n\\nDesign/methodology/approach\\nThe literature review and Delphi method identified 30 cost performance attributes relevant to the context of Afghanistan. Next, a questionnaire survey was conducted with construction management professionals working in the public sector in the Afghan construction industry to evaluate these attributes.\\n\\n\\nFindings\\nThis study found that the lack of resources, poor project management skills and corruption in procurement are the leading causes behind cost overruns in Afghan public projects. This study also identified five latent factors influencing cost performance in public projects in Afghanistan: competency of the project team, socioeconomic and political support, governance and public procurement, planning and risk management and project characteristics.\\n\\n\\nResearch limitations/implications\\nThe exploratory factor analysis did not reveal the relative significance of different cost performance success factors. Moreover, the ranking of cost performance attributes is based on the responses from the public sector construction professionals only.\\n\\n\\nPractical implications\\nThe construction industry in Afghanistan significantly contributes to the country’s social and economic growth and employment. This study’s findings will help researchers, project sponsors, government departments and industry practitioners interested in improving the cost performance in Afghan public projects.\\n\\n\\nOriginality/value\\nGiven the scarcity of research in war-affected and conflict-sensitive regions, this study fills a research gap on project cost performance by providing insights into the cost performance success factors in public projects in Afghanistan.\\n\",\"PeriodicalId\":46533,\"journal\":{\"name\":\"Journal of Engineering Design and Technology\",\"volume\":\" \",\"pages\":\"\"},\"PeriodicalIF\":2.6000,\"publicationDate\":\"2022-11-08\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Engineering Design and Technology\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1108/jedt-11-2021-0657\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q1\",\"JCRName\":\"ENGINEERING, MULTIDISCIPLINARY\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Engineering Design and Technology","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1108/jedt-11-2021-0657","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q1","JCRName":"ENGINEERING, MULTIDISCIPLINARY","Score":null,"Total":0}
Project cost performance factors in the war-affected and conflict-sensitive Afghan construction industry
Purpose
The Afghan construction industry faces resource shortages and heavily relies on foreign aid to fund public projects on the path to recovery and reconstruction. While the resource constraints demand cost-efficient delivery of construction projects, many Afghan public projects experience delays and cost overruns. This study aims to evaluate various attributes and factors influencing cost performance in public construction projects in Afghanistan.
Design/methodology/approach
The literature review and Delphi method identified 30 cost performance attributes relevant to the context of Afghanistan. Next, a questionnaire survey was conducted with construction management professionals working in the public sector in the Afghan construction industry to evaluate these attributes.
Findings
This study found that the lack of resources, poor project management skills and corruption in procurement are the leading causes behind cost overruns in Afghan public projects. This study also identified five latent factors influencing cost performance in public projects in Afghanistan: competency of the project team, socioeconomic and political support, governance and public procurement, planning and risk management and project characteristics.
Research limitations/implications
The exploratory factor analysis did not reveal the relative significance of different cost performance success factors. Moreover, the ranking of cost performance attributes is based on the responses from the public sector construction professionals only.
Practical implications
The construction industry in Afghanistan significantly contributes to the country’s social and economic growth and employment. This study’s findings will help researchers, project sponsors, government departments and industry practitioners interested in improving the cost performance in Afghan public projects.
Originality/value
Given the scarcity of research in war-affected and conflict-sensitive regions, this study fills a research gap on project cost performance by providing insights into the cost performance success factors in public projects in Afghanistan.
期刊介绍:
- Design strategies - Usability and adaptability - Material, component and systems performance - Process control - Alternative and new technologies - Organizational, management and research issues - Human factors - Environmental, quality and health and safety issues - Cost and life cycle issues - Sustainability criteria, indicators, measurement and practices - Risk management - Entrepreneurship Law, regulation and governance - Design, implementing, managing and practicing innovation - Visualization, simulation, information and communication technologies - Education practices, innovation, strategies and policy issues.