{"title":"预制预制体积建筑项目关键成功标准的评估","authors":"I. Y. Wuni, G. Shen, R. Osei-Kyei","doi":"10.1108/JFMPC-03-2020-0013","DOIUrl":null,"url":null,"abstract":"\nPurpose\nPrefabricated prefinished volumetric construction (PPVC) is a game-changing construction method that transforms the fragmented site-based construction of buildings into an integrated production, integration and assembly of value-added volumetric building components. Where circumstances merit, the effective implementation of PPVC leverages significant gains in time, cost, quality, productivity and sustainability performance of construction projects. As PPVC is increasingly becoming mainstream, it is imperative to identify the critical success criteria (CSC) for measuring PPVC project success. The purpose of this study is to identify, rank and benchmark the CSC for measuring PPVC project success.\n\n\nDesign/methodology/approach\nThis study adopted a quantitative research design where the potential CSC for PPVC projects were evaluated. A comprehensive literature and pilot expert review identified 18 CSC for measuring PPVC project success. Based on a questionnaire survey of international PPVC experts, the 18 CSC were analyzed and prioritized using mean score analysis and weighting function.\n\n\nFindings\nBased on mean index assessment, the top five CSC for PPVC projects were identified as adherence to project schedules, meeting project quality specification, meeting safety requirements, client and owner satisfaction and cost savings and profitability. Further analysis grouped the 18 CSC into six principal success criteria (PSC), comprising time performance, cost performance, quality performance, environmental and safety performance, stakeholder satisfaction and supply chain performance. Based on weighted analysis of the six PSCs, quality performance, time performance and environmental and safety performance obtained the highest weights.\n\n\nResearch limitations/implications\nThe research results are limited by the following limitations. First, although adequate, the sample size was relatively smaller. Second, the generalized analysis overlooked the geospatial sensitivities of the CSC.\n\n\nOriginality/value\nThe results constitute the first exclusive quantitative ranking and prioritization of the CSC for PPVC projects. The outputs of this study will enable practitioners to reliably and accurately evaluate the performance levels of PPVC projects. A framework of the CSC for measuring the success of PPVC projects was developed.\n","PeriodicalId":45720,"journal":{"name":"Journal of Financial Management of Property and Construction","volume":" ","pages":""},"PeriodicalIF":1.2000,"publicationDate":"2021-02-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"8","resultStr":"{\"title\":\"Evaluating the critical success criteria for prefabricated prefinished volumetric construction projects\",\"authors\":\"I. Y. Wuni, G. Shen, R. Osei-Kyei\",\"doi\":\"10.1108/JFMPC-03-2020-0013\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\nPurpose\\nPrefabricated prefinished volumetric construction (PPVC) is a game-changing construction method that transforms the fragmented site-based construction of buildings into an integrated production, integration and assembly of value-added volumetric building components. Where circumstances merit, the effective implementation of PPVC leverages significant gains in time, cost, quality, productivity and sustainability performance of construction projects. As PPVC is increasingly becoming mainstream, it is imperative to identify the critical success criteria (CSC) for measuring PPVC project success. The purpose of this study is to identify, rank and benchmark the CSC for measuring PPVC project success.\\n\\n\\nDesign/methodology/approach\\nThis study adopted a quantitative research design where the potential CSC for PPVC projects were evaluated. A comprehensive literature and pilot expert review identified 18 CSC for measuring PPVC project success. Based on a questionnaire survey of international PPVC experts, the 18 CSC were analyzed and prioritized using mean score analysis and weighting function.\\n\\n\\nFindings\\nBased on mean index assessment, the top five CSC for PPVC projects were identified as adherence to project schedules, meeting project quality specification, meeting safety requirements, client and owner satisfaction and cost savings and profitability. Further analysis grouped the 18 CSC into six principal success criteria (PSC), comprising time performance, cost performance, quality performance, environmental and safety performance, stakeholder satisfaction and supply chain performance. Based on weighted analysis of the six PSCs, quality performance, time performance and environmental and safety performance obtained the highest weights.\\n\\n\\nResearch limitations/implications\\nThe research results are limited by the following limitations. First, although adequate, the sample size was relatively smaller. Second, the generalized analysis overlooked the geospatial sensitivities of the CSC.\\n\\n\\nOriginality/value\\nThe results constitute the first exclusive quantitative ranking and prioritization of the CSC for PPVC projects. The outputs of this study will enable practitioners to reliably and accurately evaluate the performance levels of PPVC projects. A framework of the CSC for measuring the success of PPVC projects was developed.\\n\",\"PeriodicalId\":45720,\"journal\":{\"name\":\"Journal of Financial Management of Property and Construction\",\"volume\":\" \",\"pages\":\"\"},\"PeriodicalIF\":1.2000,\"publicationDate\":\"2021-02-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"8\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Financial Management of Property and Construction\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1108/JFMPC-03-2020-0013\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"BUSINESS, FINANCE\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Financial Management of Property and Construction","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1108/JFMPC-03-2020-0013","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"BUSINESS, FINANCE","Score":null,"Total":0}
Evaluating the critical success criteria for prefabricated prefinished volumetric construction projects
Purpose
Prefabricated prefinished volumetric construction (PPVC) is a game-changing construction method that transforms the fragmented site-based construction of buildings into an integrated production, integration and assembly of value-added volumetric building components. Where circumstances merit, the effective implementation of PPVC leverages significant gains in time, cost, quality, productivity and sustainability performance of construction projects. As PPVC is increasingly becoming mainstream, it is imperative to identify the critical success criteria (CSC) for measuring PPVC project success. The purpose of this study is to identify, rank and benchmark the CSC for measuring PPVC project success.
Design/methodology/approach
This study adopted a quantitative research design where the potential CSC for PPVC projects were evaluated. A comprehensive literature and pilot expert review identified 18 CSC for measuring PPVC project success. Based on a questionnaire survey of international PPVC experts, the 18 CSC were analyzed and prioritized using mean score analysis and weighting function.
Findings
Based on mean index assessment, the top five CSC for PPVC projects were identified as adherence to project schedules, meeting project quality specification, meeting safety requirements, client and owner satisfaction and cost savings and profitability. Further analysis grouped the 18 CSC into six principal success criteria (PSC), comprising time performance, cost performance, quality performance, environmental and safety performance, stakeholder satisfaction and supply chain performance. Based on weighted analysis of the six PSCs, quality performance, time performance and environmental and safety performance obtained the highest weights.
Research limitations/implications
The research results are limited by the following limitations. First, although adequate, the sample size was relatively smaller. Second, the generalized analysis overlooked the geospatial sensitivities of the CSC.
Originality/value
The results constitute the first exclusive quantitative ranking and prioritization of the CSC for PPVC projects. The outputs of this study will enable practitioners to reliably and accurately evaluate the performance levels of PPVC projects. A framework of the CSC for measuring the success of PPVC projects was developed.