利用Helioscope软件模拟200kWP工业厂房屋顶太阳能光伏并网技术性能及经济可行性

D. Damiri, Achmad Aditya Nugraha
{"title":"利用Helioscope软件模拟200kWP工业厂房屋顶太阳能光伏并网技术性能及经济可行性","authors":"D. Damiri, Achmad Aditya Nugraha","doi":"10.17529/jre.v17i2.19578","DOIUrl":null,"url":null,"abstract":"Renewable energy resources are currently being developed by Indonesia. The government is also targeting an energy mix of 23% to achieve renewable energy by 2025. One of the renewable energies is Solar Photovoltaic Generation System. On the other hand, an industrial area is an area filled with factories that are large enough so that it has great potential to develop Rooftop Solar Photovoltaic with the advantage of reducing land investment costs without reducing the operational function of the factory. The purpose of this research is to simulate the technical and economic performance of a 200kWP Solar Photovoltaic On grid on the rooftop of a factory building using Helioscope software in an industrial area in West Java. The simulation result shows that the average values for Global Horizontal Irradiance (GHI), Electrical Energy Production, and Performance Ratio (PR) in one year are 138.2 kWh/m2, 21,977 kWh, and 78.06%. Meanwhile, the total Electrical Energy Production in one year is 263,723.6 kWh. The total investment value of the 200kWP Rooftop Solar Photovoltaic On grid on the factory building is 2,457,850,800 IDR. Based on the economic feasibility study, it can be concluded that the 200kWP Rooftop Solar Photovoltaic On grid on the factory building rooftop is economically feasible as long as the interest rates is less than 12.71% (Internal Rate of Return / IRR).","PeriodicalId":30766,"journal":{"name":"Jurnal Rekayasa Elektrika","volume":null,"pages":null},"PeriodicalIF":0.0000,"publicationDate":"2021-06-30","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Technical Performance and Economic Feasibility Simulation of 200kWP Rooftop Solar Photovoltaic On grid on Industrial Estate Factory Building with Helioscope Software\",\"authors\":\"D. Damiri, Achmad Aditya Nugraha\",\"doi\":\"10.17529/jre.v17i2.19578\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Renewable energy resources are currently being developed by Indonesia. The government is also targeting an energy mix of 23% to achieve renewable energy by 2025. One of the renewable energies is Solar Photovoltaic Generation System. On the other hand, an industrial area is an area filled with factories that are large enough so that it has great potential to develop Rooftop Solar Photovoltaic with the advantage of reducing land investment costs without reducing the operational function of the factory. The purpose of this research is to simulate the technical and economic performance of a 200kWP Solar Photovoltaic On grid on the rooftop of a factory building using Helioscope software in an industrial area in West Java. The simulation result shows that the average values for Global Horizontal Irradiance (GHI), Electrical Energy Production, and Performance Ratio (PR) in one year are 138.2 kWh/m2, 21,977 kWh, and 78.06%. Meanwhile, the total Electrical Energy Production in one year is 263,723.6 kWh. The total investment value of the 200kWP Rooftop Solar Photovoltaic On grid on the factory building is 2,457,850,800 IDR. Based on the economic feasibility study, it can be concluded that the 200kWP Rooftop Solar Photovoltaic On grid on the factory building rooftop is economically feasible as long as the interest rates is less than 12.71% (Internal Rate of Return / IRR).\",\"PeriodicalId\":30766,\"journal\":{\"name\":\"Jurnal Rekayasa Elektrika\",\"volume\":null,\"pages\":null},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-06-30\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Jurnal Rekayasa Elektrika\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.17529/jre.v17i2.19578\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Jurnal Rekayasa Elektrika","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.17529/jre.v17i2.19578","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 2

摘要

印尼目前正在开发可再生能源。政府还制定了到2025年实现可再生能源占能源结构23%的目标。可再生能源之一是太阳能光伏发电系统。另一方面,一个工业区是一个充满工厂的区域,足够大,有很大的潜力发展屋顶太阳能光伏,其优势是减少土地投资成本,而不降低工厂的运营功能。本研究的目的是利用Helioscope软件在西爪哇的一个工业区模拟厂房屋顶200kWP太阳能光伏电网的技术和经济性能。模拟结果表明,一年的全球水平辐照度(GHI)、发电量和性能比(PR)平均值分别为138.2 kWh/m2、21977 kWh和78.06%。同时,一年的总发电量为263,723.6 kWh。厂房200kWP屋顶太阳能光伏并网总投资价值2,457,850,800印尼盾。通过经济可行性研究,可以得出,只要利率低于12.71%(内部收益率/ IRR),工厂楼顶200kWP屋顶太阳能光伏并网在经济上是可行的。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Technical Performance and Economic Feasibility Simulation of 200kWP Rooftop Solar Photovoltaic On grid on Industrial Estate Factory Building with Helioscope Software
Renewable energy resources are currently being developed by Indonesia. The government is also targeting an energy mix of 23% to achieve renewable energy by 2025. One of the renewable energies is Solar Photovoltaic Generation System. On the other hand, an industrial area is an area filled with factories that are large enough so that it has great potential to develop Rooftop Solar Photovoltaic with the advantage of reducing land investment costs without reducing the operational function of the factory. The purpose of this research is to simulate the technical and economic performance of a 200kWP Solar Photovoltaic On grid on the rooftop of a factory building using Helioscope software in an industrial area in West Java. The simulation result shows that the average values for Global Horizontal Irradiance (GHI), Electrical Energy Production, and Performance Ratio (PR) in one year are 138.2 kWh/m2, 21,977 kWh, and 78.06%. Meanwhile, the total Electrical Energy Production in one year is 263,723.6 kWh. The total investment value of the 200kWP Rooftop Solar Photovoltaic On grid on the factory building is 2,457,850,800 IDR. Based on the economic feasibility study, it can be concluded that the 200kWP Rooftop Solar Photovoltaic On grid on the factory building rooftop is economically feasible as long as the interest rates is less than 12.71% (Internal Rate of Return / IRR).
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
24
审稿时长
24 weeks
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信