{"title":"环保PPP项目弹性合同期限设定方式与设定效果关系研究","authors":"Lingyi Tang, Xiaer Xiahou, Kang Li, Qiming Li, Xiaoyang Hu","doi":"10.1080/10429247.2022.2097493","DOIUrl":null,"url":null,"abstract":"Abstract Environmental protection PPP projects (EP-PPP) are subject to uncertainty during the project cycle, setting flexible project contract terms in their contracts can help establish and maintain an effective partnership. This article aims to reveal the contract flexibility mechanism of EP-PPP projects by studying the relationship between flexible contract term setting methods and their effects. Questionnaires, case studies and structural equation modeling (SEM) are applied to conduct quantitative analysis. The research shows that although some flexible terms have been adopted in current EP-PPP contracts, there is still much room for improvement. In order to deal with unforeseen risks and challenges, it is necessary to consider: (1) List uncertainties as much as possible and set up response methods accordingly; (2) Guarantee a certain degree of flexibility in uncertainty response methods; (3) Give the project itself a certain degree of autonomous response power; (4) Leave plenty space for changes that may be needed in the future. The study results can help project practitioners enhance their understanding of flexible contract terms and help to promote contract flexibility in EP-PPP projects in a context-specific manner, thereby facilitating project success.","PeriodicalId":54353,"journal":{"name":"Engineering Management Journal","volume":"35 1","pages":"272 - 284"},"PeriodicalIF":1.9000,"publicationDate":"2022-07-19","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"2","resultStr":"{\"title\":\"Research on the Relationship Between Flexible Contract Term Setting Method and Setting Effect of Environmental Protection PPP Project\",\"authors\":\"Lingyi Tang, Xiaer Xiahou, Kang Li, Qiming Li, Xiaoyang Hu\",\"doi\":\"10.1080/10429247.2022.2097493\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Abstract Environmental protection PPP projects (EP-PPP) are subject to uncertainty during the project cycle, setting flexible project contract terms in their contracts can help establish and maintain an effective partnership. This article aims to reveal the contract flexibility mechanism of EP-PPP projects by studying the relationship between flexible contract term setting methods and their effects. Questionnaires, case studies and structural equation modeling (SEM) are applied to conduct quantitative analysis. The research shows that although some flexible terms have been adopted in current EP-PPP contracts, there is still much room for improvement. In order to deal with unforeseen risks and challenges, it is necessary to consider: (1) List uncertainties as much as possible and set up response methods accordingly; (2) Guarantee a certain degree of flexibility in uncertainty response methods; (3) Give the project itself a certain degree of autonomous response power; (4) Leave plenty space for changes that may be needed in the future. The study results can help project practitioners enhance their understanding of flexible contract terms and help to promote contract flexibility in EP-PPP projects in a context-specific manner, thereby facilitating project success.\",\"PeriodicalId\":54353,\"journal\":{\"name\":\"Engineering Management Journal\",\"volume\":\"35 1\",\"pages\":\"272 - 284\"},\"PeriodicalIF\":1.9000,\"publicationDate\":\"2022-07-19\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"2\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Engineering Management Journal\",\"FirstCategoryId\":\"91\",\"ListUrlMain\":\"https://doi.org/10.1080/10429247.2022.2097493\",\"RegionNum\":4,\"RegionCategory\":\"管理学\",\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"ENGINEERING, INDUSTRIAL\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Engineering Management Journal","FirstCategoryId":"91","ListUrlMain":"https://doi.org/10.1080/10429247.2022.2097493","RegionNum":4,"RegionCategory":"管理学","ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"ENGINEERING, INDUSTRIAL","Score":null,"Total":0}
Research on the Relationship Between Flexible Contract Term Setting Method and Setting Effect of Environmental Protection PPP Project
Abstract Environmental protection PPP projects (EP-PPP) are subject to uncertainty during the project cycle, setting flexible project contract terms in their contracts can help establish and maintain an effective partnership. This article aims to reveal the contract flexibility mechanism of EP-PPP projects by studying the relationship between flexible contract term setting methods and their effects. Questionnaires, case studies and structural equation modeling (SEM) are applied to conduct quantitative analysis. The research shows that although some flexible terms have been adopted in current EP-PPP contracts, there is still much room for improvement. In order to deal with unforeseen risks and challenges, it is necessary to consider: (1) List uncertainties as much as possible and set up response methods accordingly; (2) Guarantee a certain degree of flexibility in uncertainty response methods; (3) Give the project itself a certain degree of autonomous response power; (4) Leave plenty space for changes that may be needed in the future. The study results can help project practitioners enhance their understanding of flexible contract terms and help to promote contract flexibility in EP-PPP projects in a context-specific manner, thereby facilitating project success.
期刊介绍:
EMJ is designed to provide practical, pertinent knowledge on the management of technology, technical professionals, and technical organizations. EMJ strives to provide value to the practice of engineering management and engineering managers. EMJ is an archival journal that facilitates both practitioners and university faculty in publishing useful articles. The primary focus is on articles that improve the practice of engineering management. To support the practice of engineering management, EMJ publishes papers within key engineering management content areas. EMJ Editors will continue to refine these areas to ensure they are aligned with the challenges faced by technical organizations and technical managers.