{"title":"超导馈线电缆敷设及应力松弛冷却方法","authors":"T. Akasaka, Y. Fukumoto, A. Ishihara, Kenji Suzuki, Yusuke Kobayashi, Masaru Tomita","doi":"10.2219/rtriqr.62.3_201","DOIUrl":null,"url":null,"abstract":"Superconducting feeder cables shrink because of thermal stress during the cooling process. When a long superconducting feeder cable is laid along a railway line, measures must be taken to prevent cable shrinkage. This paper therefore introduces a method which was used to lay a 300-m class superconducting feeder cable along a test track. This paper also reports that the method is suitable for similar cables, because no buckling or rupture points were observed after X-ray radiographs were taken over the whole length of the cable after its installation, and that transmission tests were conducted successfully with the cable.","PeriodicalId":52445,"journal":{"name":"Quarterly Report of RTRI (Railway Technical Research Institute) (Japan)","volume":" ","pages":""},"PeriodicalIF":0.0000,"publicationDate":"2021-08-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Superconducting Feeder Cable Laying and Stress Relaxation Method for Cooling\",\"authors\":\"T. Akasaka, Y. Fukumoto, A. Ishihara, Kenji Suzuki, Yusuke Kobayashi, Masaru Tomita\",\"doi\":\"10.2219/rtriqr.62.3_201\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Superconducting feeder cables shrink because of thermal stress during the cooling process. When a long superconducting feeder cable is laid along a railway line, measures must be taken to prevent cable shrinkage. This paper therefore introduces a method which was used to lay a 300-m class superconducting feeder cable along a test track. This paper also reports that the method is suitable for similar cables, because no buckling or rupture points were observed after X-ray radiographs were taken over the whole length of the cable after its installation, and that transmission tests were conducted successfully with the cable.\",\"PeriodicalId\":52445,\"journal\":{\"name\":\"Quarterly Report of RTRI (Railway Technical Research Institute) (Japan)\",\"volume\":\" \",\"pages\":\"\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2021-08-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Quarterly Report of RTRI (Railway Technical Research Institute) (Japan)\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.2219/rtriqr.62.3_201\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q4\",\"JCRName\":\"Engineering\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Quarterly Report of RTRI (Railway Technical Research Institute) (Japan)","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.2219/rtriqr.62.3_201","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"Engineering","Score":null,"Total":0}
引用次数: 0

摘要

超导馈线电缆在冷却过程中由于热应力产生收缩。在铁路沿线敷设超导体馈线电缆时,必须采取防止电缆收缩的措施。为此,本文介绍了沿试验轨道敷设300米级超导馈线电缆的方法。本文还报道,该方法适用于类似的电缆,因为在安装后对电缆的整个长度进行x射线摄影后,没有观察到屈曲或断裂点,并且成功地进行了电缆的传输测试。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Superconducting Feeder Cable Laying and Stress Relaxation Method for Cooling
Superconducting feeder cables shrink because of thermal stress during the cooling process. When a long superconducting feeder cable is laid along a railway line, measures must be taken to prevent cable shrinkage. This paper therefore introduces a method which was used to lay a 300-m class superconducting feeder cable along a test track. This paper also reports that the method is suitable for similar cables, because no buckling or rupture points were observed after X-ray radiographs were taken over the whole length of the cable after its installation, and that transmission tests were conducted successfully with the cable.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
CiteScore
0.70
自引率
0.00%
发文量
36
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信