{"title":"提高加纳建筑业道路项目估算的准确性","authors":"O. Akinradewo, C. Aigbavboa, Ayodeji Emmanuel Oke","doi":"10.1108/jfmpc-11-2019-0087","DOIUrl":null,"url":null,"abstract":"\nPurpose\nThe inaccuracy of preliminary estimates sometimes results in wasted development effort if the project is abandoned. To curb this menace, this study aims to assess the different measures to improve the accuracy of road project estimates.\n\n\nDesign/methodology/approach\nQuantitative research design was used for this study, and questionnaire was designed to retrieve data from the target population. Engineers and quantity surveyors in Accra, Ghana formed the target population and were contacted by using an e-questionnaire through their professional bodies owing to location constraints. Descriptive and exploratory factor analyses were used in analysing the retrieved data. Mann–Whitney U non-parametric test was also used to compare the opinions of the respondents.\n\n\nFindings\nThe study revealed that factors categorised as due diligence by estimator should be given more attention for accuracy of estimates to be improved.\n\n\nResearch limitations/implications\nThis study was limited to Accra, Ghana owing to time and distance constraint.\n\n\nPractical implications\nProper consideration must be given to preliminary site investigation when preparing the estimates for road projects. This will provide the estimator with information on the physical features of the project environment.\n\n\nOriginality/value\nDefined clusters of measures to improve estimate accuracy as highlighted in this study rather than merely ranked variables which are done by previous research studies will set the tone and provide insights for effective stakeholders’ actions. The study also bridges the gap between theory and practice by outlining how the findings can be implemented practically to achieve more accurate preliminary estimate for road projects. With efforts aligned with the core characteristics of each cluster, accuracy can be improved.\n","PeriodicalId":45720,"journal":{"name":"Journal of Financial Management of Property and Construction","volume":"25 1","pages":"407-421"},"PeriodicalIF":1.2000,"publicationDate":"2020-07-29","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"https://sci-hub-pdf.com/10.1108/jfmpc-11-2019-0087","citationCount":"8","resultStr":"{\"title\":\"Improving accuracy of road projects’ estimates in the Ghanaian construction industry\",\"authors\":\"O. Akinradewo, C. Aigbavboa, Ayodeji Emmanuel Oke\",\"doi\":\"10.1108/jfmpc-11-2019-0087\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"\\nPurpose\\nThe inaccuracy of preliminary estimates sometimes results in wasted development effort if the project is abandoned. To curb this menace, this study aims to assess the different measures to improve the accuracy of road project estimates.\\n\\n\\nDesign/methodology/approach\\nQuantitative research design was used for this study, and questionnaire was designed to retrieve data from the target population. Engineers and quantity surveyors in Accra, Ghana formed the target population and were contacted by using an e-questionnaire through their professional bodies owing to location constraints. Descriptive and exploratory factor analyses were used in analysing the retrieved data. Mann–Whitney U non-parametric test was also used to compare the opinions of the respondents.\\n\\n\\nFindings\\nThe study revealed that factors categorised as due diligence by estimator should be given more attention for accuracy of estimates to be improved.\\n\\n\\nResearch limitations/implications\\nThis study was limited to Accra, Ghana owing to time and distance constraint.\\n\\n\\nPractical implications\\nProper consideration must be given to preliminary site investigation when preparing the estimates for road projects. This will provide the estimator with information on the physical features of the project environment.\\n\\n\\nOriginality/value\\nDefined clusters of measures to improve estimate accuracy as highlighted in this study rather than merely ranked variables which are done by previous research studies will set the tone and provide insights for effective stakeholders’ actions. The study also bridges the gap between theory and practice by outlining how the findings can be implemented practically to achieve more accurate preliminary estimate for road projects. With efforts aligned with the core characteristics of each cluster, accuracy can be improved.\\n\",\"PeriodicalId\":45720,\"journal\":{\"name\":\"Journal of Financial Management of Property and Construction\",\"volume\":\"25 1\",\"pages\":\"407-421\"},\"PeriodicalIF\":1.2000,\"publicationDate\":\"2020-07-29\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"https://sci-hub-pdf.com/10.1108/jfmpc-11-2019-0087\",\"citationCount\":\"8\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Financial Management of Property and Construction\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1108/jfmpc-11-2019-0087\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q3\",\"JCRName\":\"BUSINESS, FINANCE\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Financial Management of Property and Construction","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1108/jfmpc-11-2019-0087","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q3","JCRName":"BUSINESS, FINANCE","Score":null,"Total":0}
引用次数: 8

摘要

目的如果放弃项目,初步估计的不准确有时会导致开发工作的浪费。为了遏制这种威胁,本研究旨在评估提高道路项目估算准确性的不同措施。设计/方法/方法本研究采用定量研究设计,并设计问卷从目标人群中检索数据。加纳阿克拉的工程师和工料测量员组成了目标人群,由于地点限制,他们通过专业机构使用电子问卷进行了联系。描述性和探索性因素分析用于分析检索到的数据。Mann–Whitney U非参数检验也用于比较受访者的意见。研究结果表明,应更多地关注被估算者归类为尽职调查的因素,以提高估算的准确性。研究局限性/含义由于时间和距离的限制,本研究仅限于加纳阿克拉。实际意义在编制道路项目概算时,必须适当考虑初步现场调查。这将为估算者提供有关项目环境物理特征的信息。独创性/价值如本研究所强调的,为提高估计准确性而定义的一系列措施,而不仅仅是先前研究所做的排名变量,将为有效的利益相关者的行动定下基调并提供见解。该研究还通过概述如何在实践中实施这些发现,以实现对道路项目更准确的初步估计,弥合了理论和实践之间的差距。通过与每个集群的核心特征相一致的努力,可以提高准确性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Improving accuracy of road projects’ estimates in the Ghanaian construction industry
Purpose The inaccuracy of preliminary estimates sometimes results in wasted development effort if the project is abandoned. To curb this menace, this study aims to assess the different measures to improve the accuracy of road project estimates. Design/methodology/approach Quantitative research design was used for this study, and questionnaire was designed to retrieve data from the target population. Engineers and quantity surveyors in Accra, Ghana formed the target population and were contacted by using an e-questionnaire through their professional bodies owing to location constraints. Descriptive and exploratory factor analyses were used in analysing the retrieved data. Mann–Whitney U non-parametric test was also used to compare the opinions of the respondents. Findings The study revealed that factors categorised as due diligence by estimator should be given more attention for accuracy of estimates to be improved. Research limitations/implications This study was limited to Accra, Ghana owing to time and distance constraint. Practical implications Proper consideration must be given to preliminary site investigation when preparing the estimates for road projects. This will provide the estimator with information on the physical features of the project environment. Originality/value Defined clusters of measures to improve estimate accuracy as highlighted in this study rather than merely ranked variables which are done by previous research studies will set the tone and provide insights for effective stakeholders’ actions. The study also bridges the gap between theory and practice by outlining how the findings can be implemented practically to achieve more accurate preliminary estimate for road projects. With efforts aligned with the core characteristics of each cluster, accuracy can be improved.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
CiteScore
3.70
自引率
0.00%
发文量
17
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信