{"title":"公路工程延期及工期延长分析","authors":"M. Stoian, M. Dicu","doi":"10.1515/rjti-2017-0060","DOIUrl":null,"url":null,"abstract":"Abstract The implementation of road infrastructure projects often results in delays due to objective causes, with repercussions on the final execution deadline and with value implications. The use of critical path method for planning and the executin windows, will result in better time process management and optimization delays.","PeriodicalId":40630,"journal":{"name":"Romanian Journal of Transport Infrastructure","volume":"6 1","pages":"53 - 60"},"PeriodicalIF":0.1000,"publicationDate":"2017-12-01","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"Analysis of Delays and Extension of Execution Duration of a Road Project\",\"authors\":\"M. Stoian, M. Dicu\",\"doi\":\"10.1515/rjti-2017-0060\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Abstract The implementation of road infrastructure projects often results in delays due to objective causes, with repercussions on the final execution deadline and with value implications. The use of critical path method for planning and the executin windows, will result in better time process management and optimization delays.\",\"PeriodicalId\":40630,\"journal\":{\"name\":\"Romanian Journal of Transport Infrastructure\",\"volume\":\"6 1\",\"pages\":\"53 - 60\"},\"PeriodicalIF\":0.1000,\"publicationDate\":\"2017-12-01\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Romanian Journal of Transport Infrastructure\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1515/rjti-2017-0060\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"Q4\",\"JCRName\":\"ENGINEERING, CIVIL\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Romanian Journal of Transport Infrastructure","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1515/rjti-2017-0060","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"Q4","JCRName":"ENGINEERING, CIVIL","Score":null,"Total":0}
Analysis of Delays and Extension of Execution Duration of a Road Project
Abstract The implementation of road infrastructure projects often results in delays due to objective causes, with repercussions on the final execution deadline and with value implications. The use of critical path method for planning and the executin windows, will result in better time process management and optimization delays.