{"title":"影响埃及医疗机构超时的因素荟萃分析","authors":"Mona Gira, L. Khodeir, N. Elabd","doi":"10.21608/auej.2023.310352","DOIUrl":null,"url":null,"abstract":"Construction delays are a major issue in Egyptian construction projects. Delays are the costliest part, and finishing a project on schedule benefits all project partners. Healthcare facilities developments in Egypt, like all other construction projects, are usually delayed. Buildings for healthcare facilities are regarded as one of Egypt's most important construction projects. Therefore, it’s essential to study and analyze factors causing delays in these buildings’ construction. This study retrieved from the literature a list of delay factors in developing countries, especially Egypt. From 2000 to 2022, 127 relevant documents were discovered in Scopus and Web of Science databases and submitted to PRISMA protocol criteria. A list of factors was compiled from nine studies that met the effect summary analysis requirements. construction experts' feedback was obtained through interviews. This list was exposed to a questionnaire from experienced consulting engineers.Findings were compared to previous Egyptian researches. Accordingly, financial considerations, change orders, pricing variations and fluctuations, and a lack of contractor expertise were the most significant contributors.","PeriodicalId":131968,"journal":{"name":"Journal of Al-Azhar University Engineering Sector","volume":"116 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2023-07-31","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"META-ANALYSIS OF FACTORS AFFECTING TIME OVERRUN OF HEALTHCARE FACILITIES IN EGYPT\",\"authors\":\"Mona Gira, L. Khodeir, N. Elabd\",\"doi\":\"10.21608/auej.2023.310352\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Construction delays are a major issue in Egyptian construction projects. Delays are the costliest part, and finishing a project on schedule benefits all project partners. Healthcare facilities developments in Egypt, like all other construction projects, are usually delayed. Buildings for healthcare facilities are regarded as one of Egypt's most important construction projects. Therefore, it’s essential to study and analyze factors causing delays in these buildings’ construction. This study retrieved from the literature a list of delay factors in developing countries, especially Egypt. From 2000 to 2022, 127 relevant documents were discovered in Scopus and Web of Science databases and submitted to PRISMA protocol criteria. A list of factors was compiled from nine studies that met the effect summary analysis requirements. construction experts' feedback was obtained through interviews. This list was exposed to a questionnaire from experienced consulting engineers.Findings were compared to previous Egyptian researches. Accordingly, financial considerations, change orders, pricing variations and fluctuations, and a lack of contractor expertise were the most significant contributors.\",\"PeriodicalId\":131968,\"journal\":{\"name\":\"Journal of Al-Azhar University Engineering Sector\",\"volume\":\"116 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2023-07-31\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Journal of Al-Azhar University Engineering Sector\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.21608/auej.2023.310352\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Journal of Al-Azhar University Engineering Sector","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.21608/auej.2023.310352","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0
摘要
施工延误是埃及建筑项目的一个主要问题。延迟是成本最高的部分,按期完成项目对所有项目合作伙伴都有利。与所有其他建设项目一样,埃及的卫生保健设施发展通常会被推迟。医疗设施建筑被认为是埃及最重要的建筑项目之一。因此,有必要研究和分析造成这些建筑施工延误的因素。本研究从文献中检索了发展中国家,特别是埃及的延迟因素列表。从2000年到2022年,在Scopus和Web of Science数据库中发现了127篇相关文献,并提交给PRISMA协议标准。我们从9项符合效果总结分析要求的研究中编制了一份因素清单。通过访谈获得建筑专家的反馈。这份名单是由经验丰富的咨询工程师进行的问卷调查。研究结果与埃及之前的研究结果进行了比较。因此,财务考虑、变更订单、价格变化和波动以及缺乏承包商专门知识是最重要的因素。
META-ANALYSIS OF FACTORS AFFECTING TIME OVERRUN OF HEALTHCARE FACILITIES IN EGYPT
Construction delays are a major issue in Egyptian construction projects. Delays are the costliest part, and finishing a project on schedule benefits all project partners. Healthcare facilities developments in Egypt, like all other construction projects, are usually delayed. Buildings for healthcare facilities are regarded as one of Egypt's most important construction projects. Therefore, it’s essential to study and analyze factors causing delays in these buildings’ construction. This study retrieved from the literature a list of delay factors in developing countries, especially Egypt. From 2000 to 2022, 127 relevant documents were discovered in Scopus and Web of Science databases and submitted to PRISMA protocol criteria. A list of factors was compiled from nine studies that met the effect summary analysis requirements. construction experts' feedback was obtained through interviews. This list was exposed to a questionnaire from experienced consulting engineers.Findings were compared to previous Egyptian researches. Accordingly, financial considerations, change orders, pricing variations and fluctuations, and a lack of contractor expertise were the most significant contributors.