具有运行收益的工程项目时成本权衡问题

H. Li, H. Ouyang
{"title":"具有运行收益的工程项目时成本权衡问题","authors":"H. Li, H. Ouyang","doi":"10.1109/ICRMEM.2008.10","DOIUrl":null,"url":null,"abstract":"For an engineering project with running income, the result of time-cost trade-off problems (TCTP) concerning construction duration is only partly optimal. More cash flow happens during the running period, and the final goal of clients is to obtain the maximal profit across the lifecycle of engineering projects. In some situations, the cost of compressing construction duration even exceeds the increase of income of running period. Therefore, there should be an optimal scheme with the whole profit maximum. The relationship between the income of running period and the construction duration is analyzed in this paper; with the time value of capital taken into account, the mathematic model of TCTP across the running period is developed. Furthermore, the improved genetic algorithms (GA) proposed in this paper are applied to optimize the model. In the end, an example is given to testify the validity of the TCTP across the running period with the time value of capital considered.","PeriodicalId":430801,"journal":{"name":"2008 International Conference on Risk Management & Engineering Management","volume":"3 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2008-11-04","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"Time-Cost Trade-Off Problems of Engineering Project with Running Income\",\"authors\":\"H. Li, H. Ouyang\",\"doi\":\"10.1109/ICRMEM.2008.10\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"For an engineering project with running income, the result of time-cost trade-off problems (TCTP) concerning construction duration is only partly optimal. More cash flow happens during the running period, and the final goal of clients is to obtain the maximal profit across the lifecycle of engineering projects. In some situations, the cost of compressing construction duration even exceeds the increase of income of running period. Therefore, there should be an optimal scheme with the whole profit maximum. The relationship between the income of running period and the construction duration is analyzed in this paper; with the time value of capital taken into account, the mathematic model of TCTP across the running period is developed. Furthermore, the improved genetic algorithms (GA) proposed in this paper are applied to optimize the model. In the end, an example is given to testify the validity of the TCTP across the running period with the time value of capital considered.\",\"PeriodicalId\":430801,\"journal\":{\"name\":\"2008 International Conference on Risk Management & Engineering Management\",\"volume\":\"3 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2008-11-04\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2008 International Conference on Risk Management & Engineering Management\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/ICRMEM.2008.10\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2008 International Conference on Risk Management & Engineering Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/ICRMEM.2008.10","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

对于具有运行收益的工程项目,工期的时间成本权衡问题(TCTP)的结果仅是部分最优的。更多的现金流发生在运行期间,客户的最终目标是在工程项目的整个生命周期中获得最大的利润。在某些情况下,压缩工期的成本甚至超过了运行期收益的增长。因此,应该有一个整体利润最大的最优方案。分析了运行周期收益与工期之间的关系;考虑资本的时间价值,建立了跨运行周期的tcpp数学模型。在此基础上,采用改进的遗传算法对模型进行优化。最后,通过实例验证了考虑资金时间价值的tcp跨运行周期的有效性。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
Time-Cost Trade-Off Problems of Engineering Project with Running Income
For an engineering project with running income, the result of time-cost trade-off problems (TCTP) concerning construction duration is only partly optimal. More cash flow happens during the running period, and the final goal of clients is to obtain the maximal profit across the lifecycle of engineering projects. In some situations, the cost of compressing construction duration even exceeds the increase of income of running period. Therefore, there should be an optimal scheme with the whole profit maximum. The relationship between the income of running period and the construction duration is analyzed in this paper; with the time value of capital taken into account, the mathematic model of TCTP across the running period is developed. Furthermore, the improved genetic algorithms (GA) proposed in this paper are applied to optimize the model. In the end, an example is given to testify the validity of the TCTP across the running period with the time value of capital considered.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信