{"title":"马来西亚基础设施项目的现场施工生产率","authors":"S. Durdyev, S. Ismail","doi":"10.1108/SS-12-2015-0058","DOIUrl":null,"url":null,"abstract":"Purpose \n \n \n \n \nThe purpose of this paper is to examine the factors constraining the on-site construction productivity and measures for its improvement in Malaysian construction industry. \n \n \n \n \nDesign/methodology/approach \n \n \n \n \nQuestionnaire survey is administered to 171 respondents, comprising government authorities and construction players. A total of 39 constraints are found to be significant factors in various risk levels. \n \n \n \n \nFindings \n \n \n \n \nConsequently, improvement measures are recommended addressing those constraints to on-site construction productivity. It is believed that the findings of this study will assist in achieving high level of on-site construction productivity by focusing and acting upon the most risky constraints, where construction players in Malaysia could be guided well in their efforts in a time-, cost- and quality-effective manner. \n \n \n \n \nOriginality/value \n \n \n \n \nIt is believed that the findings of this study will assist in achieving high level of on-site construction productivity by focusing and acting upon the most risky constraints, where construction players in Malaysia could be guided well in their efforts in a time-, cost- and quality-effective manner.","PeriodicalId":118605,"journal":{"name":"Structural Survey","volume":"50 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2016-08-08","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"61","resultStr":"{\"title\":\"On-site construction productivity in Malaysian infrastructure projects\",\"authors\":\"S. Durdyev, S. Ismail\",\"doi\":\"10.1108/SS-12-2015-0058\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Purpose \\n \\n \\n \\n \\nThe purpose of this paper is to examine the factors constraining the on-site construction productivity and measures for its improvement in Malaysian construction industry. \\n \\n \\n \\n \\nDesign/methodology/approach \\n \\n \\n \\n \\nQuestionnaire survey is administered to 171 respondents, comprising government authorities and construction players. A total of 39 constraints are found to be significant factors in various risk levels. \\n \\n \\n \\n \\nFindings \\n \\n \\n \\n \\nConsequently, improvement measures are recommended addressing those constraints to on-site construction productivity. It is believed that the findings of this study will assist in achieving high level of on-site construction productivity by focusing and acting upon the most risky constraints, where construction players in Malaysia could be guided well in their efforts in a time-, cost- and quality-effective manner. \\n \\n \\n \\n \\nOriginality/value \\n \\n \\n \\n \\nIt is believed that the findings of this study will assist in achieving high level of on-site construction productivity by focusing and acting upon the most risky constraints, where construction players in Malaysia could be guided well in their efforts in a time-, cost- and quality-effective manner.\",\"PeriodicalId\":118605,\"journal\":{\"name\":\"Structural Survey\",\"volume\":\"50 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2016-08-08\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"61\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Structural Survey\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1108/SS-12-2015-0058\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Structural Survey","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1108/SS-12-2015-0058","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
On-site construction productivity in Malaysian infrastructure projects
Purpose
The purpose of this paper is to examine the factors constraining the on-site construction productivity and measures for its improvement in Malaysian construction industry.
Design/methodology/approach
Questionnaire survey is administered to 171 respondents, comprising government authorities and construction players. A total of 39 constraints are found to be significant factors in various risk levels.
Findings
Consequently, improvement measures are recommended addressing those constraints to on-site construction productivity. It is believed that the findings of this study will assist in achieving high level of on-site construction productivity by focusing and acting upon the most risky constraints, where construction players in Malaysia could be guided well in their efforts in a time-, cost- and quality-effective manner.
Originality/value
It is believed that the findings of this study will assist in achieving high level of on-site construction productivity by focusing and acting upon the most risky constraints, where construction players in Malaysia could be guided well in their efforts in a time-, cost- and quality-effective manner.