工厂工程中复杂交钥匙工程控制的优化模型

E. Mueller, R. Riedel, M. Krones, Henrik Vay
{"title":"工厂工程中复杂交钥匙工程控制的优化模型","authors":"E. Mueller, R. Riedel, M. Krones, Henrik Vay","doi":"10.1109/IEEM.2011.6118041","DOIUrl":null,"url":null,"abstract":"Turnkey plant projects are endeavors which are characterized by high complexity and system dynamics. The application of special methods and models in the project management processes of planning and monitoring & controlling has become a competitive advantage in turnkey plant business. Special attention has to be given to the identification and evaluation of changes and disturbances as those could have severe impacts on the project`s objectives. The selection and implementation of proper control measures becomes crucial to ensure successful projects. In this paper a novel approach for modeling the interdependencies of engineering activities is presented. The approach particularly addresses planning information and changes that will limit the effects of control measures in the case of possible delays. The modeling approach offers decision support by providing a holistic basis for the evaluation of changes.","PeriodicalId":427457,"journal":{"name":"2011 IEEE International Conference on Industrial Engineering and Engineering Management","volume":"421 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2011-12-29","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"1","resultStr":"{\"title\":\"An optimization model for the control of complex turnkey projects in plant engineering\",\"authors\":\"E. Mueller, R. Riedel, M. Krones, Henrik Vay\",\"doi\":\"10.1109/IEEM.2011.6118041\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"Turnkey plant projects are endeavors which are characterized by high complexity and system dynamics. The application of special methods and models in the project management processes of planning and monitoring & controlling has become a competitive advantage in turnkey plant business. Special attention has to be given to the identification and evaluation of changes and disturbances as those could have severe impacts on the project`s objectives. The selection and implementation of proper control measures becomes crucial to ensure successful projects. In this paper a novel approach for modeling the interdependencies of engineering activities is presented. The approach particularly addresses planning information and changes that will limit the effects of control measures in the case of possible delays. The modeling approach offers decision support by providing a holistic basis for the evaluation of changes.\",\"PeriodicalId\":427457,\"journal\":{\"name\":\"2011 IEEE International Conference on Industrial Engineering and Engineering Management\",\"volume\":\"421 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2011-12-29\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"1\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"2011 IEEE International Conference on Industrial Engineering and Engineering Management\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.1109/IEEM.2011.6118041\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"2011 IEEE International Conference on Industrial Engineering and Engineering Management","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.1109/IEEM.2011.6118041","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 1

摘要

交钥匙工厂项目具有高复杂性和系统动态性的特点。在项目管理过程中运用特殊的方法和模型进行计划和监控已成为交钥匙工厂业务的竞争优势。必须特别注意识别和评价可能对项目目标产生严重影响的变化和干扰。选择和实施适当的控制措施是确保项目成功的关键。本文提出了一种新的工程活动相互依赖关系建模方法。这种方法特别涉及规划资料和变更,在可能出现延误的情况下,这些资料和变更将限制控制措施的效果。建模方法通过为变更评估提供整体基础来提供决策支持。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
An optimization model for the control of complex turnkey projects in plant engineering
Turnkey plant projects are endeavors which are characterized by high complexity and system dynamics. The application of special methods and models in the project management processes of planning and monitoring & controlling has become a competitive advantage in turnkey plant business. Special attention has to be given to the identification and evaluation of changes and disturbances as those could have severe impacts on the project`s objectives. The selection and implementation of proper control measures becomes crucial to ensure successful projects. In this paper a novel approach for modeling the interdependencies of engineering activities is presented. The approach particularly addresses planning information and changes that will limit the effects of control measures in the case of possible delays. The modeling approach offers decision support by providing a holistic basis for the evaluation of changes.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:604180095
Book学术官方微信