{"title":"土工模型在管理操作土工风险中的快速整合作用","authors":"MC Brockman, Kmr Gosche, D. D. Plooy","doi":"10.36487/ACG_REP/1905_24_BROCKMAN","DOIUrl":null,"url":null,"abstract":"AngloGold Ashanti (AGA) has developed a concept to integrate geotechnical input into long-term mine planning using a ‘block model approach’ referred to as a geotechnical model for rapid integration (GMRi). The GMRi is a simple spatial collection of rock mass data integrated with empirical evaluations, numerical modelling results and monitoring data for a specific mine plan. In this paper, the value of using the GMRi to manage geotechnical risk and identify opportunities associated with ground support design, stress-induced damage, design stope spans and total extraction is demonstrated. The GMRi concept allows for the rapid evaluation of spatially distributed geotechnical data and identifies areas of risk and opportunity, demonstrated at two recent underground studies completed at AGA’s Australian operations.","PeriodicalId":337751,"journal":{"name":"Proceedings of the First International Conference on Mining Geomechanical Risk","volume":"138 1","pages":"0"},"PeriodicalIF":0.0000,"publicationDate":"2019-04-09","publicationTypes":"Journal Article","fieldsOfStudy":null,"isOpenAccess":false,"openAccessPdf":"","citationCount":"0","resultStr":"{\"title\":\"The role of the geotechnical model for rapid integration in managing operational geotechnical risk\",\"authors\":\"MC Brockman, Kmr Gosche, D. D. Plooy\",\"doi\":\"10.36487/ACG_REP/1905_24_BROCKMAN\",\"DOIUrl\":null,\"url\":null,\"abstract\":\"AngloGold Ashanti (AGA) has developed a concept to integrate geotechnical input into long-term mine planning using a ‘block model approach’ referred to as a geotechnical model for rapid integration (GMRi). The GMRi is a simple spatial collection of rock mass data integrated with empirical evaluations, numerical modelling results and monitoring data for a specific mine plan. In this paper, the value of using the GMRi to manage geotechnical risk and identify opportunities associated with ground support design, stress-induced damage, design stope spans and total extraction is demonstrated. The GMRi concept allows for the rapid evaluation of spatially distributed geotechnical data and identifies areas of risk and opportunity, demonstrated at two recent underground studies completed at AGA’s Australian operations.\",\"PeriodicalId\":337751,\"journal\":{\"name\":\"Proceedings of the First International Conference on Mining Geomechanical Risk\",\"volume\":\"138 1\",\"pages\":\"0\"},\"PeriodicalIF\":0.0000,\"publicationDate\":\"2019-04-09\",\"publicationTypes\":\"Journal Article\",\"fieldsOfStudy\":null,\"isOpenAccess\":false,\"openAccessPdf\":\"\",\"citationCount\":\"0\",\"resultStr\":null,\"platform\":\"Semanticscholar\",\"paperid\":null,\"PeriodicalName\":\"Proceedings of the First International Conference on Mining Geomechanical Risk\",\"FirstCategoryId\":\"1085\",\"ListUrlMain\":\"https://doi.org/10.36487/ACG_REP/1905_24_BROCKMAN\",\"RegionNum\":0,\"RegionCategory\":null,\"ArticlePicture\":[],\"TitleCN\":null,\"AbstractTextCN\":null,\"PMCID\":null,\"EPubDate\":\"\",\"PubModel\":\"\",\"JCR\":\"\",\"JCRName\":\"\",\"Score\":null,\"Total\":0}","platform":"Semanticscholar","paperid":null,"PeriodicalName":"Proceedings of the First International Conference on Mining Geomechanical Risk","FirstCategoryId":"1085","ListUrlMain":"https://doi.org/10.36487/ACG_REP/1905_24_BROCKMAN","RegionNum":0,"RegionCategory":null,"ArticlePicture":[],"TitleCN":null,"AbstractTextCN":null,"PMCID":null,"EPubDate":"","PubModel":"","JCR":"","JCRName":"","Score":null,"Total":0}
引用次数: 0

摘要

AngloGold Ashanti (AGA)开发了一种概念,使用“块模型方法”将岩土工程投入整合到长期矿山规划中,称为快速集成岩土工程模型(GMRi)。GMRi是一个简单的岩体数据空间集合,结合了经验评价、数值模拟结果和特定矿山方案的监测数据。本文论证了使用GMRi来管理岩土工程风险和识别与地面支撑设计、应力诱发损伤、设计采场跨度和总开采相关的机会的价值。GMRi概念允许对空间分布的岩土技术数据进行快速评估,并确定风险和机会区域,最近在AGA澳大利亚业务中完成的两项地下研究证明了这一点。
本文章由计算机程序翻译,如有差异,请以英文原文为准。
The role of the geotechnical model for rapid integration in managing operational geotechnical risk
AngloGold Ashanti (AGA) has developed a concept to integrate geotechnical input into long-term mine planning using a ‘block model approach’ referred to as a geotechnical model for rapid integration (GMRi). The GMRi is a simple spatial collection of rock mass data integrated with empirical evaluations, numerical modelling results and monitoring data for a specific mine plan. In this paper, the value of using the GMRi to manage geotechnical risk and identify opportunities associated with ground support design, stress-induced damage, design stope spans and total extraction is demonstrated. The GMRi concept allows for the rapid evaluation of spatially distributed geotechnical data and identifies areas of risk and opportunity, demonstrated at two recent underground studies completed at AGA’s Australian operations.
求助全文
通过发布文献求助,成功后即可免费获取论文全文。 去求助
来源期刊
自引率
0.00%
发文量
0
×
引用
GB/T 7714-2015
复制
MLA
复制
APA
复制
导出至
BibTeX EndNote RefMan NoteFirst NoteExpress
×
提示
您的信息不完整,为了账户安全,请先补充。
现在去补充
×
提示
您因"违规操作"
具体请查看互助需知
我知道了
×
提示
确定
请完成安全验证×
copy
已复制链接
快去分享给好友吧!
我知道了
右上角分享
点击右上角分享
0
联系我们:info@booksci.cn Book学术提供免费学术资源搜索服务,方便国内外学者检索中英文文献。致力于提供最便捷和优质的服务体验。 Copyright © 2023 布克学术 All rights reserved.
京ICP备2023020795号-1
ghs 京公网安备 11010802042870号
Book学术文献互助
Book学术文献互助群
群 号:481959085
Book学术官方微信